1905 N GRACE AVE UNIT C 90068
Certificate Information: 1905 N GRACE AVE UNIT C 90068
- Application / Permit
- 19010-20000-01772
- Plan Check / Job No.
- B19VN06822
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New (23'-4"x 24'-8") 3- story SFD with attached garage NFPA-13D fire sprinklers required through-out. per "small lot subdivision pursuant to tentative tract map no./ preliminary parcel map no. AA-2017-829-PMLA-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded."
- Permit Issued
- Issued on 6/24/2020
- Issuing Office
- Current Status
- CofO Issued on 5/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | TROY DEGUZMAN |
| Green Plans Picked Up | 5/31/2019 | APPLICANT |
| Corrections Issued | 6/7/2019 | TROY DEGUZMAN |
| Quality Review Completed | 6/17/2019 | STEVEN KIM |
| Building Plans Picked Up | 6/27/2019 | APPLICANT |
| Applicant returned to address corrections | 1/31/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 2/19/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 5/20/2020 | TROY DEGUZMAN |
| Plan Check Approved | 6/1/2020 | TROY DEGUZMAN |
| Issued | 6/24/2020 | APPLICANT |
| CofO in Progress | 5/9/2024 | SCOTT FINNILA |
| Permit Finaled | 5/9/2024 | DEROLD HAUFF |
| CofO Issued | 5/9/2024 | DEROLD HAUFF |
| Permit Finaled | 5/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/8/2019 | HERMINIGILDO AGUSTIN |
| Address approval | Cleared | 11/18/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 11/18/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 11/18/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 11/18/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/18/2019 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 11/19/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 11/19/2019 | HERMINIGILDO AGUSTIN |
| HPOZ | Cleared | 12/24/2019 | LAMBERT GIESSINGER |
| Distance to fire station | Cleared | 12/27/2019 | JEREMY CARTER |
| Hydrant and Access approval | Cleared | 12/27/2019 | JEREMY CARTER |
| Miscellaneous | Cleared | 12/27/2019 | EMIL KYUPELYAN |
| Miscellaneous | Cleared | 12/27/2019 | JEREMY CARTER |
| Low Impact Development | Cleared | 1/6/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/14/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 1/15/2020 | MICHAEL AYERS |
| GPI Written Notices | Cleared | 1/16/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 1/16/2020 | TROY DEGUZMAN |
| Highway dedication | Cleared | 2/19/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/14/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Pre-Inspection | 10/19/2020 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 10/22/2020 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/5/2020 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 11/6/2020 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/6/2020 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2021 | Conditional Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2021 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 2/4/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 5/11/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2021 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 5/25/2021 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 5/25/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/2/2021 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 6/2/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/21/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 6/21/2021 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 7/1/2021 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 7/1/2021 | Approved | SCOTT FINNILA |
| MERV13>=Rough | 7/1/2021 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 7/1/2021 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 7/8/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Conditional Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/3/2021 | Approved | SCOTT FINNILA |
| Insulation | 8/3/2021 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 8/3/2021 | Conditional Approval | SCOTT FINNILA |
| Drywall Nailing | 8/19/2021 | Approved | SCOTT FINNILA |
| Shower Pan | 9/13/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/20/2021 | Partial Approval | SCOTT FINNILA |
| Shower Pan | 9/20/2021 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 9/30/2021 | Approved | SCOTT FINNILA |
| Sewer | 1/19/2022 | Approved | SCOTT FINNILA |
| Underground Mechanical | 2/14/2022 | Partial Approval | SCOTT FINNILA |
| HVAC-Final | 3/14/2022 | Corrections Issued | SCOTT FINNILA |
| Gas Test | 11/23/2022 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 11/23/2022 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 3/17/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/3/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/4/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/4/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 11/8/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/8/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| MERV13>=Final | 11/8/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/8/2023 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/8/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 11/8/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/8/2024 | OK to Issue CofO | SCOTT FINNILA |
| Green Building Final | 5/8/2024 | Approved | SCOTT FINNILA |
| HVAC-Final | 5/8/2024 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/8/2024 | SGSOV Approved | SCOTT FINNILA |
| Service/Power Release | 5/8/2024 | Approved | SCOTT FINNILA |