6838 N BEVIS AVE 91405

Certificate Information: 6838 N BEVIS AVE 91405

Application / Permit
19010-20000-02217
Plan Check / Job No.
B19VN08631
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW Two-story (20'x27.5') Accessory Dwelling Unit per AB 494 AND SB 229.
Permit Issued
Issued on 11/1/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2019 APPLICANT
Green Plans Picked Up 7/1/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 LUIS RINCON
Corrections Issued 7/15/2019 LUIS RINCON
Quality Review Completed 7/18/2019 OMID HEDAYAT
Building Plans Picked Up 7/22/2019 APPLICANT
Plan Check Approved 10/7/2019 LUIS RINCON
Issued 11/1/2019 LADBS
CofO in Progress 2/4/2022 RICHARD DOCKUS
Permit Finaled 4/2/2022 DEROLD HAUFF
Permit Finaled 4/2/2022 DEROLD HAUFF
CofO Issued 4/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 7/19/2019 ORVAL HERNANDEZ-MARCI
Green Code Cleared 8/15/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 9/3/2019 JOHN CONNEALLY
Address approval Cleared 9/6/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 9/6/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 9/6/2019 GUILLERMO PETRA
Sewer availability Cleared 9/6/2019 GUILLERMO PETRA
Construction near power lines Cleared 9/9/2019 RIDWAN HARDY
Hold Cleared 4/5/2021 LOURDES RAMIRO

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/14/2021 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 4/23/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/4/2021 Partial Approval ARTHUR SARGSYAN
Green Building Rough 5/4/2021 Not Ready for Inspection ARTHUR SARGSYAN
Verify Sprinkler Sign Off 5/4/2021 Not Ready for Inspection ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 5/19/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/19/2021 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/27/2021 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 6/8/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/8/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 6/8/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/8/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/13/2021 Approved JENNIFER RABUCHIN
Green Building Rough 8/13/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 8/13/2021 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 8/13/2021 Approved JENNIFER RABUCHIN
Shower Pan 8/23/2021 Approved RICHARD DOCKUS
Insulation 8/25/2021 Approved RICHARD DOCKUS
Drywall Nailing 9/1/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 9/7/2021 No Access for Inspection MISAEL ESPARZA
Sewer 10/12/2021 Corrections Issued ALAN MORELOS
Sewer 10/15/2021 Approved ALAN MORELOS
Underground Mechanical 10/15/2021 Approved ALAN MORELOS
ELECTRICAL-Final 10/26/2021 Corrections Issued RICHARD DOCKUS
Final 10/26/2021 Corrections Issued RICHARD DOCKUS
Green Building Final 10/26/2021 Approved RICHARD DOCKUS
HVAC-Final 10/26/2021 Corrections Issued RICHARD DOCKUS
PLUMBING-Final 10/26/2021 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Approved RICHARD DOCKUS
Service/Power Release 10/26/2021 Not Ready for Inspection RICHARD DOCKUS
Smoke Detectors 10/26/2021 Approved RICHARD DOCKUS
ELECTRICAL-Final 11/23/2021 Not Ready for Inspection RICHARD DOCKUS
Service/Power Release 11/23/2021 Corrections Issued RICHARD DOCKUS
Final 11/30/2021 Not Ready for Inspection MICHAEL TEMPLE
Service/Power Release 11/30/2021 Corrections Issued MICHAEL TEMPLE
Final 12/6/2021 Not Ready for Inspection RICHARD DOCKUS
Service/Power Release 12/6/2021 Corrections Issued RICHARD DOCKUS
Final 2/3/2022 OK to Issue CofO RICHARD DOCKUS
Service/Power Release 2/3/2022 Approved RICHARD DOCKUS