1344 W 223RD ST 90501
Certificate Information: 1344 W 223RD ST 90501
- Application / Permit
- 19010-20000-01824
- Plan Check / Job No.
- B19VN07052
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 37'-8" X 40' ACCESSORY DWELLING UNIT WITH 19'-2" X 4'-0" AND 20'-0" X 20'-0" ATTACHED GARAGE PER AB 494 & SB 229
- Permit Issued
- Issued on 8/20/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/11/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2019 | APPLICANT |
| Green Plans Picked Up | 5/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | ROSENDO MEDINA |
| Corrections Issued | 5/20/2019 | ROSENDO MEDINA |
| Quality Review Completed | 5/22/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 6/5/2019 | APPLICANT |
| Applicant returned to address corrections | 8/2/2019 | ROSENDO MEDINA |
| Plan Check Approved | 8/20/2019 | ROSENDO MEDINA |
| Issued | 8/20/2019 | LADBS |
| CofO in Progress | 5/19/2020 | JOHN KLARIN |
| No Progress | 7/8/2020 | ANSON MAGLASANG |
| CofO in Progress | 8/3/2020 | ANSON MAGLASANG |
| Permit Finaled | 9/11/2020 | DEROLD HAUFF |
| CofO Issued | 9/11/2020 | DEROLD HAUFF |
| Permit Finaled | 9/11/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2019 | JOHN LIN |
| Green Code | Cleared | 6/21/2019 | COLIN LOREDO |
| Sewer availability | Cleared | 6/21/2019 | JOHN LIN |
| Low Impact Development | Cleared | 7/12/2019 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 7/24/2019 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 7/24/2019 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/4/2019 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Barrier | 9/4/2019 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Subgrade | 9/4/2019 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 9/9/2019 | Approved | JOHN KLARIN |
| METHANE-Barrier | 9/9/2019 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 9/9/2019 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 9/16/2019 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 9/27/2019 | Partial Inspection | JOHN KLARIN |
| PLUMBING-Rough | 9/27/2019 | Partial Inspection | JOHN KLARIN |
| Insulation | 9/30/2019 | Corrections Issued | JOHN KLARIN |
| Insulation | 10/2/2019 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2019 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2019 | Partial Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/6/2019 | Conditional Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 12/6/2019 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2019 | Approved | JOHN KLARIN |
| Green Building Rough | 12/6/2019 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 12/6/2019 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 12/6/2019 | Approved | JOHN KLARIN |
| Insulation | 12/13/2019 | Conditional Approval | JOHN KLARIN |
| Interior/Exterior Lathing | 12/13/2019 | Corrections Issued | JOHN KLARIN |
| Drywall Nailing | 12/18/2019 | Corrections Issued | BOB DUNN |
| Interior/Exterior Lathing | 12/18/2019 | Partial Approval | BOB DUNN |
| HVAC-Rough | 12/23/2019 | Approved | JOHN KLARIN |
| HVAC-Rough | 12/26/2019 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 4/13/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 4/13/2020 | Approved | JOHN KLARIN |
| Final | 4/13/2020 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 4/13/2020 | Corrections Issued | JOHN KLARIN |
| METHANE-Final | 4/13/2020 | Approved | JOHN KLARIN |
| METHANE-Rough | 4/13/2020 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 4/13/2020 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 4/13/2020 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 4/13/2020 | Approved | JOHN KLARIN |
| Final | 4/15/2020 | Partial Inspection | JOHN KLARIN |
| Green Building Final | 4/15/2020 | Approved | JOHN KLARIN |
| Service/Power Release | 4/15/2020 | Approved | JOHN KLARIN |
| Final | 5/1/2020 | Conditional Approval | JOHN KLARIN |
| Final | 5/19/2020 | OK to Issue CofO | JOHN KLARIN |