641 N HOBART BLVD #1 - #14 90004

Certificate Information: 641 N HOBART BLVD #1 - #14 90004

Application / Permit
19010-20000-01620
Plan Check / Job No.
B19VN06228
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(1 OF 3) NEW 4-STORY 14 UNIT APT WITH 1 LEVEL SUBTERRANEAN PARKING. WITH 32.5% DENSITY BONUS, SET ASIDE 10% VERY LOW INCOME UNITS.
Permit Issued
Issued on 1/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2019 APPLICANT
Disabled Access Plans Picked Up 5/1/2019 APPLICANT
Green Plans Picked Up 5/1/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 CHON CHIO KUO
Corrections Issued 5/6/2019 CHON CHIO KUO
Quality Review Completed 5/7/2019 STEVEN KIM
Building Plans Picked Up 5/15/2019 APPLICANT
Applicant returned to address corrections 7/16/2019 CHON CHIO KUO
Applicant returned to address corrections 12/18/2019 CHON CHIO KUO
Applicant returned to address corrections 12/27/2019 CHON CHIO KUO
Plan Check Approved 1/2/2020 CHON CHIO KUO
Issued 1/3/2020 LADBS
CofO in Progress 12/13/2022 DAVID BURKHEAD
No Progress 12/15/2022 DAVID BURKHEAD
TCO Issued (Expire Date: 06-13-2023) 12/15/2022 ERNESTO CORRAL
CofO in Progress 12/30/2022 DAVID BURKHEAD
Permit Finaled 2/16/2023 TED RIES
CofO Issued 2/16/2023 TED RIES
Permit Finaled 2/16/2023 TED RIES

Permit Application Clearance Information

Address approval Cleared 6/11/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/11/2019 LEE GUILBEAUX
Highway dedication Cleared 6/11/2019 LEE GUILBEAUX
Permit Cleared 6/11/2019 LEE GUILBEAUX
Sewer availability Cleared 6/11/2019 LEE GUILBEAUX
Hydrant and Access approval Cleared 6/25/2019 GEORGE SUCHAND
Density Bonus 12.22.A.25 Cleared 7/22/2019 JACOB COMER
Trees in Parkway Cleared 7/26/2019 ADRIAN SANCHEZ
Frnt yard landscape/Water mgmt Cleared 8/22/2019 RINA LARA
Opn space landscape/Water mgmt Cleared 8/22/2019 RINA LARA
Prkng lot landscape/Water mgmt Cleared 8/22/2019 RINA LARA
DAS Clearance Cleared 11/26/2019 NORLITO MEDRANO
Green Code Cleared 11/26/2019 MICHAEL AYERS
Work Adjacent to Public Way Cleared 12/3/2019 BOK GOH
Fire Marshall Fire Life Safety Cleared 12/13/2019 DOMINIQUE MEDINA
Low Impact Development Cleared 12/16/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/17/2019 CHRISTINE REUSCH
Building over 3-story or 36-ft Cleared 12/27/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/27/2019 CALOSHA APPROVED

