6845 N FIGUEROA ST LOT #4 90042
Certificate Information: 6845 N FIGUEROA ST LOT #4 90042
- Application / Permit
- 19010-20000-01666
- Plan Check / Job No.
- B19VN06493
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-STORY SFD W/ ROOFTOP DECK & ATTACHED 2-CAR GARAGE [Small lot subdivision pursuant to Tentative Tract Map No. VTT-77134-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded] (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 7/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2019 | APPLICANT |
| Green Plans Picked Up | 5/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/6/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/9/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 5/9/2019 | APPLICANT |
| Applicant returned to address corrections | 7/5/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/16/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/17/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 7/7/2021 | NILOOFAR MEHRAIN |
| Issued | 7/22/2021 | APPLICANT |
| CofO in Progress | 8/19/2025 | BRENDAN MORELLI |
| Permit Finaled | 8/21/2025 | DEROLD HAUFF |
| CofO Issued | 8/21/2025 | DEROLD HAUFF |
| Permit Finaled | 8/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2019 | ELAINE LEI |
| Green Code | Cleared | 7/8/2019 | NILOOFAR MEHRAIN |
| Internal circulation | Cleared | 8/2/2019 | EDUARDO HERMOSO |
| Address approval | Cleared | 8/8/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 8/13/2019 | ERIK BEASLEY |
| Highway dedication | Cleared | 8/14/2019 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 8/14/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 9/17/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/17/2019 | CELINA MORENO |
| Building over 3-story or 36-ft | Cleared | 10/16/2019 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 10/16/2019 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 10/16/2019 | NILOOFAR MEHRAIN |
| Disturb/Remove Protected Trees | Cleared | 10/18/2019 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 10/18/2019 | ADRIAN SANCHEZ |
| Miscellaneous | Cleared | 10/24/2019 | SARAH GOLDMAN |
| Tract Map conditions | Cleared | 10/24/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 7/7/2021 | ARMEN MEHRABIAN |
| Permit | Cleared | 7/7/2021 | ARMEN MEHRABIAN |
Contact Information
| Architect | Maly,, Farzin; Lic. No.: C33731 | 7136 HASKELL AVENUE # 320 VAN NUYS, CA 91406 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/5/2021 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 9/8/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/8/2021 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 9/23/2021 | Approved | SCOTT FINNILA |
| Deputy Wood Construction | 10/15/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 10/21/2021 | Corrections Issued | SCOTT FINNILA |
| Drywall Nailing | 10/25/2021 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 11/18/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 1/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/25/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2022 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 3/11/2022 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2022 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 4/12/2022 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/14/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/14/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/14/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/21/2022 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 6/21/2022 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 6/21/2022 | Corrections Issued | SCOTT FINNILA |
| Deputy Wood Construction | 6/23/2022 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 7/13/2022 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 7/13/2022 | Partial Inspection | SCOTT FINNILA |
| HVAC-Rough | 7/13/2022 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 7/13/2022 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 7/28/2022 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 7/28/2022 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 7/28/2022 | Partial Approval | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 7/28/2022 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 8/1/2022 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/5/2022 | Not Ready for Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/8/2022 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/16/2022 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 12/28/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 1/20/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 1/25/2023 | Partial Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 1/26/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 1/27/2023 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 2/7/2023 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 2/22/2023 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 2/24/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Sewer | 1/4/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Underground Mechanical | 1/4/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Underground Mechanical | 1/31/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Underground Mechanical | 2/2/2024 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 2/13/2024 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Final | 12/24/2024 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 12/24/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 12/24/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/18/2025 | Approved | BRENDAN MORELLI |
| Final | 8/18/2025 | OK to Issue CofO | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/18/2025 | Approved | BRENDAN MORELLI |
| Green Building Final | 8/18/2025 | Approved | BRENDAN MORELLI |
| Green Building Rough | 8/18/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 8/18/2025 | SGSOV Approved | BRENDAN MORELLI |
| Service/Power Release | 8/18/2025 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 8/18/2025 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 8/18/2025 | Approved | BRENDAN MORELLI |