439 N VIA DE LA PAZ 90272
Certificate Information: 439 N VIA DE LA PAZ 90272
- Application / Permit
- 19010-20000-01489
- Plan Check / Job No.
- B19VN05815
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 11/19/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 4/29/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/1/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 5/3/2019 | APPLICANT |
| Green Plans Picked Up | 5/3/2019 | APPLICANT |
| Applicant returned to address corrections | 6/17/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 8/2/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/19/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/2/2019 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/18/2019 | NILOOFAR MEHRAIN |
| Issued | 11/19/2019 | LADBS |
| CofO in Progress | 7/2/2021 | ANDREW NAVE |
| Permit Finaled | 7/9/2021 | KENNETH NAGLE |
| CofO Issued | 7/9/2021 | KENNETH NAGLE |
| Permit Finaled | 7/9/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2019 | LEE GUILBEAUX |
| Coastal Zone | Cleared | 6/17/2019 | ANNA VIDAL |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2019 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 6/17/2019 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 6/17/2019 | NILOOFAR MEHRAIN |
| Miscellaneous | Cleared | 6/17/2019 | ANNA VIDAL |
| Sewer availability | Cleared | 6/17/2019 | LEE GUILBEAUX |
| ZI | Cleared | 6/17/2019 | ANNA VIDAL |
| Hydrant and Access approval | Cleared | 7/11/2019 | GILBERT URREA |
| Excavation more than 5-ft deep | Cleared | 9/19/2019 | CALOSHA APPROVED |
| Permit | Cleared | 9/23/2019 | EMIL KYUPELYAN |
| Trees in Parkway | Cleared | 9/26/2019 | ADRIAN SANCHEZ |
| Green Code | Cleared | 10/10/2019 | DAVID MATSON |
| Low Impact Development | Cleared | 10/28/2019 | SARAH YOUSSEF |
| Miscellaneous | Cleared | 11/14/2019 | KIT AWAKUNI |
| Miscellaneous | Cleared | 11/14/2019 | KIT AWAKUNI |
| Roof/Waste drainage to street | Cleared | 11/18/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | J L M Development; Lic. No.: 1025019-B | 1301 WEST 35TH PLACE LOS ANGELES, CA 90007 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/2/2020 | Not Ready for Inspection | ANDREW NAVE |
| Special/Order Compliance | 1/2/2020 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 2/13/2020 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 2/13/2020 | Approved | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/4/2020 | Conditional Approval | ANDREW NAVE |
| Deputy Shotcrete | 3/5/2020 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 3/5/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 3/27/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2020 | Partial Approval | ANDREW NAVE |
| Special/Order Compliance | 4/22/2020 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2020 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 5/21/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 5/21/2020 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 6/3/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/3/2020 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 6/9/2020 | Approved | ANDREW NAVE |
| Deputy Wood Construction | 6/24/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Rough | 7/2/2020 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 7/2/2020 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2020 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Rough | 7/24/2020 | Conditional Approval | ANDREW NAVE |
| Shower Pan | 7/24/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 7/27/2020 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 7/29/2020 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2020 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 8/6/2020 | Conditional Approval | ANDREW NAVE |
| Green Building Rough | 8/6/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 8/6/2020 | Partial Approval | ANDREW NAVE |
| Verify Sprinkler Sign Off | 8/6/2020 | Approved | ANDREW NAVE |
| Insulation | 8/14/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 8/26/2020 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 8/28/2020 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 9/8/2020 | Approved | ANDREW NAVE |
| Drywall Nailing | 9/8/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 4/28/2021 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Final | 4/28/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 4/30/2021 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 4/30/2021 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Final | 5/4/2021 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 5/4/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 5/7/2021 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 5/7/2021 | Approved | ANDREW NAVE |
| PLUMBING-Final | 5/7/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 5/18/2021 | Approved | ANDREW NAVE |
| Final | 5/18/2021 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 5/18/2021 | Approved | ANDREW NAVE |
| Green Building Final | 5/18/2021 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 5/18/2021 | SGSOV Approved | ANDREW NAVE |
| Service/Power Release | 5/18/2021 | Not Ready for Inspection | ANDREW NAVE |
| Smoke Detectors | 5/18/2021 | Corrections Issued | ANDREW NAVE |
| Final | 5/26/2021 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 5/26/2021 | Approved | ANDREW NAVE |
| Service/Power Release | 5/26/2021 | Not Ready for Inspection | ANDREW NAVE |
| Smoke Detectors | 5/26/2021 | Approved | ANDREW NAVE |
| Final | 7/2/2021 | Partial Approval | ANDREW NAVE |
| Service/Power Release | 7/2/2021 | Approved | ANDREW NAVE |