6838 N BEVIS AVE 91405
Certificate Information: 6838 N BEVIS AVE 91405
- Application / Permit
- 19010-20000-02217
- Plan Check / Job No.
- B19VN08631
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW Two-story (20'x27.5') Accessory Dwelling Unit per AB 494 AND SB 229.
- Permit Issued
- Issued on 11/1/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2019 | APPLICANT |
| Green Plans Picked Up | 7/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | LUIS RINCON |
| Corrections Issued | 7/15/2019 | LUIS RINCON |
| Quality Review Completed | 7/18/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 7/22/2019 | APPLICANT |
| Plan Check Approved | 10/7/2019 | LUIS RINCON |
| Issued | 11/1/2019 | LADBS |
| CofO in Progress | 2/4/2022 | RICHARD DOCKUS |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
| CofO Issued | 4/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/19/2019 | ORVAL HERNANDEZ-MARCI |
| Green Code | Cleared | 8/15/2019 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 9/3/2019 | JOHN CONNEALLY |
| Address approval | Cleared | 9/6/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 9/6/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 9/6/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 9/9/2019 | RIDWAN HARDY |
| Hold | Cleared | 4/5/2021 | LOURDES RAMIRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James W; Lic. No.: C43590 | 15315 BLEDSOE ST SYLMAR, CA 91342 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/14/2021 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/23/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/4/2021 | Partial Approval | ARTHUR SARGSYAN |
| Green Building Rough | 5/4/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Verify Sprinkler Sign Off | 5/4/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2021 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/19/2021 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2021 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2021 | Corrections Issued | MARK JOHNSON |
| BUILDING-Rough-Frame | 6/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/8/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/8/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/13/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/13/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/13/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 8/13/2021 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 8/23/2021 | Approved | RICHARD DOCKUS |
| Insulation | 8/25/2021 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 9/1/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 9/7/2021 | No Access for Inspection | MISAEL ESPARZA |
| Sewer | 10/12/2021 | Corrections Issued | ALAN MORELOS |
| Sewer | 10/15/2021 | Approved | ALAN MORELOS |
| Underground Mechanical | 10/15/2021 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 10/26/2021 | Corrections Issued | RICHARD DOCKUS |
| Final | 10/26/2021 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 10/26/2021 | Approved | RICHARD DOCKUS |
| HVAC-Final | 10/26/2021 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Final | 10/26/2021 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 10/26/2021 | SGSOV Approved | RICHARD DOCKUS |
| Service/Power Release | 10/26/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 10/26/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 11/23/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Service/Power Release | 11/23/2021 | Corrections Issued | RICHARD DOCKUS |
| Final | 11/30/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Service/Power Release | 11/30/2021 | Corrections Issued | MICHAEL TEMPLE |
| Final | 12/6/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Service/Power Release | 12/6/2021 | Corrections Issued | RICHARD DOCKUS |
| Final | 2/3/2022 | OK to Issue CofO | RICHARD DOCKUS |
| Service/Power Release | 2/3/2022 | Approved | RICHARD DOCKUS |