18239 W MARGATE ST 91356
Certificate Information: 18239 W MARGATE ST 91356
- Application / Permit
- 19010-20000-01504
- Plan Check / Job No.
- B19VN05924
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 27'-3" X 62'-0" IRREGULAR DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2019 | JENNIFER LEE |
| Green Plans Picked Up | 4/25/2019 | APPLICANT |
| Corrections Issued | 5/1/2019 | JENNIFER LEE |
| Quality Review Completed | 5/1/2019 | STEVEN KIM |
| Building Plans Picked Up | 5/2/2019 | APPLICANT |
| Plan Check Approved | 11/5/2019 | JENNIFER LEE |
| Issued | 2/4/2020 | LADBS |
| CofO in Progress | 11/10/2020 | DAVID SANDOVAL |
| CofO Issued | 11/10/2020 | MICHAEL SMITH |
| Permit Finaled | 11/10/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 6/10/2019 | PARISA ZAHABI |
| Address approval | Cleared | 7/17/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/24/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 8/30/2019 | RIDWAN HARDY |
| Low Impact Development | Cleared | 9/25/2019 | RYAN HUDSON |
| Hydrant and Access approval | Cleared | 11/1/2019 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 11/1/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/11/2020 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 5/14/2020 | Partial Approval | DAVID SANDOVAL |
| Sewer | 5/14/2020 | Approved | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 5/28/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 5/28/2020 | Corrections Issued | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 6/2/2020 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 6/2/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 7/28/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 7/28/2020 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2020 | Partial Approval | DAVID SANDOVAL |
| HVAC-Rough | 7/28/2020 | Corrections Issued | DAVID SANDOVAL |
| MERV13>=Rough | 7/28/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 7/28/2020 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2020 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 7/30/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 8/7/2020 | Approved | DAVID SANDOVAL |
| Green Building Rough | 8/7/2020 | Approved | DAVID SANDOVAL |
| Insulation | 8/7/2020 | Approved | DAVID SANDOVAL |
| MERV13>=Rough | 8/7/2020 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 8/14/2020 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/14/2020 | Partial Approval | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/24/2020 | Approved | DAVID SANDOVAL |
| Final | 9/30/2020 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 9/30/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| MERV13>=Final | 9/30/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 9/30/2020 | SGSOV Not Ready | DAVID SANDOVAL |
| Service/Power Release | 9/30/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Smoke Detectors | 9/30/2020 | Approved | DAVID SANDOVAL |
| Final | 11/9/2020 | OK to Issue CofO | DAVID SANDOVAL |
| Green Building Final | 11/9/2020 | Approved | DAVID SANDOVAL |
| MERV13>=Final | 11/9/2020 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 11/9/2020 | SGSOV Approved | DAVID SANDOVAL |
| Service/Power Release | 11/9/2020 | Approved | DAVID SANDOVAL |