10004 N CORBIN AVE 91324

Certificate Information: 10004 N CORBIN AVE 91324

Application / Permit
19010-20000-01538
Plan Check / Job No.
B19VN05974
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21’-8” X 59’-0” DETACHED 1-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 5/14/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2019 APPLICANT
Green Plans Picked Up 4/22/2019 APPLICANT
Assigned to Plan Check Engineer 4/25/2019 JENNIFER LEE
Corrections Issued 4/30/2019 JENNIFER LEE
Quality Review Completed 5/1/2019 STEVEN KIM
Building Plans Picked Up 5/1/2019 APPLICANT
Plan Check Approved 5/13/2019 JENNIFER LEE
Issued 5/14/2019 LADBS
CofO in Progress 12/3/2020 JEFFREY PARD
Permit Finaled 12/3/2020 JOHN JANSON
CofO Issued 12/3/2020 JOHN JANSON
Permit Finaled 12/3/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/6/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/6/2019 JEANETTE VONG
Hydrant and Access approval Cleared 5/6/2019 ROBERT DUFF
Sewer availability Cleared 5/6/2019 JEANETTE VONG
Green Code Cleared 5/7/2019 DAVID MATSON
Low Impact Development Cleared 5/10/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/10/2019 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/1/2019 Partial Approval VINCENT HANLEY
Sewer 10/1/2019 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 10/10/2019 Approved VINCENT HANLEY
ELECTRICAL-Rough 10/31/2019 Approved COREY HUPP
PLUMBING-Rough 11/1/2019 Approved COREY HUPP
BUILDING-Rough-Frame 11/8/2019 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/8/2019 Approved VINCENT HANLEY
Green Building Rough 11/8/2019 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 11/8/2019 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 11/8/2019 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 11/8/2019 Not Ready for Inspection VINCENT HANLEY
Interior/Exterior Lathing 11/16/2019 Corrections Issued JOSEPH SAGEN
HVAC-Rough 11/21/2019 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/21/2019 Partial Approval VINCENT HANLEY
Wood Frame 11/21/2019 Approved VINCENT HANLEY
Insulation 11/23/2019 Approved JOSEPH SAGEN
Shower Pan 11/23/2019 Approved JOSEPH SAGEN
Drywall Nailing 11/29/2019 Approved JOSEPH SAGEN
Green Building Rough 11/29/2019 Approved JOSEPH SAGEN
Interior/Exterior Lathing 11/29/2019 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 1/28/2020 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 1/28/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 1/28/2020 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 1/28/2020 Approved KATHRYN BUTTERWORTH
HVAC-Final 1/28/2020 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Final 1/28/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 1/28/2020 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 1/28/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 1/28/2020 Corrections Issued KATHRYN BUTTERWORTH
Final 2/18/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 2/18/2020 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 2/18/2020 Not Required KATHRYN BUTTERWORTH
Smoke Detectors 2/18/2020 Approved KATHRYN BUTTERWORTH
Final 5/1/2020 Not Ready for Inspection JOHN KIDWELL
Final 11/16/2020 Not Ready for Inspection DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/16/2020 SGSOV Approved DAVID STEPANYAN
Final 12/1/2020 OK to Issue CofO JEFFREY PARD