1344 W 223RD ST 90501

Certificate Information: 1344 W 223RD ST 90501

Application / Permit
19010-20000-01824
Plan Check / Job No.
B19VN07052
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 37'-8" X 40' ACCESSORY DWELLING UNIT WITH 19'-2" X 4'-0" AND 20'-0" X 20'-0" ATTACHED GARAGE PER AB 494 & SB 229
Permit Issued
Issued on 8/20/2019
Issuing Office
Valley
Current Status
CofO Issued on 9/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2019 APPLICANT
Green Plans Picked Up 5/10/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 ROSENDO MEDINA
Corrections Issued 5/20/2019 ROSENDO MEDINA
Quality Review Completed 5/22/2019 OMID HEDAYAT
Building Plans Picked Up 6/5/2019 APPLICANT
Applicant returned to address corrections 8/2/2019 ROSENDO MEDINA
Plan Check Approved 8/20/2019 ROSENDO MEDINA
Issued 8/20/2019 LADBS
CofO in Progress 5/19/2020 JOHN KLARIN
No Progress 7/8/2020 ANSON MAGLASANG
CofO in Progress 8/3/2020 ANSON MAGLASANG
Permit Finaled 9/11/2020 DEROLD HAUFF
CofO Issued 9/11/2020 DEROLD HAUFF
Permit Finaled 9/11/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/21/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 6/21/2019 JOHN LIN
Green Code Cleared 6/21/2019 COLIN LOREDO
Sewer availability Cleared 6/21/2019 JOHN LIN
Low Impact Development Cleared 7/12/2019 MITESH PATEL
Hydrant and Access approval Cleared 7/24/2019 ROBERT DUFF
Roof/Waste drainage to street Cleared 7/24/2019 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/4/2019 Not Ready for Inspection JOHN KLARIN
METHANE-Barrier 9/4/2019 Not Ready for Inspection JOHN KLARIN
METHANE-Subgrade 9/4/2019 Not Ready for Inspection JOHN KLARIN
Footing/Foundation/Slab 9/9/2019 Approved JOHN KLARIN
METHANE-Barrier 9/9/2019 Approved JOHN KLARIN
METHANE-Subgrade 9/9/2019 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 9/16/2019 Approved JOHN KLARIN
BUILDING-Rough-Frame 9/27/2019 Partial Inspection JOHN KLARIN
PLUMBING-Rough 9/27/2019 Partial Inspection JOHN KLARIN
Insulation 9/30/2019 Corrections Issued JOHN KLARIN
Insulation 10/2/2019 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/4/2019 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/3/2019 Partial Inspection JOHN KLARIN
BUILDING-Rough-Frame 12/6/2019 Conditional Approval JOHN KLARIN
ELECTRICAL-Rough 12/6/2019 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/6/2019 Approved JOHN KLARIN
Green Building Rough 12/6/2019 Approved JOHN KLARIN
PLUMBING-Rough 12/6/2019 Approved JOHN KLARIN
Verify Sprinkler Sign Off 12/6/2019 Approved JOHN KLARIN
Insulation 12/13/2019 Conditional Approval JOHN KLARIN
Interior/Exterior Lathing 12/13/2019 Corrections Issued JOHN KLARIN
Drywall Nailing 12/18/2019 Corrections Issued BOB DUNN
Interior/Exterior Lathing 12/18/2019 Partial Approval BOB DUNN
HVAC-Rough 12/23/2019 Approved JOHN KLARIN
HVAC-Rough 12/26/2019 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 4/13/2020 Approved JOHN KLARIN
Drywall Nailing 4/13/2020 Approved JOHN KLARIN
Final 4/13/2020 Corrections Issued JOHN KLARIN
Green Building Final 4/13/2020 Corrections Issued JOHN KLARIN
METHANE-Final 4/13/2020 Approved JOHN KLARIN
METHANE-Rough 4/13/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 4/13/2020 SGSOV Approved JOHN KLARIN
Service/Power Release 4/13/2020 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 4/13/2020 Approved JOHN KLARIN
Final 4/15/2020 Partial Inspection JOHN KLARIN
Green Building Final 4/15/2020 Approved JOHN KLARIN
Service/Power Release 4/15/2020 Approved JOHN KLARIN
Final 5/1/2020 Conditional Approval JOHN KLARIN
Final 5/19/2020 OK to Issue CofO JOHN KLARIN