6724 N KRAFT AVE 91606

Certificate Information: 6724 N KRAFT AVE 91606

Application / Permit
19010-20000-01456
Plan Check / Job No.
B19VN05641
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 39' 4" X 35' 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 39' 4" X 20' 4-CAR GARAGE AND 3' 5" X 8' 3" COVERED PORCH. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 8/13/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 GURUNATH NESARAJAH
Green Plans Picked Up 5/14/2019 APPLICANT
Corrections Issued 5/16/2019 GURUNATH NESARAJAH
Quality Review Completed 5/16/2019 OMID HEDAYAT
Building Plans Picked Up 5/21/2019 APPLICANT
Plan Check Approved 8/13/2019 GURUNATH NESARAJAH
Issued 8/13/2019 LADBS
CofO in Progress 5/18/2021 MICHAEL PELHAM
CofO Issued 7/3/2021 MICHAEL SMITH
Permit Finaled 7/3/2021 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/4/2019 GEORGE SUCHAND
Address approval Cleared 6/5/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/5/2019 LEE GUILBEAUX
Permit Cleared 6/5/2019 LEE GUILBEAUX
Sewer availability Cleared 6/5/2019 LEE GUILBEAUX
Low Impact Development Cleared 6/27/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 6/27/2019 JOHN LIN
Green Code Cleared 8/6/2019 DAVID MATSON

Contact Information

Architect Bahman, Ezzat; Lic. No.: C34210       ,
Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/4/2019 Corrections Issued MISAEL ESPARZA
Sewer 9/10/2019 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 9/27/2019 Approved MISAEL ESPARZA
Footing/Foundation/Slab 9/27/2019 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/29/2019 Partial Approval MISAEL ESPARZA
HVAC-Rough 1/24/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 1/24/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 1/31/2020 Approved RAYMOND KEHOE
MERV13>=Rough 1/31/2020 Not Ready for Inspection RAYMOND KEHOE
PLUMBING-Rough 1/31/2020 Approved RAYMOND KEHOE
BUILDING-Rough-Frame 2/6/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 2/6/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 2/6/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 2/6/2020 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 2/6/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/11/2020 Partial Approval RAYMOND KEHOE
ELECTRICAL-Rough 2/11/2020 Approved RAYMOND KEHOE
Green Building Rough 2/11/2020 Approved RAYMOND KEHOE
Insulation 2/25/2020 Approved RAYMOND KEHOE
Interior/Exterior Lathing 2/25/2020 Partial Approval RAYMOND KEHOE
Drywall Nailing 3/13/2020 Approved RAYMOND KEHOE
ELECTRICAL-Final 9/22/2020 Corrections Issued DANIEL DREW
HVAC-Final 9/22/2020 Not Ready for Inspection DANIEL DREW
PLUMBING-Final 9/22/2020 Not Ready for Inspection DANIEL DREW
BUILDING-Rough-Frame 10/26/2020 Corrections Issued BEAU COLLINS
ELECTRICAL-Final 10/26/2020 Corrections Issued BEAU COLLINS
HVAC-Final 10/26/2020 Corrections Issued BEAU COLLINS
PLUMBING-Final 10/26/2020 Corrections Issued BEAU COLLINS
ELECTRICAL-Final 11/4/2020 Corrections Issued DANIEL DREW
PLUMBING-Final 11/4/2020 Corrections Issued DANIEL DREW
ELECTRICAL-Final 11/10/2020 Corrections Issued DANIEL DREW
PLUMBING-Final 11/10/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 12/2/2020 Partial Approval MATTHEW NELSON
ELECTRICAL-Final 12/2/2020 Not Ready for Inspection MATTHEW NELSON
Final 12/2/2020 Not Ready for Inspection MATTHEW NELSON
Green Building Final 12/2/2020 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/2/2020 SGSOV Approved MATTHEW NELSON
Service/Power Release 12/2/2020 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 12/2/2020 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 12/2/2020 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 1/12/2021 Approved DANIEL DREW
ELECTRICAL-Final 1/12/2021 Not Ready for Inspection DANIEL DREW
Green Building Final 1/12/2021 Approved DANIEL DREW
HVAC-Final 1/12/2021 Approved DANIEL DREW
Service/Power Release 1/12/2021 Not Ready for Inspection DANIEL DREW
Verify Sprinkler Sign Off 1/12/2021 Approved DANIEL DREW
Final 1/28/2021 Corrections Issued DANIEL DREW
Service/Power Release 1/28/2021 Not Ready for Inspection DANIEL DREW
Final 5/17/2021 Conditional Approval MICHAEL PELHAM
Service/Power Release 5/17/2021 Approved MICHAEL PELHAM