2580 N ROSCOMARE ROAD 90077

Certificate Information: 2580 N ROSCOMARE ROAD 90077

Application / Permit
19010-20000-01628
Plan Check / Job No.
B19VN06296
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2 STORY SFD W/ATT. GARGE <SPRINKLERS REQ'D THROUGHOUT>
Permit Issued
Issued on 6/30/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 ABDUL CHEGENI
Green Plans Picked Up 5/23/2019 APPLICANT
Corrections Issued 6/6/2019 ABDUL CHEGENI
Quality Review Completed 6/12/2019 STEVEN KIM
Building Plans Picked Up 6/17/2019 APPLICANT
Applicant returned to address corrections 1/2/2020 ABDUL CHEGENI
Applicant returned to address corrections 1/27/2020 ABDUL CHEGENI
Applicant returned to address corrections 1/29/2020 ABDUL CHEGENI
Plan Check Approved 2/19/2020 ABDUL CHEGENI
Issued 6/30/2020 LADBS
CofO in Progress 10/1/2024 CHRISTOPHER WILSON
Permit Finaled 10/15/2024 RICHARD STEINBACH
CofO Issued 10/15/2024 RICHARD STEINBACH
Permit Finaled 10/15/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/11/2019 JOHN LIN
BHO/Hillside ordinance Cleared 10/11/2019 JOHN LIN
BHO/Hillside ordinance Cleared 10/11/2019 JOHN LIN
BHO/Hillside ordinance Cleared 10/11/2019 JOHN LIN
BHO/Hillside ordinance Cleared 10/11/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 10/11/2019 JOHN LIN
Highway dedication Cleared 10/11/2019 JOHN LIN
Permit Cleared 10/11/2019 JOHN LIN
Sewer availability Cleared 10/11/2019 JOHN LIN
Green Code Cleared 12/12/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 12/17/2019 GEORGE SUCHAND
Specific Plan Cleared 12/23/2019 STEVEN WECHSLER
ZA Case Cleared 12/23/2019 STEVEN WECHSLER
Trees in Parkway Cleared 12/31/2019 ADRIAN SANCHEZ
Disturb/Remove Protected Trees Cleared 1/10/2020 STEPHEN DUPREY
Low Impact Development Cleared 1/10/2020 SARAH YOUSSEF
GPI Written Notices Cleared 1/27/2020 ABDUL CHEGENI
Grading Pre-Inspection Cleared 1/27/2020 ABDUL CHEGENI
Miscellaneous Cleared 1/27/2020 ABDUL CHEGENI
Roof/Waste drainage to street Cleared 1/29/2020 LEE GUILBEAUX

Contact Information

Contractor Quadrant Inc; Lic. No.: 543948-B 7586 WOODROW WILSON DR      LOS ANGELES, CA 90046
Engineer Jitechian,, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504
Engineer Lombera,, Raymundo A; Lic. No.: L7740 135 S JACKSON STREET #202      GLENDALE, CA 91205
Engineer Yogurtian,, Arpinee; Lic. No.: C49916 2529 FOOTHILL BLVD, STE 208      LA CRESCENTA, CA 91214
Geologist Miller,, Steven Burl; Lic. No.: EG1303 23890 COPPERHILL DRIVE #111      VALENCIA, CA 91354

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/30/2021 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 11/10/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/25/2022 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 1/28/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/12/2022 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 7/12/2022 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 7/15/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 7/15/2022 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/18/2022 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/18/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/18/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 7/18/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/19/2022 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 8/18/2022 Conditional Approval CHRISTOPHER WILSON
Structural Steel Frame 9/22/2022 Approved CHRISTOPHER WILSON
Deputy Wood Construction 9/30/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 10/3/2022 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 10/3/2022 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 10/3/2022 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Partial Approval CHRISTOPHER WILSON
Green Building Rough 10/5/2022 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 10/5/2022 Not Ready for Inspection CHRISTOPHER WILSON
Structural Steel Frame 11/7/2022 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/29/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 12/29/2022 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 3/30/2023 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/3/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 4/3/2023 Approved CHRISTOPHER WILSON
HVAC-Rough 4/5/2023 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 4/14/2023 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 4/17/2023 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 4/25/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 4/25/2023 Approved CHRISTOPHER WILSON
Green Building Rough 4/25/2023 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 4/25/2023 Approved CHRISTOPHER WILSON
Deputy Drilled-In Anchors 5/3/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Partial Approval CHRISTOPHER WILSON
Green Building Rough 5/19/2023 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 5/19/2023 Partial Inspection MICHAEL PELHAM
Wood Frame 5/19/2023 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/27/2023 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 6/27/2023 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 6/27/2023 Partial Approval CHRISTOPHER WILSON
Wood Frame 6/27/2023 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 7/7/2023 Corrections Issued CHRISTOPHER WILSON
Wood Frame 7/7/2023 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 7/12/2023 Approved CHRISTOPHER WILSON
Green Building Rough 7/12/2023 Approved CHRISTOPHER WILSON
Insulation 7/25/2023 Approved STEPHANIE SWANSON
Drywall Nailing 8/2/2023 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 8/28/2023 Approved CHRISTOPHER WILSON
PLUMBING-Rough 1/5/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 4/18/2024 Corrections Issued CARLOS MATAMOROS
Gas Test 4/18/2024 Approved CARLOS MATAMOROS
PLUMBING-Final 4/18/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Final 4/25/2024 Approved CHRISTOPHER WILSON
HVAC-Final 4/25/2024 Approved CHRISTOPHER WILSON
Service/Power Release 4/25/2024 Approved CHRISTOPHER WILSON
Pre-Inspection 4/29/2024 Corrections Issued CHRISTOPHER WILSON
Final 9/16/2024 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 9/16/2024 Approved CHRISTOPHER WILSON
Green Building Final 9/16/2024 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 9/16/2024 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 9/16/2024 Approved CHRISTOPHER WILSON
Final 9/30/2024 OK to Issue CofO CHRISTOPHER WILSON
Green Building Final 9/30/2024 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Approved CHRISTOPHER WILSON