10422 W CROCKETT ST 91352

Certificate Information: 10422 W CROCKETT ST 91352

Application / Permit
19010-20000-02025
Plan Check / Job No.
B19VN07974
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT (30.83'X40.83'), PER AB 494 AND SB 229.
Permit Issued
Issued on 1/22/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2019 APPLICANT
Green Plans Picked Up 5/29/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 ABDUL CHEGENI
Corrections Issued 6/3/2019 ABDUL CHEGENI
Quality Review Completed 6/3/2019 STEVEN KIM
Building Plans Picked Up 6/6/2019 APPLICANT
Applicant returned to address corrections 12/3/2019 ABDUL CHEGENI
Applicant returned to address corrections 1/17/2020 ABDUL CHEGENI
Plan Check Approved 1/22/2020 ABDUL CHEGENI
Issued 1/22/2020 LADBS
CofO in Progress 2/19/2021 MICHAEL SMITH
CofO in Progress 2/19/2021 MICHAEL SMITH
CofO Issued 2/19/2021 MICHAEL SMITH
Permit Finaled 2/19/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/17/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 6/17/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 6/17/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 7/1/2019 GEORGE SUCHAND
Green Code Cleared 7/29/2019 PARISA ZAHABI
Construction near power lines Cleared 10/23/2019 RIDWAN HARDY
Construction within easement Cleared 10/23/2019 RIDWAN HARDY
Low Impact Development Cleared 1/22/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/22/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Alexanians,, Edward Ohanesi; Lic. No.: S2909 736 CORDOVA AVE      GLENDALE, CA 91206
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/28/2020 Conditional Approval BEAU COLLINS
Footing/Foundation/Slab 1/28/2020 Conditional Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 2/6/2020 Partial Approval BEAU COLLINS
PLUMBING-Rough 2/6/2020 Approved BEAU COLLINS
BUILDING-Rough-Frame 2/27/2020 Corrections Issued BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 2/27/2020 Approved BEAU COLLINS
Rough-Elec/Plmb/HVAC 2/27/2020 Partial Approval BEAU COLLINS
Insulation 3/17/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 3/17/2020 Partial Approval BEAU COLLINS
Insulation 3/20/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 3/20/2020 Partial Inspection BEAU COLLINS
Drywall Nailing 3/26/2020 Approved BEAU COLLINS
Green Building Rough 3/26/2020 Approved BEAU COLLINS
BUILDING-Rough-Frame 6/4/2020 Approved BEAU COLLINS
Final 6/4/2020 Corrections Issued BEAU COLLINS
Footing/Foundation/Slab 6/4/2020 Approved BEAU COLLINS
Green Building Final 6/4/2020 Not Ready for Inspection BEAU COLLINS
MERV13>=Final 6/4/2020 Not Ready for Inspection BEAU COLLINS
MERV13>=Rough 6/4/2020 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 6/4/2020 SGSOV Approved BEAU COLLINS
Service/Power Release 6/4/2020 Not Ready for Inspection BEAU COLLINS
Smoke Detectors 6/4/2020 Not Ready for Inspection BEAU COLLINS
Verify Sprinkler Sign Off 6/4/2020 Approved BEAU COLLINS
Final 6/19/2020 No Access for Inspection BEAU COLLINS
Green Building Final 6/19/2020 No Access for Inspection BEAU COLLINS
MERV13>=Final 6/19/2020 No Access for Inspection BEAU COLLINS
Service/Power Release 6/19/2020 No Access for Inspection BEAU COLLINS
Smoke Detectors 6/19/2020 No Access for Inspection BEAU COLLINS
Final 6/30/2020 Corrections Issued ROBERT MINASSIANS
Green Building Final 6/30/2020 Not Ready for Inspection ROBERT MINASSIANS
MERV13>=Final 6/30/2020 Not Ready for Inspection ROBERT MINASSIANS
Service/Power Release 6/30/2020 Corrections Issued ROBERT MINASSIANS
Smoke Detectors 6/30/2020 Not Ready for Inspection ROBERT MINASSIANS
Final 8/13/2020 Corrections Issued BEAU COLLINS
Final 8/25/2020 Not Ready for Inspection BEAU COLLINS
Green Building Final 8/25/2020 Approved BEAU COLLINS
MERV13>=Final 8/25/2020 Approved BEAU COLLINS
Service/Power Release 8/25/2020 Not Ready for Inspection BEAU COLLINS
Smoke Detectors 8/25/2020 Approved BEAU COLLINS
Service/Power Release 11/2/2020 Approved BEAU COLLINS
Final 11/4/2020 Corrections Issued BEAU COLLINS
Final 2/5/2021 Partial Inspection GREGG CUMMINGS
Final 2/9/2021 OK to Issue CofO BEAU COLLINS