1360 E 110TH ST 90059

Certificate Information: 1360 E 110TH ST 90059

Application / Permit
19010-20000-02270
Plan Check / Job No.
B19VN08876
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 59' X 19' ONE STORY SFD WITH 19' X 10' ATTACHED GARAGE , NFPA-13D FIRE SPRINKLERS REQUIRED, ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/22/2019
Issuing Office
Metro
Current Status
CofO Issued on 7/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2019 APPLICANT
Assigned to Plan Check Engineer 6/20/2019 RARES BODEA
Corrections Issued 6/22/2019 RARES BODEA
Quality Review Completed 6/28/2019 OMID HEDAYAT
Building Plans Picked Up 6/28/2019 APPLICANT
Green Plans Picked Up 6/28/2019 APPLICANT
Plan Check Approved 8/15/2019 RARES BODEA
Issued 8/22/2019 LADBS
CofO in Progress 5/1/2020 EUGENE CASSIDY
CofO in Progress 5/4/2020 EUGENE CASSIDY
No Progress 6/24/2020 BOB DUNN
CofO in Progress 7/2/2020 BOB DUNN
Permit Finaled 7/2/2020 BOB DUNN
CofO Issued 7/2/2020 BOB DUNN
Permit Finaled 7/2/2020 BOB DUNN

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 7/30/2019 JOHN KIM
Community Plan Implem. Overlay Cleared 7/30/2019 SARAHI ORTEGA
Permit Cleared 7/30/2019 ERIK BEASLEY
Trees in Parkway Cleared 8/2/2019 JOHN KIM
Green Code Cleared 8/8/2019 PARISA ZAHABI
Address approval Cleared 8/13/2019 JEANETTE VONG
Community Plan Implem. Overlay Cleared 8/13/2019 JEANETTE VONG
Community Plan Implem. Overlay Cleared 8/13/2019 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 8/13/2019 JEANETTE VONG
Hydrant and Access approval Cleared 8/13/2019 GILBERT URREA
Low Impact Development Cleared 8/13/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/13/2019 JEANETTE VONG
Sewer availability Cleared 8/13/2019 JEANETTE VONG

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B 9214 MANZANAR AVE      DOWNEY, CA 90240
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 26851 GRAYSLAKE ROAD      RANCHO PALOS VERDES, CA 90275

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2019 Corrections Issued WILLIAM ROSE
Sewer 9/9/2019 Approved WILLIAM ROSE
Underground Mechanical 9/9/2019 Not Ready for Inspection WILLIAM ROSE
Excavation/Setback/Form/Re-Bar 9/18/2019 Partial Approval WILLIAM ROSE
PLUMBING-Rough 9/18/2019 Partial Approval WILLIAM ROSE
Footing/Foundation/Slab 9/30/2019 Approved WILLIAM ROSE
BUILDING-Rough-Frame 11/6/2019 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/6/2019 Partial Approval EUGENE CASSIDY
Green Building Rough 11/6/2019 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 11/6/2019 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/8/2019 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 11/26/2019 Conditional Approval WILLIAM ROSE
ELECTRICAL-Rough 11/26/2019 Corrections Issued WILLIAM ROSE
HVAC-Rough 11/26/2019 Approved WILLIAM ROSE
PLUMBING-Rough 11/26/2019 Approved WILLIAM ROSE
Verify Sprinkler Sign Off 11/26/2019 Not Ready for Inspection WILLIAM ROSE
BUILDING-Rough-Frame 12/6/2019 Approved WILLIAM ROSE
ELECTRICAL-Rough 12/6/2019 Approved WILLIAM ROSE
Insulation 12/6/2019 Approved WILLIAM ROSE
PLUMBING-Rough 12/6/2019 Approved WILLIAM ROSE
Verify Sprinkler Sign Off 12/6/2019 Approved WILLIAM ROSE
Drywall Nailing 12/11/2019 Approved WILLIAM ROSE
Interior/Exterior Lathing 12/11/2019 Approved WILLIAM ROSE
Final 3/25/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 3/25/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/25/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 3/25/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 3/25/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/31/2020 Approved EUGENE CASSIDY
Final 3/31/2020 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 3/31/2020 Approved EUGENE CASSIDY
PLUMBING-Final 3/31/2020 Approved EUGENE CASSIDY
Service/Power Release 3/31/2020 Not Ready for Inspection EUGENE CASSIDY
Final 4/17/2020 Corrections Issued EUGENE CASSIDY
Service/Power Release 4/17/2020 Not Ready for Inspection EUGENE CASSIDY
Final 4/30/2020 OK to Issue CofO EUGENE CASSIDY
Service/Power Release 4/30/2020 Approved EUGENE CASSIDY
Final 5/4/2020 OK to Issue CofO EUGENE CASSIDY