7762 N LURLINE AVE 91306
Certificate Information: 7762 N LURLINE AVE 91306
- Application / Permit
- 19010-20000-01610
- Plan Check / Job No.
- B19VN06178
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 24' X 50' 1-STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK DONE PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 10/21/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | GURUNATH NESARAJAH |
| Green Plans Picked Up | 5/17/2019 | APPLICANT |
| Corrections Issued | 5/23/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 5/24/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 5/28/2019 | APPLICANT |
| Plan Check Approved | 10/18/2019 | GURUNATH NESARAJAH |
| Issued | 10/21/2019 | LADBS |
| CofO in Progress | 2/26/2021 | HENRY KIM |
| Permit Finaled | 3/1/2021 | JOHN JANSON |
| CofO Issued | 3/1/2021 | JOHN JANSON |
| Permit Finaled | 3/1/2021 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/15/2019 | RIDWAN HARDY |
| Address approval | Cleared | 9/18/2019 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 9/18/2019 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 10/8/2019 | PARISA ZAHABI |
| Hydrant and Access approval | Cleared | 10/8/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 10/15/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/16/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/2/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 6/19/2020 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 6/26/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2020 | Partial Approval | HENRY KIM |
| HVAC-Rough | 7/22/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 8/6/2020 | Approved | HENRY KIM |
| HVAC-Rough | 8/6/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 8/11/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2020 | Approved | HENRY KIM |
| Green Building Rough | 8/11/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 8/11/2020 | Approved | HENRY KIM |
| Verify Sprinkler Sign Off | 8/11/2020 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 8/18/2020 | Approved | HENRY KIM |
| Green Building Rough | 8/18/2020 | Approved | HENRY KIM |
| Insulation | 8/18/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 8/18/2020 | Approved | HENRY KIM |
| Drywall Nailing | 9/16/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 9/16/2020 | Approved | HENRY KIM |
| Sewer | 10/15/2020 | Approved | HENRY KIM |
| Underground Mechanical | 10/15/2020 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 10/26/2020 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Final | 12/3/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 12/9/2020 | Approved | HENRY KIM |
| PLUMBING-Final | 1/20/2021 | Corrections Issued | HENRY KIM |
| Final | 2/12/2021 | Corrections Issued | HENRY KIM |
| Gas Test | 2/12/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 2/12/2021 | Approved | HENRY KIM |
| HVAC-Final | 2/12/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 2/12/2021 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 2/12/2021 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 2/12/2021 | Approved | HENRY KIM |
| Final | 2/23/2021 | Not Ready for Inspection | HENRY KIM |
| Gas Test | 2/23/2021 | Approved | HENRY KIM |
| Final | 2/26/2021 | OK to Issue CofO | HENRY KIM |