3838 N WESTFALL DR 91436

Certificate Information: 3838 N WESTFALL DR 91436

Application / Permit
19010-20000-02165
Plan Check / Job No.
B19VN08470
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19'-1" x 59'-1" ACCESSORY DWELLING UNIT PER AB 494 & SB 229 WITH ATTACHED DECK. "BUILDING EQUIPPED WITH NFPA- 13D FIRE SPRINKLERS THRU-OUT "
Permit Issued
Issued on 11/2/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2019 APPLICANT
Assigned to Plan Check Engineer 6/7/2019 SARKIS HARABEDIAN
Corrections Issued 6/24/2019 SARKIS HARABEDIAN
Quality Review Completed 7/2/2019 ABDUL CHEGENI
Building Plans Picked Up 7/3/2019 APPLICANT
Green Plans Picked Up 7/11/2019 APPLICANT
Applicant returned to address corrections 10/17/2019 SARKIS HARABEDIAN
Applicant returned to address corrections 12/3/2019 SARKIS HARABEDIAN
Applicant returned to address corrections 12/6/2019 SARKIS HARABEDIAN
Plan Check Approved 12/13/2019 SARKIS HARABEDIAN
Issued 11/2/2020 APPLICANT
CofO in Progress 1/18/2023 VINCENT HANLEY
Permit Finaled 1/25/2023 JOHN JANSON
CofO Issued 1/25/2023 JOHN JANSON
Permit Finaled 1/25/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/11/2019 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 7/11/2019 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 7/11/2019 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 7/11/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 7/11/2019 GUILLERMO PETRA
Sewer availability Cleared 7/11/2019 GUILLERMO PETRA
Green Code Cleared 8/9/2019 DAVID MATSON
GPI Written Notices Cleared 10/17/2019 SARKIS HARABEDIAN
Grading Pre-Inspection Cleared 10/17/2019 SARKIS HARABEDIAN
Hydrant and Access approval Cleared 10/29/2019 GEORGE SUCHAND
Low Impact Development Cleared 11/5/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/5/2019 ADRIAN CASTRO

Contact Information

Architect Salcedo,, Glen Charles; Lic. No.: C33143 P O BOX 14202      VAN NUYS, CA 91409
Contractor Z Development Corp; Lic. No.: 596875-B 5222 WINNETKA AVE      WOODLAND HILLS, CA 91364
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Moeini,, Soheil; Lic. No.: C84000 1836 PARNELL AVE 202      LOS ANGELES, CA 90025
Engineer Shank,, Ken M; Lic. No.: L8271 2566 N FERNANDO RD      LOS ANGELES, CA 90065
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 3/22/2021 Approved DAVID SCANTLIN
Deputy Reinf. Concrete 5/7/2021 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 5/10/2021 Partial Approval DAVID SANDOVAL
Deputy Reinf. Concrete 5/11/2021 Conditional Approval RYAN SALAZAR
Deputy Reinf. Concrete 5/18/2021 Approved RONALD COWAN
Footing/Foundation/Slab 5/21/2021 Partial Approval RONALD COWAN
Deputy Reinf. Concrete 5/25/2021 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 6/15/2021 Partial Approval RONALD COWAN
Deputy Reinf. Concrete 6/22/2021 Conditional Approval ALAN MORELOS
Footing/Foundation/Slab 6/23/2021 Partial Approval STEVEN BACK
Deputy Reinf. Concrete 6/25/2021 Conditional Approval ASHLEY THOMPSON
Deputy Shotcrete 7/1/2021 Conditional Approval MICHAEL PELHAM
Deputy Shotcrete 7/2/2021 Conditional Approval STEPHANIE SWANSON
Deputy Shotcrete 7/6/2021 Conditional Approval RYAN SALAZAR
Deputy Shotcrete 7/7/2021 Approved RONALD COWAN
Deputy Shotcrete 7/8/2021 Approved RONALD COWAN
Reinforced Concrete Frame 7/15/2021 Partial Approval RONALD COWAN
Reinforced Masonry Frame 7/15/2021 Partial Approval RONALD COWAN
Deputy Shotcrete 7/29/2021 Approved RONALD COWAN
Deputy Shotcrete 8/3/2021 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 8/12/2021 Corrections Issued RONALD COWAN
Underground Mechanical 8/20/2021 Partial Approval RONALD COWAN
Deputy Reinf. Concrete 9/28/2021 Approved RONALD COWAN
Footing/Foundation/Slab 9/29/2021 Partial Approval RONALD COWAN
Deputy Reinf. Concrete 10/4/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Partial Approval RONALD COWAN
Deputy Reinf. Concrete 11/10/2021 Conditional Approval RONALD COWAN
ELECTRICAL-Rough 12/6/2021 Approved SEAN HAUPT
Gas Test 12/6/2021 Partial Approval SEAN HAUPT
HVAC-Rough 12/6/2021 Approved SEAN HAUPT
PLUMBING-Rough 12/6/2021 Approved SEAN HAUPT
Insulation 12/8/2021 Partial Inspection DAVID SANDOVAL
Deputy Wood Construction 1/28/2022 Conditional Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 2/2/2022 Partial Approval DAVID SANDOVAL
Green Building Rough 2/2/2022 Not Ready for Inspection DAVID SANDOVAL
Verify Sprinkler Sign Off 2/2/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 2/15/2022 Approved SEAN HAUPT
Insulation 2/18/2022 Approved DAVID SANDOVAL
Drywall Nailing 2/25/2022 Approved DAVID SANDOVAL
Green Building Rough 2/25/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 2/25/2022 Approved DAVID SANDOVAL
Shower Pan 2/25/2022 Approved DAVID SANDOVAL
Underground Mechanical 4/11/2022 Partial Approval PETER FOLLING
Underground Mechanical 5/20/2022 Corrections Issued VINCENT HANLEY
Sewer 5/26/2022 Approved PETER FOLLING
ELECTRICAL-Final 7/19/2022 Not Ready for Inspection VINCENT HANLEY
Gas Test 8/8/2022 Approved VINCENT HANLEY
Sewer 8/8/2022 Approved VINCENT HANLEY
Underground Mechanical 8/8/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 11/21/2022 Corrections Issued VINCENT HANLEY
HVAC-Final 11/21/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Final 11/21/2022 Corrections Issued VINCENT HANLEY
Special/Order Compliance 11/21/2022 Approved JON MCHUGH
ELECTRICAL-Final 12/23/2022 Approved VINCENT HANLEY
HVAC-Final 12/23/2022 Approved VINCENT HANLEY
PLUMBING-Final 12/23/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/13/2023 Approved VINCENT HANLEY
Final 1/13/2023 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 1/13/2023 Approved VINCENT HANLEY
Green Building Final 1/13/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Approved VINCENT HANLEY
Service/Power Release 1/13/2023 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 1/13/2023 Approved VINCENT HANLEY
Final 1/18/2023 OK to Issue CofO VINCENT HANLEY
Service/Power Release 1/18/2023 Approved VINCENT HANLEY