8941 N TELFAIR AVE 91352
Certificate Information: 8941 N TELFAIR AVE 91352
- Application / Permit
- 19010-20000-02000
- Plan Check / Job No.
- B19VN07870
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) Detached (33'x40' Irr.) one-story Accessory Dwelling Unit.
- Permit Issued
- Issued on 4/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2019 | LUIS RINCON |
| Corrections Issued | 7/11/2019 | LUIS RINCON |
| Quality Review Completed | 7/12/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 7/15/2019 | APPLICANT |
| Green Plans Picked Up | 7/15/2019 | APPLICANT |
| Plan Check Approved | 9/23/2019 | LUIS RINCON |
| No Progress | 11/6/2019 | LUIS RINCON |
| Plan Check Approved | 1/21/2020 | LUIS RINCON |
| No Progress | 2/27/2020 | LUIS RINCON |
| Plan Check Approved | 2/27/2020 | LUIS RINCON |
| Issued | 4/6/2020 | LADBS |
| CofO in Progress | 8/27/2021 | JOHN HAYES |
| CofO Issued | 9/16/2021 | MICHAEL SMITH |
| Permit Finaled | 9/16/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2019 | SAFA JAVANMARDI |
| Clean Up Green Up | Cleared | 7/18/2019 | SHEILA GERSHON |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2019 | SAFA JAVANMARDI |
| Hydrant and Access approval | Cleared | 7/18/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 7/18/2019 | SAFA JAVANMARDI |
| ZI | Cleared | 7/18/2019 | SHEILA GERSHON |
| Low Impact Development | Cleared | 8/15/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/15/2019 | CELINA MORENO |
| Green Code | Cleared | 9/10/2019 | PARISA ZAHABI |
| Construction near power lines | Cleared | 1/14/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/17/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 4/21/2020 | Approved | JOHN HAYES |
| PLUMBING-Rough | 5/8/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 5/12/2020 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 6/10/2020 | Partial Approval | JOHN HAYES |
| Green Building Rough | 6/10/2020 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 6/10/2020 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 6/10/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 9/10/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 9/17/2020 | No Access for Inspection | DAVID MATSON |
| Gas Test | 9/21/2020 | Partial Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 9/25/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/25/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/25/2020 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 9/25/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/25/2020 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 9/25/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 10/1/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 10/1/2020 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 10/27/2020 | No Access for Inspection | JOHN HAYES |
| Insulation | 10/27/2020 | No Access for Inspection | JOHN HAYES |
| Drywall Nailing | 10/29/2020 | Approved | MATTHEW NELSON |
| Insulation | 10/29/2020 | Approved | MATTHEW NELSON |
| Shower Pan | 12/8/2020 | No Access for Inspection | JOHN HAYES |
| Shower Pan | 12/10/2020 | No Access for Inspection | JOHN HAYES |
| Shower Pan | 12/14/2020 | No Access for Inspection | JOHN HAYES |
| Shower Pan | 12/16/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 1/12/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 5/27/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/27/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 5/27/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 5/27/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 6/30/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 6/30/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 6/30/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 6/30/2021 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 6/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 6/30/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 7/20/2021 | Approved | MICHEL ABAJAN |
| Final | 7/20/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 7/20/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 7/20/2021 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 7/20/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/20/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2021 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 7/20/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 7/20/2021 | Approved | MICHEL ABAJAN |
| Final | 8/20/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 8/20/2021 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 8/20/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/25/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 8/25/2021 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 8/25/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/26/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 8/26/2021 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 8/26/2021 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 8/26/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/27/2021 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 8/27/2021 | Approved | JOHN HAYES |
| Service/Power Release | 8/27/2021 | Approved | JOHN HAYES |