3032 S CHESAPEAKE AVE 90016
Certificate Information: 3032 S CHESAPEAKE AVE 90016
- Application / Permit
- 19010-20000-01913
- Plan Check / Job No.
- B19VN07463
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 20'X30' ACCESSORY DWELLING UNIT PER AB 494 & SB 229.
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2019 | RODNEY SAMIIAN |
| Green Plans Picked Up | 6/7/2019 | APPLICANT |
| Corrections Issued | 6/13/2019 | RODNEY SAMIIAN |
| Quality Review Completed | 6/13/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 6/14/2019 | APPLICANT |
| Plan Check Approved | 9/20/2019 | RODNEY SAMIIAN |
| Issued | 2/18/2020 | LADBS |
| CofO in Progress | 7/13/2022 | STUART CHAPMAN |
| Permit Finaled | 4/11/2023 | DEROLD HAUFF |
| CofO Issued | 4/11/2023 | DEROLD HAUFF |
| Permit Finaled | 4/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 6/12/2019 | MICHAEL AYERS |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/23/2019 | GUILLERMO PETRA |
| Address approval | Cleared | 8/22/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 8/22/2019 | JEREMY CARTER |
| Low Impact Development | Cleared | 8/22/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/22/2019 | CELINA MORENO |
| Construction near power lines | Cleared | 9/20/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Ameera Enterprises Inc; Lic. No.: 935432-B | P O BOX 1331 HAWTHORNE, CA 90251 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/11/2020 | Partial Approval | HORACE FULTZ |
| Insulation | 3/26/2020 | Corrections Issued | SABAS ALONSO |
| Insulation | 4/1/2020 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 4/1/2020 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 4/2/2020 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2020 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 5/14/2020 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 5/14/2020 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 7/9/2020 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/28/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/28/2020 | Approved | STUART CHAPMAN |
| HVAC-Rough | 7/28/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 7/28/2020 | Conditional Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/7/2020 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/25/2020 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 8/25/2020 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 8/25/2020 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 8/25/2020 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 9/29/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Interior/Exterior Lathing | 9/29/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/10/2021 | Approved | STUART CHAPMAN |
| Final | 8/20/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/20/2021 | Approved | STUART CHAPMAN |
| Green Building Final | 8/20/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/20/2021 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 8/20/2021 | Approved | STUART CHAPMAN |
| Smoke Detectors | 8/20/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 9/13/2021 | Approved | STUART CHAPMAN |
| Final | 9/13/2021 | OK for TCO | STUART CHAPMAN |
| HVAC-Final | 9/13/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 9/13/2021 | Approved | STUART CHAPMAN |
| Final | 7/13/2022 | OK to Issue CofO | STUART CHAPMAN |