Contact Information

Architect Sammie, Tbrizi; Lic. No.: C34954 21731 AMBAR DR      WOODLAND HILL, CA 91364
Contractor Schon Tepler Construction, Inc; Lic. No.: 969338-B 6250 HOLLYWOOOD BLVD 10L      LOS ANGELES, CA 90028
Engineer Foroughi,, Mohammad Hossein; Lic. No.: C66179 767 NORTH HILL STREET 407      LOS ANGELES, CA 90012
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/31/2020 Partial Inspection DAVID BURKHEAD
Pre-Inspection 4/21/2020 Approved DAVID BURKHEAD
Deputy Grading 4/23/2020 Conditional Approval DAVID BURKHEAD
Deputy Grading 4/24/2020 Conditional Approval DAVID BURKHEAD
Deputy Grading 4/27/2020 Conditional Approval DAVID BURKHEAD
Deputy Grading 4/28/2020 Conditional Approval DAVID BURKHEAD
Deputy Grading 4/29/2020 Conditional Approval DAVID BURKHEAD
Deputy Grading 5/11/2020 Conditional Approval DAVID BURKHEAD
Deputy Grading 5/12/2020 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 7/9/2020 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/15/2020 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 7/15/2020 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/29/2020 Partial Inspection DAVID BURKHEAD
Deputy Shotcrete 7/30/2020 Approved DAVID BURKHEAD
Green Building Rough 7/30/2020 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 7/30/2020 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 7/30/2020 Not Ready for Inspection DAVID BURKHEAD
Deputy Other (see comments) 8/4/2020 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 8/4/2020 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 8/5/2020 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/1/2020 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/11/2020 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 9/11/2020 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 9/11/2020 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/12/2020 Off-Hour Fees Due
Footing/Foundation/Slab 9/12/2020 Off-Hour Fees Due
Green Building Rough 9/12/2020 Off-Hour Fees Due
Masonry Wall/Backfill 9/12/2020 Off-Hour Fees Due
Piling/Pier/Caisson 9/12/2020 Off-Hour Fees Due
Reinforced Concrete Frame 9/12/2020 Off-Hour Fees Due
Reinforced Masonry Frame 9/12/2020 Off-Hour Fees Due
Structural Steel Frame 9/12/2020 Off-Hour Fees Due
Verify Sprinkler Sign Off 9/12/2020 Off-Hour Fees Due
Wood Frame 9/12/2020 Off-Hour Fees Due
Green Building Rough 9/30/2020 Not Ready for Inspection DAVID BURKHEAD
Reinforced Masonry Frame 9/30/2020 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 9/30/2020 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 11/5/2020 Partial Approval DAVID BURKHEAD
Green Building Rough 11/5/2020 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 11/5/2020 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/23/2020 Partial Approval DAVID BURKHEAD
Green Building Rough 12/17/2020 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 12/17/2020 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 12/17/2020 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 12/24/2020 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 12/24/2020 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 12/24/2020 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 1/5/2021 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 1/5/2021 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 1/5/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Wood Construction 1/25/2021 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 1/25/2021 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 2/12/2021 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/13/2021 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 5/17/2021 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 6/14/2021 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 6/23/2021 Partial Approval DAVID BURKHEAD
Wood Frame 7/19/2021 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 8/4/2021 Partial Inspection DAVID BURKHEAD
Insulation 8/30/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 10/18/2021 Partial Approval DANIEL MC AULIFFE
Drywall Nailing 10/25/2021 Partial Inspection DAVID BURKHEAD
Interior/Exterior Lathing 11/1/2021 Approved DAVID BURKHEAD
Drywall Nailing 11/15/2021 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 11/15/2021 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 11/22/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 11/29/2021 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 12/3/2021 Partial Approval DAVID BURKHEAD
Drywall Nailing 12/6/2021 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 12/16/2021 Approved DAVID BURKHEAD
Pre-Inspection 5/19/2022 Approved DAVID BURKHEAD
Pre-Inspection 10/20/2022 Corrections Issued DAVID BURKHEAD
Final 10/27/2022 Corrections Issued DAVID BURKHEAD
Footing/Foundation/Slab 10/27/2022 Approved DAVID BURKHEAD
Green Building Final 10/27/2022 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 10/27/2022 Approved DAVID BURKHEAD
Reinforced Concrete Frame 10/27/2022 Approved DAVID BURKHEAD
Reinforced Masonry Frame 10/27/2022 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 10/27/2022 Not Ready for Inspection DAVID BURKHEAD
Structural Steel Frame 10/27/2022 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 10/27/2022 Approved DAVID BURKHEAD
Final 11/28/2022 Partial Inspection DAVID BURKHEAD
Green Building Final 11/28/2022 Partial Inspection DAVID BURKHEAD
Smoke Detectors 11/28/2022 Approved DAVID BURKHEAD
Structural Steel Frame 11/28/2022 Approved DAVID BURKHEAD
Final 12/5/2022 Partial Inspection DAVID BURKHEAD
Green Building Final 12/5/2022 Approved DAVID BURKHEAD
Final 12/8/2022 OK to Issue CofO DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Approved DAVID BURKHEAD