19131 W MENARD PL 91356

Certificate Information: 19131 W MENARD PL 91356

Application / Permit
19010-20000-01974
Plan Check / Job No.
B19VN07756
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30' 6" X 61' 8" ACCESSORY DWELLING UNIT WITH ATTACHED 8' X 3' COVERED PORCH AND 22' X 9' 2" EXTERIOR STAIRS PER AB 494 & SB 229 ON CONCRETE PILES. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 4/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2019 APPLICANT
Green Plans Picked Up 5/21/2019 APPLICANT
Assigned to Plan Check Engineer 5/23/2019 GURUNATH NESARAJAH
Corrections Issued 5/26/2019 GURUNATH NESARAJAH
Quality Review Completed 5/30/2019 OMID HEDAYAT
Building Plans Picked Up 5/31/2019 APPLICANT
Plan Check Approved 12/16/2019 GURUNATH NESARAJAH
Issued 4/9/2020 LADBS
CofO in Progress 11/8/2021 DAVID SANDOVAL
CofO Issued 1/6/2022 MICHAEL SMITH
Permit Finaled 1/6/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/26/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 6/26/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 6/26/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 6/26/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 6/26/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 6/26/2019 MARKOS PEREZ-BRAN
ZA Case Cleared 6/27/2019 ANNA VIDAL
ZI Cleared 6/27/2019 ANNA VIDAL
Hydrant and Access approval Cleared 7/1/2019 GEORGE SUCHAND
Distance to fire station Cleared 7/3/2019 OSCAR SALGADO JR
Low Impact Development Cleared 10/17/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/18/2019 APEKSHYA BAJRACHARYA
GPI Written Notices Cleared 10/22/2019 GURUNATH NESARAJAH
Grading Pre-Inspection Cleared 10/22/2019 GURUNATH NESARAJAH
Green Code Cleared 10/22/2019 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/14/2020 Approved DAVID SANDOVAL
Piling/Pier/Caisson 5/19/2020 Partial Approval DAVID SANDOVAL
Piling/Pier/Caisson 5/22/2020 Partial Approval DAVID SANDOVAL
Deputy Reinf. Concrete 5/26/2020 Approved DAVID SANDOVAL
Deputy Reinf. Concrete 5/28/2020 Approved DAVID SANDOVAL
Pre-Inspection 6/3/2020 Corrections Issued DAVID SANDOVAL
Piling/Pier/Caisson 6/29/2020 Approved MICHAEL TEMPLE
Footing/Foundation/Slab 7/9/2020 Approved DAVID SANDOVAL
Deputy Reinf. Concrete 7/13/2020 Approved DAVID SANDOVAL
Reinforced Concrete Frame 7/16/2020 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 8/7/2020 Partial Approval DAVID SANDOVAL
HVAC-Rough 8/24/2020 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 8/24/2020 Corrections Issued DAVID SANDOVAL
HVAC-Rough 9/3/2020 Approved DAVID SANDOVAL
PLUMBING-Rough 9/3/2020 Approved DAVID SANDOVAL
Rough-Elec/Plmb/HVAC 9/3/2020 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 9/8/2020 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 9/8/2020 Approved DAVID SANDOVAL
Green Building Rough 9/8/2020 Not Ready for Inspection DAVID SANDOVAL
Verify Sprinkler Sign Off 9/8/2020 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 9/14/2020 Approved DAVID SANDOVAL
Green Building Rough 9/14/2020 Approved DAVID SANDOVAL
Interior/Exterior Lathing 9/14/2020 Approved DAVID SANDOVAL
Insulation 9/18/2020 Approved DAVID SANDOVAL
Drywall Nailing 9/22/2020 Approved DAVID SANDOVAL
Shower Pan 10/2/2020 Approved DAVID SANDOVAL
Interior/Exterior Lathing 10/13/2020 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 11/30/2020 Approved DAVID SANDOVAL
ELECTRICAL-Rough 2/9/2021 Partial Approval DAVID SCANTLIN
Underground Mechanical 2/23/2021 Partial Approval DAVID SANDOVAL
ELECTRICAL-Final 5/28/2021 Corrections Issued DAVID SANDOVAL
Service/Power Release 5/28/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Final 6/1/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 6/30/2021 Corrections Issued DAVID SANDOVAL
Service/Power Release 6/30/2021 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Final 7/6/2021 Approved DAVID SANDOVAL
Final 7/13/2021 Partial Approval PETER FOLLING
Green Building Final 7/13/2021 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 7/13/2021 SGSOV Approved PETER FOLLING
Service/Power Release 7/13/2021 Approved PETER FOLLING
Smoke Detectors 7/13/2021 Approved PETER FOLLING
Final 11/8/2021 OK to Issue CofO DAVID SANDOVAL