21731 W TUBA ST 91311
Certificate Information: 21731 W TUBA ST 91311
- Application / Permit
- 19010-20000-01585
- Plan Check / Job No.
- B19VN06095
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (32'-0"x 38'-0") DETACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229. WORK PER LA STD WFPP.
- Permit Issued
- Issued on 8/1/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | TROY DEGUZMAN |
| Green Plans Picked Up | 5/16/2019 | APPLICANT |
| Corrections Issued | 5/22/2019 | TROY DEGUZMAN |
| Quality Review Completed | 5/24/2019 | STEVEN KIM |
| Building Plans Picked Up | 6/18/2019 | APPLICANT |
| Plan Check Approved | 7/31/2019 | TROY DEGUZMAN |
| Issued | 8/1/2019 | LADBS |
| CofO in Progress | 3/11/2022 | PETER FOLLING |
| Permit Finaled | 3/25/2022 | DEROLD HAUFF |
| CofO Issued | 3/25/2022 | DEROLD HAUFF |
| Permit Finaled | 3/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/25/2019 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 7/2/2019 | NADER ISKANDER |
| ZI | Cleared | 7/9/2019 | ANNA VIDAL |
| Green Code | Cleared | 7/18/2019 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 7/29/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 7/30/2019 | ANDRES COVARRUBIAS |
| Address approval | Cleared | 7/31/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 7/31/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Mukherjee Mani; Lic. No.: 450270-B | 4408 TOSCA ROAD WOODLAND HILLS, CA 91364 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/18/2019 | Partial Approval | PETER FOLLING |
| Footing/Foundation/Slab | 9/23/2019 | Not Ready for Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/26/2019 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 9/26/2019 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 11/1/2019 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2019 | Approved | PETER FOLLING |
| Green Building Rough | 11/1/2019 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 11/1/2019 | Not Ready for Inspection | PETER FOLLING |
| Verify Sprinkler Sign Off | 11/1/2019 | Not Ready for Inspection | PETER FOLLING |
| Green Building Rough | 11/6/2019 | Approved | PETER FOLLING |
| HVAC-Rough | 11/6/2019 | Approved | PETER FOLLING |
| PLUMBING-Rough | 11/6/2019 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 11/13/2019 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 11/21/2019 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 11/21/2019 | Partial Approval | PETER FOLLING |
| Verify Sprinkler Sign Off | 11/21/2019 | Approved | PETER FOLLING |
| Insulation | 11/27/2019 | Approved | PETER FOLLING |
| Drywall Nailing | 12/4/2019 | Approved | PETER FOLLING |
| Final | 5/20/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 5/20/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 5/20/2020 | SGSOV Not Ready | DAVID STEPANYAN |
| Service/Power Release | 5/20/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Smoke Detectors | 5/20/2020 | Approved | DAVID STEPANYAN |
| Final | 10/21/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 10/21/2020 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 10/21/2020 | SGSOV Not Ready | DAVID STEPANYAN |
| Service/Power Release | 10/21/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Final | 3/23/2021 | No Access for Inspection | JEFFREY PARD |
| Green Building Final | 3/23/2021 | No Access for Inspection | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 3/23/2021 | SGSOV Not Ready | JEFFREY PARD |
| Service/Power Release | 3/23/2021 | No Access for Inspection | JEFFREY PARD |
| Final | 4/28/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Final | 4/28/2021 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 4/28/2021 | SGSOV Not Ready | DAVID STEPANYAN |
| Service/Power Release | 4/28/2021 | Not Required | DAVID STEPANYAN |
| Final | 5/27/2021 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 5/27/2021 | SGSOV Approved | DAVID STEPANYAN |
| Final | 2/23/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 3/10/2022 | OK to Issue CofO | PETER FOLLING |
| Service/Power Release | 3/10/2022 | Approved | PETER FOLLING |