7324 N CAMELLIA AVE 91605
Certificate Information: 7324 N CAMELLIA AVE 91605
- Application / Permit
- 19010-20000-02086
- Plan Check / Job No.
- B19VN08196
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 16'-6" X 19'-0" IRREGULAR SHAPE DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WFPP. COMPLY WITH DEPARTMENT ORDER effective date 04/05/2019.
- Permit Issued
- Issued on 3/11/2020
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 8/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2019 | ROSENDO MEDINA |
| Green Plans Picked Up | 6/27/2019 | APPLICANT |
| Corrections Issued | 7/2/2019 | ROSENDO MEDINA |
| Quality Review Completed | 7/5/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 7/12/2019 | APPLICANT |
| Plan Check Approved | 3/11/2020 | ROSENDO MEDINA |
| Issued | 3/11/2020 | LADBS |
| CofO in Progress | 9/12/2023 | THOMAS WOODS |
| CofO Issued-Status Void | 9/26/2023 | DAVID JAMES |
| Permit Finaled-Status Void | 9/26/2023 | DAVID JAMES |
| Re-Activate Permit | 8/12/2024 | DAVID JAMES |
| Permit Finaled | 8/12/2024 | DAVID JAMES |
| CofO Corrected | 8/12/2024 | DAVID JAMES |
| Permit Finaled | 8/12/2024 | DAVID JAMES |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/12/2019 | OSCAR CASTRO |
| Address approval | Cleared | 2/6/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2020 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 2/6/2020 | JOHN LIN |
| Sewer availability | Cleared | 2/6/2020 | JOHN LIN |
| Green Code | Cleared | 2/28/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/12/2020 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 5/21/2020 | Corrections Issued | BRYAN MEYER |
| Footing/Foundation/Slab | 6/3/2020 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 7/19/2023 | Not Ready for Inspection | THOMAS WOODS |
| Drywall Nailing | 7/19/2023 | Not Ready for Inspection | THOMAS WOODS |
| Final | 7/19/2023 | Not Ready for Inspection | THOMAS WOODS |
| Footing/Foundation/Slab | 7/19/2023 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 7/19/2023 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Rough | 7/19/2023 | Not Ready for Inspection | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Not Ready | THOMAS WOODS |
| Service/Power Release | 7/19/2023 | Not Ready for Inspection | THOMAS WOODS |
| Smoke Detectors | 7/19/2023 | Not Ready for Inspection | THOMAS WOODS |
| Verify Sprinkler Sign Off | 7/19/2023 | Not Ready for Inspection | THOMAS WOODS |
| BUILDING-Rough-Frame | 8/15/2023 | Not Ready for Inspection | THOMAS WOODS |
| Drywall Nailing | 8/15/2023 | Approved | THOMAS WOODS |
| Final | 8/15/2023 | Not Ready for Inspection | THOMAS WOODS |
| Footing/Foundation/Slab | 8/15/2023 | Approved | THOMAS WOODS |
| Green Building Final | 8/15/2023 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Rough | 8/15/2023 | Approved | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 8/15/2023 | SGSOV Approved | THOMAS WOODS |
| Service/Power Release | 8/15/2023 | Not Ready for Inspection | THOMAS WOODS |
| Smoke Detectors | 8/15/2023 | Not Ready for Inspection | THOMAS WOODS |
| Verify Sprinkler Sign Off | 8/15/2023 | Not Ready for Inspection | THOMAS WOODS |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | THOMAS WOODS |
| ELECTRICAL-Final | 9/12/2023 | Approved | THOMAS WOODS |
| Final | 9/12/2023 | OK to Issue CofO | THOMAS WOODS |
| Gas Test | 9/12/2023 | Approved | THOMAS WOODS |
| Green Building Final | 9/12/2023 | Approved | THOMAS WOODS |
| HVAC-Final | 9/12/2023 | Approved | THOMAS WOODS |
| PLUMBING-Final | 9/12/2023 | Approved | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Approved | THOMAS WOODS |
| Service/Power Release | 9/12/2023 | Approved | THOMAS WOODS |
| Sewer | 9/12/2023 | Approved | THOMAS WOODS |
| Smoke Detectors | 9/12/2023 | Approved | THOMAS WOODS |