11870 W WEIR ST 90230
Certificate Information: 11870 W WEIR ST 90230
- Application / Permit
- 19010-20000-02243
- Plan Check / Job No.
- B19VN08749
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 16'-3"x 13'-8" ONE STORY DETACHED ACCESSORY DWELLING UNIT. WORK PER AB 494 AND SB 229. WORK PER ENGINEER.
- Permit Issued
- Issued on 10/3/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2019 | APPLICANT |
| Green Plans Picked Up | 6/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | TROY DEGUZMAN |
| Corrections Issued | 6/18/2019 | TROY DEGUZMAN |
| Quality Review Completed | 6/20/2019 | STEVEN KIM |
| Building Plans Picked Up | 6/20/2019 | APPLICANT |
| Applicant returned to address corrections | 8/13/2019 | TROY DEGUZMAN |
| Plan Check Approved | 10/2/2019 | TROY DEGUZMAN |
| Issued | 10/3/2019 | LADBS |
| CofO in Progress | 3/11/2021 | DAVID HEINE |
| CofO Issued | 3/23/2021 | VINCENT COTTON |
| Permit Finaled | 3/23/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/19/2019 | ORVAL HERNANDEZ-MARCI |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 7/22/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 7/22/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 7/24/2019 | GEORGE SUCHAND |
| ZI | Cleared | 7/24/2019 | RINA LARA |
| Green Code | Cleared | 7/26/2019 | MICHAEL AYERS |
| Construction near power lines | Cleared | 9/18/2019 | RIDWAN HARDY |
| Address approval | Cleared | 10/1/2019 | SAFA JAVANMARDI |
Contact Information
| Contractor | Gold Lion Construction Inc; Lic. No.: 1014010-B | 2657 MALCOLM AVENUE LOS ANGELES, CA 90064 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 6270 MCLEOD DR STE 140 LAS VEGAS, NV 89120 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/23/2019 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 11/1/2019 | Partial Inspection | KENNETH NAGLE |
| METHANE-Barrier | 11/1/2019 | Approved | KENNETH NAGLE |
| METHANE-Subgrade | 11/1/2019 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2020 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 1/30/2020 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 2/5/2020 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 2/11/2020 | No Access for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 2/19/2020 | No Access for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 2/28/2020 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 3/6/2020 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 3/6/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2020 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 3/6/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 3/6/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 3/6/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 3/6/2020 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/12/2020 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/13/2020 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/27/2020 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 3/27/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 3/27/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 3/27/2020 | Approved | JOHNNY MIRANDA |
| METHANE-Rough | 3/27/2020 | Approved | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 3/27/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/29/2020 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 4/29/2020 | Approved | JOHNNY MIRANDA |
| Insulation | 4/29/2020 | Corrections Issued | JOHNNY MIRANDA |
| Insulation | 5/4/2020 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 5/8/2020 | Approved | JUAN VALENZUELA |
| Gas Test | 10/6/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 10/13/2020 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 10/26/2020 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Final | 10/28/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 10/28/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 11/4/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 11/9/2020 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 11/9/2020 | Approved | JOHNNY MIRANDA |
| Green Building Final | 11/9/2020 | Corrections Issued | JOHNNY MIRANDA |
| MERV13>=Final | 11/9/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 11/9/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/9/2020 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 11/9/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Smoke Detectors | 11/9/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 11/12/2020 | Approved | JOHNNY MIRANDA |
| Green Building Final | 11/16/2020 | Approved | JOHNNY MIRANDA |
| Final | 11/30/2020 | Partial Approval | JOHNNY MIRANDA |
| Service/Power Release | 11/30/2020 | Approved | JOHNNY MIRANDA |
| Final | 12/2/2020 | Partial Approval | JOHNNY MIRANDA |
| Final | 3/11/2021 | OK to Issue CofO | DAVID HEINE |