9844 N BURNET AVE 91343
Certificate Information: 9844 N BURNET AVE 91343
- Application / Permit
- 19010-20000-01723
- Plan Check / Job No.
- B19VN06697
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40' X 30' DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED 21'-8" X 11' OPEN TRELLIS PER AB 494 AND SB 229
- Permit Issued
- Issued on 7/8/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/7/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2019 | APPLICANT |
| Green Plans Picked Up | 5/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | ROSENDO MEDINA |
| Corrections Issued | 6/4/2019 | ROSENDO MEDINA |
| Quality Review Completed | 6/7/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 6/10/2019 | APPLICANT |
| Applicant returned to address corrections | 6/25/2019 | ROSENDO MEDINA |
| Plan Check Approved | 7/3/2019 | ROSENDO MEDINA |
| Issued | 7/8/2019 | LADBS |
| CofO in Progress | 6/2/2020 | JENNIFER RABUCHIN |
| CofO Issued | 7/7/2020 | MICHAEL SMITH |
| Permit Finaled | 7/7/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 6/18/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 6/20/2019 | DAVID MATSON |
| Low Impact Development | Cleared | 7/2/2019 | ORVAL HERNANDEZ-MARCI |
| Address approval | Cleared | 7/3/2019 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2019 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 7/3/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 7/3/2019 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arsen, Adzhemyan; Lic. No.: C89103 | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/31/2019 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/9/2019 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2019 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 8/20/2019 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 8/20/2019 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/10/2019 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/10/2019 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2019 | Approved | JENNIFER RABUCHIN |
| Gas Test | 10/10/2019 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 10/10/2019 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/10/2019 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/10/2019 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 10/10/2019 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/21/2019 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/25/2019 | Approved | JENNIFER RABUCHIN |
| Sewer | 12/3/2019 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 12/26/2019 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/18/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 2/18/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 2/18/2020 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 2/18/2020 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2020 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 2/18/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 2/18/2020 | Approved | JENNIFER RABUCHIN |
| Final | 3/4/2020 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 3/4/2020 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/4/2020 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 3/4/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/10/2020 | Approved | JENNIFER RABUCHIN |
| Final | 3/10/2020 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Final | 3/10/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/10/2020 | Approved | JENNIFER RABUCHIN |
| Final | 5/19/2020 | Partial Approval | JENNIFER RABUCHIN |
| Final | 6/2/2020 | OK to Issue CofO | JENNIFER RABUCHIN |