21906 W VELICATA ST 91364

Certificate Information: 21906 W VELICATA ST 91364

Application / Permit
19010-20000-02230
Plan Check / Job No.
B19VN08682
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 39'-0" X 23'-8" ACCESSORY DWELLING UNIT PER AB 494 & SB 229.
Permit Issued
Issued on 6/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 ARTIN ZARUKIAN
Green Plans Picked Up 7/3/2019 APPLICANT
Corrections Issued 7/8/2019 ARTIN ZARUKIAN
Quality Review Completed 7/16/2019 CHON CHIO KUO
Building Plans Picked Up 7/26/2019 APPLICANT
Applicant returned to address corrections 8/16/2019 ARTIN ZARUKIAN
Plan Check Approved 8/22/2019 ARTIN ZARUKIAN
Issued 6/9/2020 LADBS
CofO in Progress 11/20/2020 VINCENT HANLEY
CofO Issued 11/23/2020 MICHAEL SMITH
Permit Finaled 11/23/2020 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 7/31/2019 RIDWAN HARDY
Address approval Cleared 8/2/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/5/2019 GUILLERMO PETRA
Sewer availability Cleared 8/5/2019 GUILLERMO PETRA
Green Code Cleared 8/9/2019 MICHAEL AYERS
Low Impact Development Cleared 8/13/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/13/2019 APEKSHYA BAJRACHARYA
GPI Written Notices Cleared 8/16/2019 ARTIN ZARUKIAN
Grading Pre-Inspection Cleared 8/16/2019 ARTIN ZARUKIAN
Hydrant and Access approval Cleared 8/22/2019 GILBERT URREA

Contact Information

Contractor R L Remodeling Inc; Lic. No.: 885032-B 22817 VENTURA BLVD #852      WOODLAND HILLS, CA 91364
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/10/2020 Partial Approval MICHAEL TEMPLE
Footing/Foundation/Slab 6/17/2020 Corrections Issued DONALD SUNSERI
Footing/Foundation/Slab 6/19/2020 Approved DONALD SUNSERI
BUILDING-Rough-Frame 8/3/2020 Partial Approval DONALD SUNSERI
ELECTRICAL-Rough 8/3/2020 Not Ready for Inspection DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 8/3/2020 Approved DONALD SUNSERI
Green Building Rough 8/3/2020 Not Ready for Inspection DONALD SUNSERI
PLUMBING-Rough 8/3/2020 Not Ready for Inspection DONALD SUNSERI
Wood Frame 8/3/2020 Partial Approval DONALD SUNSERI
ELECTRICAL-Rough 8/12/2020 Approved DONALD SUNSERI
PLUMBING-Rough 8/12/2020 Approved DONALD SUNSERI
BUILDING-Rough-Frame 8/14/2020 Approved DONALD SUNSERI
Green Building Rough 8/14/2020 Approved DONALD SUNSERI
Drywall Nailing 8/24/2020 Approved DAVID SANDOVAL
Interior/Exterior Lathing 8/24/2020 Approved DAVID SANDOVAL
Shower Pan 8/24/2020 Approved DAVID SANDOVAL
Final 10/5/2020 Not Ready for Inspection DAVID SANDOVAL
Green Building Final 10/5/2020 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 10/5/2020 SGSOV Not Ready DAVID SANDOVAL
Service/Power Release 10/5/2020 Not Ready for Inspection DAVID SANDOVAL
Smoke Detectors 10/5/2020 Approved DAVID SANDOVAL
Final 11/16/2020 Corrections Issued DAVID SANDOVAL
Green Building Final 11/16/2020 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 11/16/2020 SGSOV Approved DAVID SANDOVAL
Service/Power Release 11/16/2020 Not Ready for Inspection DAVID SANDOVAL
Final 11/20/2020 OK to Issue CofO VINCENT HANLEY
Green Building Final 11/20/2020 Approved VINCENT HANLEY
Service/Power Release 11/20/2020 Not Required VINCENT HANLEY