4243 N MAMMOTH AVE #1-4 91423
Certificate Information: 4243 N MAMMOTH AVE #1-4 91423
- Application / Permit
- 19010-20000-01464
- Plan Check / Job No.
- B19VN05679
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 2-STORY 4-UNIT TYPE V-B APARTMENT W/ (4) ATTACHED 2-CAR GARAGES (NFPA-13R FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 1/30/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 4/23/2019 | APPLICANT |
| Green Plans Picked Up | 4/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 4/29/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/1/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 5/1/2019 | APPLICANT |
| Plan Check Approved | 8/19/2019 | NILOOFAR MEHRAIN |
| Issued | 1/30/2020 | LADBS |
| CofO in Progress | 9/7/2021 | JOHN KITCKO |
| Permit Finaled | 9/14/2021 | RICKEY JACKSON |
| CofO Issued | 9/14/2021 | RICKEY JACKSON |
| Permit Finaled | 9/14/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 6/17/2019 | ROBERT DUFF |
| Low Impact Development | Cleared | 6/17/2019 | MITESH PATEL |
| Address approval | Cleared | 6/18/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2019 | LEE GUILBEAUX |
| Highway dedication | Cleared | 6/18/2019 | LEE GUILBEAUX |
| Permit | Cleared | 6/18/2019 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/18/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/18/2019 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 6/24/2019 | JOHN KIM |
| DAS Clearance | Cleared | 7/8/2019 | NILOOFAR MEHRAIN |
| GPI Written Notices | Cleared | 8/5/2019 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 8/5/2019 | NILOOFAR MEHRAIN |
| "Q" conditions | Cleared | 8/6/2019 | DAISY BENICIA |
| Green Code | Cleared | 8/7/2019 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 6270 MCLEOD DR STE 140 LAS VEGAS, NV 89120 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Verify Rec and Parks Fee Memo | 5/14/2020 | Partial Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 6/24/2020 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 6/26/2020 | Approved | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2020 | Partial Approval | JOHN KITCKO |
| Verify Rec and Parks Fee Memo | 8/4/2020 | Approved | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2020 | Not Ready for Inspection | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2020 | Not Ready for Inspection | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2020 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 10/8/2020 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 11/4/2020 | Partial Inspection | JOHN KITCKO |
| Verify Sprinkler Sign Off | 11/4/2020 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 11/4/2020 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 11/20/2020 | Not Ready for Inspection | JOHN KITCKO |
| Verify Sprinkler Sign Off | 11/20/2020 | Approved | JOHN KITCKO |
| Wood Frame | 11/20/2020 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 12/9/2020 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 12/9/2020 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 12/11/2020 | Approved | JOHN KITCKO |
| Wood Frame | 12/11/2020 | Approved | JOHN KITCKO |
| Insulation | 12/15/2020 | Approved | ANDREW DORSO |
| Drywall Nailing | 12/21/2020 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 12/23/2020 | Partial Approval | JOHN KITCKO |
| Final | 5/6/2021 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 5/6/2021 | Approved | JOHN KITCKO |
| Green Building Final | 5/6/2021 | Not Ready for Inspection | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Not Ready | JOHN KITCKO |
| Smoke Detectors | 5/6/2021 | No Access for Inspection | JOHN KITCKO |
| Final | 6/15/2021 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Final | 6/15/2021 | Not Ready for Inspection | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 6/15/2021 | SGSOV Approved | JOHN KITCKO |
| Smoke Detectors | 6/15/2021 | Approved | JOHN KITCKO |
| Final | 7/8/2021 | Partial Inspection | CAMERON CHABAN |
| Green Building Final | 7/8/2021 | Partial Inspection | CAMERON CHABAN |
| Final | 7/23/2021 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Final | 7/23/2021 | Not Ready for Inspection | JOHN KITCKO |
| Final | 7/26/2021 | Partial Inspection | JOHN KITCKO |
| Green Building Final | 7/26/2021 | Approved | JOHN KITCKO |
| Final | 9/7/2021 | OK to Issue CofO | JOHN KITCKO |