9766 N VENA AVE 91331

Certificate Information: 9766 N VENA AVE 91331

Application / Permit
19010-20000-02171
Plan Check / Job No.
B19VN08494
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30'-0" X 20'-0" DETACHED ACCESSORY DWELLING UNIT AND ATTACHED 4' X 3' COVERED PATIO PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 7/13/2022
Issuing Office
Current Status
CofO Issued on 2/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2019 APPLICANT
Assigned to Plan Check Engineer 6/7/2019 JEROME MAGAT PALMA
Corrections Issued 6/10/2019 JEROME MAGAT PALMA
Quality Review Completed 6/10/2019 ABDUL CHEGENI
Green Plans Picked Up 2/7/2020 APPLICANT
Applicant returned to address corrections 12/4/2020 JEROME MAGAT PALMA
Applicant returned to address corrections 4/8/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 10/22/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 11/18/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 5/3/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 6/2/2022 JEROME MAGAT PALMA
Plan Check Approved 7/5/2022 JEROME MAGAT PALMA
Building Plans Picked Up 7/7/2022 APPLICANT
Issued 7/13/2022 APPLICANT
CofO in Progress 9/29/2023 MICHEL ABAJAN
No Progress 2/21/2024 ROBERT GOLD
CofO in Progress 2/21/2024 ROBERT GOLD
Permit Finaled 2/27/2024 RUBEN SALAS
CofO Issued 2/27/2024 RUBEN SALAS
Permit Finaled 2/27/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/19/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/19/2019 LEE GUILBEAUX
Sewer availability Cleared 6/19/2019 LEE GUILBEAUX
Hydrant and Access approval Cleared 7/8/2020 MATTHEW CRAIG
Low Impact Development Cleared 2/15/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/30/2022 JOHN LIN
Construction near power lines Cleared 4/18/2022 NADER ISKANDER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/19/2022 Corrections Issued MICHEL ABAJAN
METHANE-Barrier 7/19/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 7/19/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 8/31/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/13/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 12/16/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 12/16/2022 Approved MICHEL ABAJAN
Green Building Rough 12/16/2022 Approved MICHEL ABAJAN
MERV13>=Rough 12/16/2022 Approved MICHEL ABAJAN
METHANE-Rough 12/16/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 12/16/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 12/16/2022 Approved MICHEL ABAJAN
Insulation 1/12/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/12/2023 Approved MICHEL ABAJAN
Drywall Nailing 1/30/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/30/2023 Approved MATTHEW NELSON
Underground Mechanical 7/17/2023 Partial Approval MICHEL ABAJAN
Final 8/16/2023 Corrections Issued ROBERT GOLD
Green Building Final 8/16/2023 Approved ROBERT GOLD
MERV13>=Final 8/16/2023 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 8/16/2023 SGSOV Not Ready ROBERT GOLD
Service/Power Release 8/16/2023 Not Required ROBERT GOLD
Smoke Detectors 8/16/2023 Corrections Issued ROBERT GOLD
ELECTRICAL-Final 9/29/2023 Approved MICHEL ABAJAN
Final 9/29/2023 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 9/29/2023 Approved MICHEL ABAJAN
PLUMBING-Final 9/29/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 9/29/2023 Approved MICHEL ABAJAN