10950 N WINNETKA AVE 91311
Certificate Information: 10950 N WINNETKA AVE 91311
- Application / Permit
- 19010-20000-02210
- Plan Check / Job No.
- B19VN08615
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 30' x 40' Recreational Room, with a 10' x 40 trellis patio cover.
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- Issued on 7/22/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/24/2019 | APPLICANT |
| Green Plans Picked Up | 6/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | LUIS RINCON |
| Corrections Issued | 7/17/2019 | LUIS RINCON |
| Quality Review Completed | 7/18/2019 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/23/2021 | LUIS RINCON |
| Applicant returned to address corrections | 1/19/2022 | LUIS RINCON |
| Applicant returned to address corrections | 3/15/2022 | LUIS RINCON |
| Plan Check Approved | 5/16/2022 | LUIS RINCON |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| Issued | 7/22/2022 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 7/30/2019 | AARON COSTA |
| BHO/Hillside ordinance | Cleared | 8/19/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 8/19/2019 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 8/19/2019 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 8/19/2019 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 8/19/2019 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 8/19/2019 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 8/19/2019 | MARITZA PRZEKOP |
| ZI | Cleared | 8/19/2019 | MARITZA PRZEKOP |
| Hydrant and Access approval | Cleared | 8/27/2019 | GILBERT URREA |
| Private sewage disp. approval | Cleared | 3/8/2021 | DAN RYAN EVANGELISTA |
| Low Impact Development | Cleared | 9/22/2021 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/1/2021 | CARLOS AGUILERA |
| Private sewage disp. approval | Cleared | 2/1/2022 | DAN RYAN EVANGELISTA |
| Grading Pre-Inspection | Cleared | 5/16/2022 | LUIS RINCON |
Contact Information
| Contractor | Treeium Inc; Lic. No.: 617148-B | 5352 LAUREL CANYON BLVD #200 VALLEY VILLAGE, CA 91607 |
| Engineer | Rolin,, Kenneth Wayne; Lic. No.: C23471 | 2031 SEA OAK LN ARROYO GRANDE, CA 93420 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/1/2023 | Approved | SEAN HAUPT |
| Pre-Inspection | 4/26/2024 | Approved | DAVID SCANTLIN |
| Grading Pre-Inspection | 5/1/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 6/25/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 9/24/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 10/1/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 10/30/2024 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 10/30/2024 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 10/30/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Sewer | 10/30/2024 | No Access for Inspection | DAVID SCANTLIN |
| Underground Mechanical | 10/30/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Gas Test | 11/14/2024 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 11/14/2024 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 11/21/2024 | Partial Approval | DAVID SCANTLIN |
| PLUMBING-Rough | 11/21/2024 | Partial Approval | DAVID SCANTLIN |
| ELECTRICAL-Rough | 1/24/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2025 | Partial Approval | DAVID SCANTLIN |
| Green Building Rough | 1/24/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 1/24/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 1/24/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 1/30/2025 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/7/2025 | Corrections Issued | DAVID SCANTLIN |
| Green Building Rough | 2/7/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 2/7/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Interior/Exterior Lathing | 2/21/2025 | Partial Approval | DAVID SCANTLIN |
| Insulation | 4/14/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 4/15/2025 | Approved | DAVID SCANTLIN |
| Green Building Rough | 4/15/2025 | Approved | DAVID SCANTLIN |
| Insulation | 4/15/2025 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 4/15/2025 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 4/28/2025 | Approved | DAVID SCANTLIN |