731 N CURSON AVE 90046
Certificate Information: 731 N CURSON AVE 90046
- Application / Permit
- 19010-20000-01790
- Plan Check / Job No.
- B19VN06901
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (1 OF 2) NEW 2-STORY SFD WITH BASEMENT AND ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | CHON CHIO KUO |
| Corrections Issued | 6/14/2019 | CHON CHIO KUO |
| Quality Review Completed | 6/14/2019 | STEVEN KIM |
| Building Plans Picked Up | 6/24/2019 | APPLICANT |
| Green Plans Picked Up | 6/24/2019 | APPLICANT |
| Applicant returned to address corrections | 1/9/2020 | CHON CHIO KUO |
| Plan Check Approved | 1/15/2020 | CHON CHIO KUO |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 3/1/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 3/16/2022 | DEROLD HAUFF |
| CofO Issued | 3/16/2022 | DEROLD HAUFF |
| Permit Finaled | 3/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 7/30/2019 | MICHAEL AYERS |
| Low Impact Development | Cleared | 8/1/2019 | ORVAL HERNANDEZ-MARCI |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2019 | JOHN LIN |
| Permit | Cleared | 11/5/2019 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 11/5/2019 | JOHN LIN |
| Sewer availability | Cleared | 11/5/2019 | JOHN LIN |
| Hydrant and Access approval | Cleared | 11/6/2019 | GEORGE SUCHAND |
| Excavation more than 5-ft deep | Cleared | 11/15/2019 | CALOSHA APPROVED |
Contact Information
| Contractor | Vision Construction; Lic. No.: 541505-B | 6012 TOPEKA DRIVE TARZANA, CA 91356 |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/11/2020 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 4/20/2020 | Conditional Approval | RAUL BARAJAS |
| METHANE-Barrier | 4/20/2020 | Approved | RAUL BARAJAS |
| METHANE-Subgrade | 4/20/2020 | Approved | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/30/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 5/1/2020 | Approved | JOSEPH MCGARRY |
| Deputy Shotcrete | 5/5/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 6/18/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2020 | No Access for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2020 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/30/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 7/30/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 7/30/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 7/30/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/22/2020 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/22/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/30/2020 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 1/11/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/4/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/22/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 2/22/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Insulation | 2/22/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| METHANE-Rough | 2/22/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 2/22/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 3/25/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 3/25/2021 | Approved | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 4/14/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 5/20/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/27/2021 | Approved | CHRIS CHRISTENSEN |
| Grounding or Bonding | 9/1/2021 | Approved | CHRIS CHRISTENSEN |
| Sewer | 10/1/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/19/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Enclosure/Fence | 12/9/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Pool/Spa Cover | 12/17/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Enclosure/Fence | 12/22/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Enclosure/Fence | 12/29/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 1/11/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 1/14/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 1/14/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Final | 1/14/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 1/31/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/31/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 1/31/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 1/31/2022 | Approved | CHRIS CHRISTENSEN |
| Reinforced Concrete Frame | 1/31/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 1/31/2022 | Partial Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 1/31/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 2/22/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 2/22/2022 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 2/22/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 2/28/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |