617-617 1/2 W 79TH ST 90044
Certificate Information: 617-617 1/2 W 79TH ST 90044
- Application / Permit
- 19010-20000-01514
- Plan Check / Job No.
- B19VN05961
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 56' X 40' TWO STORY DUPLEX WITH 40' X 33'8" FOUR CAR GARAGE , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/10/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 10/2/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2019 | RARES BODEA |
| Corrections Issued | 4/27/2019 | RARES BODEA |
| Quality Review Completed | 4/30/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 5/1/2019 | APPLICANT |
| Green Plans Picked Up | 5/1/2019 | APPLICANT |
| Plan Check Approved | 6/21/2019 | RARES BODEA |
| Issued | 10/10/2019 | LADBS |
| CofO in Progress | 7/20/2020 | EUGENE CASSIDY |
| Permit Finaled | 10/2/2020 | DEROLD HAUFF |
| CofO Issued | 10/2/2020 | DEROLD HAUFF |
| Permit Finaled | 10/2/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2019 | ELENA LOPEZ |
| Frnt yard landscape/Water mgmt | Cleared | 6/13/2019 | SOPHIE GABEL-SCHEINBAU |
| Hydrant and Access approval | Cleared | 6/13/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 6/13/2019 | SEAN SHAHMIRI |
| Roof/Waste drainage to street | Cleared | 6/13/2019 | ELENA LOPEZ |
| Sewer availability | Cleared | 6/13/2019 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2019 | ADRIAN SANCHEZ |
| Highway dedication | Cleared | 6/14/2019 | ADRIAN SANCHEZ |
| Green Code | Cleared | 6/17/2019 | DAVID MATSON |
Contact Information
| Contractor | Mgbd Inc; Lic. No.: 1021337-B | 5940 OAK AVE #1442 TEMPLE CITY, CA 91780 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 26851 GRAYSLAKE ROAD RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/15/2019 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2019 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2019 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 1/8/2020 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 1/8/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 1/8/2020 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 1/8/2020 | Approved | EUGENE CASSIDY |
| Insulation | 1/16/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 1/28/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/28/2020 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/28/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/4/2020 | Corrections Issued | EUGENE CASSIDY |
| Final | 6/4/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/4/2020 | Approved | EUGENE CASSIDY |
| Green Building Final | 6/4/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/4/2020 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 6/4/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 6/4/2020 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 6/4/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/11/2020 | Approved | EUGENE CASSIDY |
| Final | 6/11/2020 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 6/11/2020 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 6/11/2020 | Approved | EUGENE CASSIDY |
| Final | 7/20/2020 | OK to Issue CofO | EUGENE CASSIDY |