Deputy Reinf. Concrete
|
1/16/2020
|
Conditional Approval
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
2/21/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
2/21/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Deputy Reinf. Concrete
|
2/24/2020
|
No Access for Inspection
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
2/28/2020
|
Corrections Issued
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
2/28/2020
|
Corrections Issued
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
3/3/2020
|
Partial Inspection
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
3/3/2020
|
Partial Inspection
|
DANNY TOLENTINO
|
|
Deputy Reinf. Concrete
|
3/6/2020
|
Conditional Approval
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
3/6/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
3/6/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
3/20/2020
|
No Access for Inspection
|
ROBERT SHELLY
|
|
Piling/Pier/Caisson
|
3/20/2020
|
No Access for Inspection
|
ROBERT SHELLY
|
|
Excavation/Setback/Form/Re-Bar
|
3/24/2020
|
Corrections Issued
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
3/24/2020
|
Corrections Issued
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
3/25/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
3/25/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
3/27/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
3/27/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
PLUMBING-Rough
|
5/20/2020
|
Corrections Issued
|
DANNY TOLENTINO
|
|
PLUMBING-Rough
|
5/22/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
5/27/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Deputy Reinf. Concrete
|
5/28/2020
|
No Access for Inspection
|
DANNY TOLENTINO
|
|
Deputy Reinf. Concrete
|
5/29/2020
|
No Access for Inspection
|
DANNY TOLENTINO
|
|
Deputy Shotcrete
|
6/8/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Excavation/Setback/Form/Re-Bar
|
6/9/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Deputy Shotcrete
|
6/11/2020
|
Approved
|
ROBERT SHELLY
|
|
Deputy Shotcrete
|
6/15/2020
|
No Access for Inspection
|
ROBERT SHELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/16/2020
|
Not Ready for Inspection
|
ROBERT SHELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/17/2020
|
Partial Approval
|
ROBERT SHELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/30/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Wood Frame
|
7/31/2020
|
Not Ready for Inspection
|
ROBERT SHELLY
|
|
Wood Frame
|
8/3/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Excavation/Setback/Form/Re-Bar
|
8/7/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Piling/Pier/Caisson
|
8/7/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Deputy Reinf. Concrete
|
8/14/2020
|
Approved
|
JOHN KIDWELL
|
|
Excavation/Setback/Form/Re-Bar
|
8/14/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
PLUMBING-Rough
|
8/14/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Excavation/Setback/Form/Re-Bar
|
8/18/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Footing/Foundation/Slab
|
8/18/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Footing/Foundation/Slab
|
8/20/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Deputy Reinf. Concrete
|
8/21/2020
|
Corrections Issued
|
ROBERT SHELLY
|
|
Excavation/Setback/Form/Re-Bar
|
8/31/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/2/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Interior/Exterior Lathing
|
9/15/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
HVAC-Rough
|
9/16/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
ELECTRICAL-Rough
|
9/17/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Gas Test
|
9/17/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
PLUMBING-Rough
|
9/17/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
BUILDING-Rough-Frame
|
9/18/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
ELECTRICAL-Rough
|
9/18/2020
|
Approved
|
JOHN KIDWELL
|
|
HVAC-Rough
|
9/18/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
PLUMBING-Final
|
9/18/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
PLUMBING-Rough
|
9/18/2020
|
Approved
|
JOHN KIDWELL
|
|
BUILDING-Rough-Frame
|
9/22/2020
|
Approved
|
JOHN KIDWELL
|
|
Green Building Rough
|
9/22/2020
|
Approved
|
JOHN KIDWELL
|
|
HVAC-Rough
|
9/22/2020
|
Approved
|
JOHN KIDWELL
|
|
Verify Sprinkler Sign Off
|
9/22/2020
|
Approved
|
JOHN KIDWELL
|
|
Insulation
|
9/23/2020
|
Approved
|
JOHN KIDWELL
|
|
Drywall Nailing
|
10/5/2020
|
Approved
|
JOHN KIDWELL
|
|
Interior/Exterior Lathing
|
10/9/2020
|
Approved
|
JOHN KIDWELL
|
|
Shower Pan
|
10/9/2020
|
Approved
|
JOHN KIDWELL
|
|
Gas Test
|
12/18/2020
|
Partial Approval
|
MICHAEL PELHAM
|
|
Sewer
|
12/18/2020
|
Approved
|
MICHAEL PELHAM
|
|
Underground Mechanical
|
12/18/2020
|
Partial Approval
|
MICHAEL PELHAM
|
|
HVAC-Final
|
2/5/2021
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
HVAC-Final
|
2/24/2021
|
Approved
|
JOHN KIDWELL
|
|
PLUMBING-Final
|
2/26/2021
|
Approved
|
JOHN KIDWELL
|
|
ELECTRICAL-Final
|
3/12/2021
|
Approved
|
JOHN KIDWELL
|
|
Smoke Detectors
|
3/22/2021
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Service/Power Release
|
3/24/2021
|
Approved
|
JOHN KIDWELL
|
|
Final
|
4/7/2021
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Footing/Foundation/Slab
|
4/7/2021
|
Approved
|
JOHN KIDWELL
|
|
Green Building Final
|
4/7/2021
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Reinforced Concrete Frame
|
4/7/2021
|
Approved
|
JOHN KIDWELL
|
|
SGSOV-Seismic Gas S/O Valve
|
4/7/2021
|
SGSOV Not Ready
|
JOHN KIDWELL
|
|
Smoke Detectors
|
4/7/2021
|
Approved
|
JOHN KIDWELL
|
|
Special/Order Compliance
|
4/7/2021
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Verify Rec and Parks Fee Memo
|
4/7/2021
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
SGSOV-Seismic Gas S/O Valve
|
4/12/2021
|
SGSOV Approved
|
JOHN KIDWELL
|
|
Special/Order Compliance
|
4/12/2021
|
Partial Inspection
|
JOHN KIDWELL
|
|
Final
|
4/13/2021
|
OK to Issue CofO
|
JOHN KIDWELL
|
|
Green Building Final
|
4/13/2021
|
Approved
|
JOHN KIDWELL
|