9413 N FARRALONE AVE 91311
Certificate Information: 9413 N FARRALONE AVE 91311
- Application / Permit
- 19010-20000-02229
- Plan Check / Job No.
- B19VN08680
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20'-0" X 24'-0" DETACHED ACCESSORY DWELLING UNIT PER AB494 AND SB229. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 7/22/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2019 | APPLICANT |
| Green Plans Picked Up | 6/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | ROSENDO MEDINA |
| Corrections Issued | 7/9/2019 | ROSENDO MEDINA |
| Quality Review Completed | 7/15/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 7/16/2019 | APPLICANT |
| Applicant returned to address corrections | 10/30/2019 | ROSENDO MEDINA |
| Plan Check Approved | 7/22/2020 | ROSENDO MEDINA |
| Issued | 7/22/2020 | APPLICANT |
| CofO in Progress | 3/12/2021 | DAVID STEPANYAN |
| Permit Finaled | 3/16/2021 | JOHN JANSON |
| CofO Issued | 3/16/2021 | JOHN JANSON |
| Permit Finaled | 3/16/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2019 | SAFA JAVANMARDI |
| ZA Case | Cleared | 7/16/2019 | DAISY BENICIA |
| ZA Case | Cleared | 7/16/2019 | DAISY BENICIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 7/18/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/18/2019 | GUILLERMO PETRA |
| Specific Plan | Cleared | 7/22/2019 | CHRISTINE BUSTILLOS |
| Green Code | Cleared | 7/30/2019 | AARON COSTA |
| Hydrant and Access approval | Cleared | 7/30/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 8/27/2019 | ORVAL HERNANDEZ-MARCI |
| Grading Pre-Inspection | Cleared | 5/12/2020 | ROSENDO MEDINA |
| Disturb/Remove Protected Trees | Cleared | 6/30/2020 | STEPHEN DUPREY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2020 | Corrections Issued | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 9/4/2020 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 9/14/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 10/6/2020 | Corrections Issued | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 10/6/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 10/6/2020 | Approved | DAVID STEPANYAN |
| Verify Sprinkler Sign Off | 10/6/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/16/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 10/16/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 10/16/2020 | Approved | DAVID STEPANYAN |
| Sewer | 10/16/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 10/16/2020 | Approved | DAVID STEPANYAN |
| Verify Sprinkler Sign Off | 10/16/2020 | Approved | DAVID STEPANYAN |
| Insulation | 10/27/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 11/2/2020 | Approved | DAVID STEPANYAN |
| Final | 1/4/2021 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 1/4/2021 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 1/4/2021 | SGSOV Approved | DAVID STEPANYAN |
| Service/Power Release | 1/4/2021 | Not Required | DAVID STEPANYAN |
| Smoke Detectors | 1/4/2021 | Approved | DAVID STEPANYAN |
| Green Building Final | 2/24/2021 | Approved | DAVID STEPANYAN |
| HVAC-Final | 2/24/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 2/24/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 3/11/2021 | Approved | DAVID STEPANYAN |
| Final | 3/11/2021 | OK to Issue CofO | DAVID STEPANYAN |