21731 W TUBA ST 91311

Certificate Information: 21731 W TUBA ST 91311

Application / Permit
19010-20000-01585
Plan Check / Job No.
B19VN06095
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (32'-0"x 38'-0") DETACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229. WORK PER LA STD WFPP.
Permit Issued
Issued on 8/1/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 TROY DEGUZMAN
Green Plans Picked Up 5/16/2019 APPLICANT
Corrections Issued 5/22/2019 TROY DEGUZMAN
Quality Review Completed 5/24/2019 STEVEN KIM
Building Plans Picked Up 6/18/2019 APPLICANT
Plan Check Approved 7/31/2019 TROY DEGUZMAN
Issued 8/1/2019 LADBS
CofO in Progress 3/11/2022 PETER FOLLING
Permit Finaled 3/25/2022 DEROLD HAUFF
CofO Issued 3/25/2022 DEROLD HAUFF
Permit Finaled 3/25/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/25/2019 LEE GUILBEAUX
Sewer availability Cleared 6/25/2019 LEE GUILBEAUX
Construction near power lines Cleared 7/2/2019 NADER ISKANDER
ZI Cleared 7/9/2019 ANNA VIDAL
Green Code Cleared 7/18/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 7/29/2019 GEORGE SUCHAND
Low Impact Development Cleared 7/30/2019 ANDRES COVARRUBIAS
Address approval Cleared 7/31/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 7/31/2019 GUILLERMO PETRA

Contact Information

Contractor Mukherjee Mani; Lic. No.: 450270-B 4408 TOSCA ROAD      WOODLAND HILLS, CA 91364

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/18/2019 Partial Approval PETER FOLLING
Footing/Foundation/Slab 9/23/2019 Not Ready for Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 9/26/2019 Approved PETER FOLLING
Footing/Foundation/Slab 9/26/2019 Approved PETER FOLLING
ELECTRICAL-Rough 11/1/2019 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 11/1/2019 Approved PETER FOLLING
Green Building Rough 11/1/2019 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 11/1/2019 Not Ready for Inspection PETER FOLLING
Verify Sprinkler Sign Off 11/1/2019 Not Ready for Inspection PETER FOLLING
Green Building Rough 11/6/2019 Approved PETER FOLLING
HVAC-Rough 11/6/2019 Approved PETER FOLLING
PLUMBING-Rough 11/6/2019 Approved PETER FOLLING
ELECTRICAL-Rough 11/13/2019 Approved PETER FOLLING
BUILDING-Rough-Frame 11/21/2019 Approved PETER FOLLING
Interior/Exterior Lathing 11/21/2019 Partial Approval PETER FOLLING
Verify Sprinkler Sign Off 11/21/2019 Approved PETER FOLLING
Insulation 11/27/2019 Approved PETER FOLLING
Drywall Nailing 12/4/2019 Approved PETER FOLLING
Final 5/20/2020 Corrections Issued DAVID STEPANYAN
Green Building Final 5/20/2020 Not Ready for Inspection DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 5/20/2020 SGSOV Not Ready DAVID STEPANYAN
Service/Power Release 5/20/2020 Not Ready for Inspection DAVID STEPANYAN
Smoke Detectors 5/20/2020 Approved DAVID STEPANYAN
Final 10/21/2020 Corrections Issued DAVID STEPANYAN
Green Building Final 10/21/2020 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 10/21/2020 SGSOV Not Ready DAVID STEPANYAN
Service/Power Release 10/21/2020 Not Ready for Inspection DAVID STEPANYAN
Final 3/23/2021 No Access for Inspection JEFFREY PARD
Green Building Final 3/23/2021 No Access for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 3/23/2021 SGSOV Not Ready JEFFREY PARD
Service/Power Release 3/23/2021 No Access for Inspection JEFFREY PARD
Final 4/28/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 4/28/2021 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 4/28/2021 SGSOV Not Ready DAVID STEPANYAN
Service/Power Release 4/28/2021 Not Required DAVID STEPANYAN
Final 5/27/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 5/27/2021 SGSOV Approved DAVID STEPANYAN
Final 2/23/2022 Not Ready for Inspection DAVID SCANTLIN
Final 3/10/2022 OK to Issue CofO PETER FOLLING
Service/Power Release 3/10/2022 Approved PETER FOLLING