4243 N MAMMOTH AVE #1-4 91423

Certificate Information: 4243 N MAMMOTH AVE #1-4 91423

Application / Permit
19010-20000-01464
Plan Check / Job No.
B19VN05679
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 2-STORY 4-UNIT TYPE V-B APARTMENT W/ (4) ATTACHED 2-CAR GARAGES (NFPA-13R FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 1/30/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2019 APPLICANT
Disabled Access Plans Picked Up 4/23/2019 APPLICANT
Green Plans Picked Up 4/23/2019 APPLICANT
Assigned to Plan Check Engineer 4/25/2019 NILOOFAR MEHRAIN
Corrections Issued 4/29/2019 NILOOFAR MEHRAIN
Quality Review Completed 5/1/2019 CHON CHIO KUO
Building Plans Picked Up 5/1/2019 APPLICANT
Plan Check Approved 8/19/2019 NILOOFAR MEHRAIN
Issued 1/30/2020 LADBS
CofO in Progress 9/7/2021 JOHN KITCKO
Permit Finaled 9/14/2021 RICKEY JACKSON
CofO Issued 9/14/2021 RICKEY JACKSON
Permit Finaled 9/14/2021 RICKEY JACKSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/17/2019 ROBERT DUFF
Low Impact Development Cleared 6/17/2019 MITESH PATEL
Address approval Cleared 6/18/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/18/2019 LEE GUILBEAUX
Highway dedication Cleared 6/18/2019 LEE GUILBEAUX
Permit Cleared 6/18/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/18/2019 LEE GUILBEAUX
Sewer availability Cleared 6/18/2019 LEE GUILBEAUX
Trees in Parkway Cleared 6/24/2019 JOHN KIM
DAS Clearance Cleared 7/8/2019 NILOOFAR MEHRAIN
GPI Written Notices Cleared 8/5/2019 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 8/5/2019 NILOOFAR MEHRAIN
"Q" conditions Cleared 8/6/2019 DAISY BENICIA
Green Code Cleared 8/7/2019 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 6270 MCLEOD DR STE 140      LAS VEGAS, NV 89120

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Verify Rec and Parks Fee Memo 5/14/2020 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 6/24/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 6/26/2020 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/15/2020 Partial Approval JOHN KITCKO
Verify Rec and Parks Fee Memo 8/4/2020 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/3/2020 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/10/2020 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 10/8/2020 Partial Approval JOHN KITCKO
Green Building Rough 11/4/2020 Partial Inspection JOHN KITCKO
Verify Sprinkler Sign Off 11/4/2020 Not Ready for Inspection JOHN KITCKO
Wood Frame 11/4/2020 Not Ready for Inspection JOHN KITCKO
Green Building Rough 11/20/2020 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 11/20/2020 Approved JOHN KITCKO
Wood Frame 11/20/2020 Partial Approval JOHN KITCKO
Green Building Rough 12/9/2020 Not Ready for Inspection JOHN KITCKO
Wood Frame 12/9/2020 Not Ready for Inspection JOHN KITCKO
Green Building Rough 12/11/2020 Approved JOHN KITCKO
Wood Frame 12/11/2020 Approved JOHN KITCKO
Insulation 12/15/2020 Approved ANDREW DORSO
Drywall Nailing 12/21/2020 Partial Approval JOHN KITCKO
Drywall Nailing 12/23/2020 Partial Approval JOHN KITCKO
Final 5/6/2021 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 5/6/2021 Approved JOHN KITCKO
Green Building Final 5/6/2021 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 5/6/2021 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 5/6/2021 No Access for Inspection JOHN KITCKO
Final 6/15/2021 Not Ready for Inspection JOHN KITCKO
Green Building Final 6/15/2021 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 6/15/2021 SGSOV Approved JOHN KITCKO
Smoke Detectors 6/15/2021 Approved JOHN KITCKO
Final 7/8/2021 Partial Inspection CAMERON CHABAN
Green Building Final 7/8/2021 Partial Inspection CAMERON CHABAN
Final 7/23/2021 Not Ready for Inspection JOHN KITCKO
Green Building Final 7/23/2021 Not Ready for Inspection JOHN KITCKO
Final 7/26/2021 Partial Inspection JOHN KITCKO
Green Building Final 7/26/2021 Approved JOHN KITCKO
Final 9/7/2021 OK to Issue CofO JOHN KITCKO