9700 N ESTABAN WAY 91042
Certificate Information: 9700 N ESTABAN WAY 91042
- Application / Permit
- 19010-20000-01879
- Plan Check / Job No.
- B19VN07248
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 29'-3" x 53'-8" two-story single family dwelling with attached 2-car garage. NFPA 13 D fire sprinklers required throughout
- Permit Issued
- Issued on 2/14/2022
- Issuing Office
- Current Status
- Issued on 2/14/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2019 | ALYSSA N NARCISO |
| Corrections Issued | 6/13/2019 | ALYSSA N NARCISO |
| Quality Review Completed | 6/13/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 6/17/2019 | APPLICANT |
| Green Plans Picked Up | 6/17/2019 | APPLICANT |
| Applicant returned to address corrections | 10/14/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 2/8/2022 | SEAN SHAHMIRI |
| Issued | 2/14/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2019 | JULIUS GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2019 | JULIUS GARCIA |
| Low Impact Development | Cleared | 8/28/2019 | MITESH PATEL |
| Private sewage disp. approval | Cleared | 10/14/2020 | DAN RYAN EVANGELISTA |
| Distance to fire station | Cleared | 6/25/2021 | JOHN CONNEALLY |
| Hydrant and Access approval | Cleared | 6/25/2021 | JOHN CONNEALLY |
| Specific Plan | Cleared | 8/16/2021 | PEGGY MALONE-BROWN |
| BHO/Hillside ordinance | Cleared | 9/1/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 9/1/2021 | GABRIEL ROBLES |
| Miscellaneous | Cleared | 9/1/2021 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 9/1/2021 | MIGUEL GAMBOA |
| Permit | Cleared | 9/1/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 9/15/2021 | GABRIEL ROBLES |
| GPI Written Notices | Cleared | 10/14/2021 | ALYSSA N NARCISO |
| Grading Pre-Inspection | Cleared | 10/14/2021 | ALYSSA N NARCISO |
| Trees in Parkway | Cleared | 12/21/2021 | ADALBERTO VERA |
| Green Code | Cleared | 2/3/2022 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Service/Power Release | 2/17/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 3/10/2022 | Partial Inspection | DAVID MATSON |
| Piling/Pier/Caisson | 4/22/2022 | Corrections Issued | MICHEL ABAJAN |
| Piling/Pier/Caisson | 5/24/2022 | Approved | MATT KELLERMAN |
| Deputy Reinf. Concrete | 5/25/2022 | Conditional Approval | WILLIAM WREN |
| Deputy Reinf. Concrete | 6/7/2022 | Conditional Approval | DAVID MATSON |
| Piling/Pier/Caisson | 6/8/2022 | Approved | MATTHEW NELSON |
| Deputy Reinf. Concrete | 6/10/2022 | Conditional Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/27/2022 | Corrections Issued | DAVID ANDERSON |
| Grading Pre-Inspection | 8/1/2022 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 8/9/2022 | Approved | DAVID ANDERSON |
| Deputy Reinf. Concrete | 8/16/2022 | Conditional Approval | DAVID MATSON |
| Drywall Nailing | 8/29/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 8/29/2022 | Approved | DAVID ANDERSON |
| Deputy Reinf. Concrete | 8/30/2022 | Conditional Approval | DAVID MATSON |
| Deputy Reinf. Concrete | 9/30/2022 | Conditional Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Partial Approval | DAVID ANDERSON |
| Green Building Rough | 11/8/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 11/8/2022 | Corrections Issued | DAVID ANDERSON |
| Insulation | 11/15/2022 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 3/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Deputy Wood Construction | 3/9/2023 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 4/27/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 5/31/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 5/31/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 5/31/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 6/7/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 6/7/2023 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 6/7/2023 | Approved | DAVID ANDERSON |
| Insulation | 6/14/2023 | Corrections Issued | DAVID ANDERSON |
| Drywall Nailing | 6/26/2023 | Approved | DAVID ANDERSON |
| Insulation | 6/26/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/25/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 7/25/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 8/22/2023 | Approved | DAVID ANDERSON |