8631 W OLIN ST 1-3 90034
Certificate Information: 8631 W OLIN ST 1-3 90034
- Application / Permit
- 19010-20000-01775
- Plan Check / Job No.
- B19VN06833
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 70'-0" x 36'-0" FOUR-STORY FULLY SPRINKLERED WITH NFPA-13 THREE-UNIT APARTMENT (TYPE VA CONSTRUCTION) WITH ATTACHED GARAGE ON GRADE.
- Permit Issued
- Issued on 8/6/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2019 | SARKIS HARABEDIAN |
| Green Plans Picked Up | 5/10/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 5/14/2019 | APPLICANT |
| Corrections Issued | 5/30/2019 | SARKIS HARABEDIAN |
| Quality Review Completed | 6/3/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 6/6/2019 | APPLICANT |
| Applicant returned to address corrections | 7/21/2020 | SARKIS HARABEDIAN |
| Plan Check Approved | 7/31/2020 | SARKIS HARABEDIAN |
| Issued | 8/6/2020 | APPLICANT |
| CofO in Progress | 7/14/2022 | JEFF BYTHEWAY |
| Permit Finaled | 2/7/2023 | DAVID TSAU |
| CofO Issued | 2/7/2023 | DAVID TSAU |
| Permit Finaled | 2/7/2023 | DAVID TSAU |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/8/2019 | RINA LARA |
| Address approval | Cleared | 7/8/2019 | GUILLERMO PETRA |
| Permit | Cleared | 7/8/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/8/2019 | GUILLERMO PETRA |
| Trees in Parkway | Cleared | 8/15/2019 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 11/6/2019 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 11/7/2019 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 11/7/2019 | APEKSHYA BAJRACHARYA |
| DAS Clearance | Cleared | 11/20/2019 | NORLITO MEDRANO |
| Green Code | Cleared | 11/21/2019 | PARISA ZAHABI |
| Fire Marshall Fire Life Safety | Cleared | 1/14/2020 | VIDAL GARCIA |
| Building over 3-story or 36-ft | Cleared | 7/22/2020 | CALOSHA APPROVED |
| Highway dedication | Cleared | 7/29/2020 | CELINA MORENO |
Contact Information
| Contractor | Makeover Builders Inc; Lic. No.: 986740-B | 21781 VENTURA BLVD UNIT 634 WOODLAND HILLS, CA 91364 |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
| Engineer | Munroe,, Massie; Lic. No.: C59905 | PO BOX 189 LA CANADA FLINTRIDGE, CA 91012 |
| Engineer | Valenzuela,, Carlos; Lic. No.: C44990 | 7801 BACON ROAD WHITTIER, CA 90602 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/23/2020 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 10/2/2020 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 10/5/2020 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 11/2/2020 | Approved | JEFF BYTHEWAY |
| Deputy Wood Construction | 11/20/2020 | Approved | JEFF BYTHEWAY |
| Green Building Rough | 11/20/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Structural Steel Frame | 11/20/2020 | Approved | JEFF BYTHEWAY |
| Verify Sprinkler Sign Off | 11/20/2020 | Approved | JEFF BYTHEWAY |
| Wood Frame | 11/20/2020 | Partial Approval | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2020 | Partial Approval | JEFF BYTHEWAY |
| Deputy Wood Construction | 12/8/2020 | Approved | JEFF BYTHEWAY |
| Green Building Rough | 12/8/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Wood Frame | 12/8/2020 | Partial Approval | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2020 | Partial Approval | JEFF BYTHEWAY |
| Green Building Rough | 12/21/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Insulation | 1/15/2021 | Partial Approval | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Partial Approval | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 5/10/2021 | Partial Approval | JEFF BYTHEWAY |
| Wood Frame | 5/10/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Green Building Rough | 5/19/2021 | Approved | JEFF BYTHEWAY |
| Wood Frame | 5/19/2021 | Partial Approval | JEFF BYTHEWAY |
| Drywall Nailing | 6/17/2021 | Partial Approval | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 6/30/2021 | Approved | JEFF BYTHEWAY |
| Special/Order Compliance | 10/22/2021 | Approved | JEFF BYTHEWAY |
| Drywall Nailing | 6/7/2022 | Approved | JEFF BYTHEWAY |
| Final | 6/7/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Green Building Final | 6/7/2022 | Approved | JEFF BYTHEWAY |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Approved | JEFF BYTHEWAY |
| Smoke Detectors | 6/7/2022 | Approved | JEFF BYTHEWAY |
| Wood Frame | 6/7/2022 | Approved | JEFF BYTHEWAY |
| Final | 7/13/2022 | OK to Issue CofO | JEFF BYTHEWAY |