1348 E 27TH ST #1-14 90011

Certificate Information: 1348 E 27TH ST #1-14 90011

Application / Permit
19010-20000-02093
Plan Check / Job No.
B19VN08229
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 2-STORY 14-UNIT TYPE V-A 100% AFFORDABLE HOUSING APARTMENT BUILDING, TIER 2 (2 UNITS FOR EXTREMELY LOW INCOME, 3 UNITS FOR VERY LOW INCOME & 9 UNITS FOR LOW INCOME) (NFPA-13R FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 1/27/2021
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2019 APPLICANT
Assigned to Plan Check Engineer 6/20/2019 NILOOFAR MEHRAIN
Corrections Issued 7/3/2019 NILOOFAR MEHRAIN
Disabled Access Plans Picked Up 7/9/2019 APPLICANT
Green Plans Picked Up 7/9/2019 APPLICANT
Quality Review Completed 7/10/2019 CHON CHIO KUO
Applicant returned to address corrections 3/27/2020 NILOOFAR MEHRAIN
Plan Check Approved 12/1/2020 NILOOFAR MEHRAIN
Issued 1/27/2021 APPLICANT
Building Plans Picked Up 1/29/2021 APPLICANT
TCO Issued (Expire Date: 12-30-2025) 7/3/2025 RAFAEL ESPINOZA
CofO in Progress 11/18/2025 ERNESTO CORRAL
Permit Finaled 11/18/2025 ERNESTO CORRAL
Permit Finaled 11/18/2025 ERNESTO CORRAL
CofO Issued 11/18/2025 ERNESTO CORRAL

Permit Application Clearance Information

Fire Marshall Fire Life Safety Cleared 7/9/2019 GILBERT URREA
Hydrant and Access approval Cleared 7/9/2019 GILBERT URREA
Address approval Cleared 7/16/2019 ELAINE LEI
Community Plan Implem. Overlay Cleared 7/16/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 7/16/2019 ELAINE LEI
Highway dedication Cleared 7/16/2019 ELAINE LEI
Permit Cleared 7/16/2019 ELAINE LEI
Sewer availability Cleared 7/16/2019 ELAINE LEI
Community Plan Implem. Overlay Cleared 8/8/2019 JOHN KIM
Community Plan Implem. Overlay Cleared 8/8/2019 TERRI OSBORNE
Trees in Parkway Cleared 8/8/2019 JOHN KIM
ZI Cleared 8/8/2019 TERRI OSBORNE
Project located in CRA area Cleared 9/5/2019 JIM URQUHART
Low Impact Development Cleared 1/16/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/17/2020 GUILLERMO PETRA
Green Code Cleared 1/24/2020 MICHAEL AYERS
DAS Clearance Cleared 2/18/2020 NILOOFAR MEHRAIN
DCP conditions approval Cleared 10/28/2020 JACOB COMER
Density Bonus 12.22.A.31 Cleared 10/28/2020 JACOB COMER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2021 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/5/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/7/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/28/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Partial Approval JAMES POWERS
Green Building Rough 11/3/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 11/3/2021 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 11/23/2021 Partial Approval TED RIES
SGSOV-Seismic Gas S/O Valve 1/25/2022 SGSOV Not Ready JAMES POWERS
Verify Sprinkler Sign Off 1/25/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 1/25/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 4/18/2022 Corrections Issued RAFAEL ESPINOZA
Drywall Nailing 5/11/2022 Partial Approval JAMES POWERS
Insulation 8/23/2023 Partial Approval JAMES POWERS
Drywall Nailing 8/30/2023 Partial Approval ALAN MORELOS
Drywall Nailing 10/17/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/6/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 11/6/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/17/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 11/17/2023 Partial Approval JAMES POWERS
Insulation 12/11/2023 Partial Approval NICK DANERI
Insulation 12/14/2023 Approved RAFAEL ESPINOZA
Drywall Nailing 12/20/2023 Partial Approval LARRY ARNICK
Pre-Inspection 3/22/2024 Partial Approval JAMES POWERS
Pre-Inspection 6/24/2024 Not Ready for Inspection JAMES POWERS
Pre-Inspection 6/26/2024 Partial Approval JAMES POWERS
Pre-Inspection 7/25/2024 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Not Ready JAMES POWERS
Pre-Inspection 9/11/2024 Partial Approval JAMES POWERS
Pre-Inspection 9/13/2024 Not Ready for Inspection JAMES POWERS
Pre-Inspection 9/16/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/20/2024 Partial Approval JAMES POWERS
Pre-Inspection 9/27/2024 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/10/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 10/10/2024 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 11/5/2024 Not Ready for Inspection JAMES POWERS
Pre-Inspection 1/28/2025 Not Ready for Inspection JAMES POWERS
Final 5/2/2025 Not Ready for Inspection PAUL BAZERKANIAN
Footing/Foundation/Slab 5/2/2025 Approved PAUL BAZERKANIAN
Green Building Final 5/2/2025 Approved PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved PAUL BAZERKANIAN
Smoke Detectors 5/2/2025 Approved PAUL BAZERKANIAN
Verify Sprinkler Sign Off 5/2/2025 Approved PAUL BAZERKANIAN
Wood Frame 5/2/2025 Approved PAUL BAZERKANIAN
Final 11/6/2025 Not Ready for Inspection JAMES POWERS
Final 11/18/2025 OK to Issue CofO ERNESTO CORRAL