6724 N KRAFT AVE 91606
Certificate Information: 6724 N KRAFT AVE 91606
- Application / Permit
- 19010-20000-01456
- Plan Check / Job No.
- B19VN05641
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 39' 4" X 35' 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 39' 4" X 20' 4-CAR GARAGE AND 3' 5" X 8' 3" COVERED PORCH. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 8/13/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2019 | GURUNATH NESARAJAH |
| Green Plans Picked Up | 5/14/2019 | APPLICANT |
| Corrections Issued | 5/16/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 5/16/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 5/21/2019 | APPLICANT |
| Plan Check Approved | 8/13/2019 | GURUNATH NESARAJAH |
| Issued | 8/13/2019 | LADBS |
| CofO in Progress | 5/18/2021 | MICHAEL PELHAM |
| CofO Issued | 7/3/2021 | MICHAEL SMITH |
| Permit Finaled | 7/3/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 6/4/2019 | GEORGE SUCHAND |
| Address approval | Cleared | 6/5/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2019 | LEE GUILBEAUX |
| Permit | Cleared | 6/5/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/5/2019 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 6/27/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/27/2019 | JOHN LIN |
| Green Code | Cleared | 8/6/2019 | DAVID MATSON |
Contact Information
| Architect | Bahman, Ezzat; Lic. No.: C34210 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/4/2019 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 9/10/2019 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 9/27/2019 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/27/2019 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2019 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 1/24/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 1/24/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/31/2020 | Approved | RAYMOND KEHOE |
| MERV13>=Rough | 1/31/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| PLUMBING-Rough | 1/31/2020 | Approved | RAYMOND KEHOE |
| BUILDING-Rough-Frame | 2/6/2020 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 2/6/2020 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 2/6/2020 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 2/6/2020 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 2/6/2020 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/11/2020 | Partial Approval | RAYMOND KEHOE |
| ELECTRICAL-Rough | 2/11/2020 | Approved | RAYMOND KEHOE |
| Green Building Rough | 2/11/2020 | Approved | RAYMOND KEHOE |
| Insulation | 2/25/2020 | Approved | RAYMOND KEHOE |
| Interior/Exterior Lathing | 2/25/2020 | Partial Approval | RAYMOND KEHOE |
| Drywall Nailing | 3/13/2020 | Approved | RAYMOND KEHOE |
| ELECTRICAL-Final | 9/22/2020 | Corrections Issued | DANIEL DREW |
| HVAC-Final | 9/22/2020 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Final | 9/22/2020 | Not Ready for Inspection | DANIEL DREW |
| BUILDING-Rough-Frame | 10/26/2020 | Corrections Issued | BEAU COLLINS |
| ELECTRICAL-Final | 10/26/2020 | Corrections Issued | BEAU COLLINS |
| HVAC-Final | 10/26/2020 | Corrections Issued | BEAU COLLINS |
| PLUMBING-Final | 10/26/2020 | Corrections Issued | BEAU COLLINS |
| ELECTRICAL-Final | 11/4/2020 | Corrections Issued | DANIEL DREW |
| PLUMBING-Final | 11/4/2020 | Corrections Issued | DANIEL DREW |
| ELECTRICAL-Final | 11/10/2020 | Corrections Issued | DANIEL DREW |
| PLUMBING-Final | 11/10/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 12/2/2020 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Final | 12/2/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 12/2/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 12/2/2020 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/2/2020 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 12/2/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 12/2/2020 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 12/2/2020 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/12/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 1/12/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Final | 1/12/2021 | Approved | DANIEL DREW |
| HVAC-Final | 1/12/2021 | Approved | DANIEL DREW |
| Service/Power Release | 1/12/2021 | Not Ready for Inspection | DANIEL DREW |
| Verify Sprinkler Sign Off | 1/12/2021 | Approved | DANIEL DREW |
| Final | 1/28/2021 | Corrections Issued | DANIEL DREW |
| Service/Power Release | 1/28/2021 | Not Ready for Inspection | DANIEL DREW |
| Final | 5/17/2021 | Conditional Approval | MICHAEL PELHAM |
| Service/Power Release | 5/17/2021 | Approved | MICHAEL PELHAM |