3847 N WEST POINT DR 90065

Certificate Information: 3847 N WEST POINT DR 90065

Application / Permit
19010-20000-01444
Plan Check / Job No.
B19VN05570
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 33'8" x 31'9" irregular shape NFPA13-D spriinkler throughout 3-story dwelling with 1 level basement, and attached garage
Permit Issued
Issued on 8/30/2023
Issuing Office
Current Status
Issued on 8/30/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/8/2019 APPLICANT
Green Plans Picked Up 4/16/2019 APPLICANT
Assigned to Plan Check Engineer 4/25/2019 ALDOUS CHIC
Corrections Issued 4/29/2019 ALDOUS CHIC
Quality Review Completed 4/29/2019 ABDUL CHEGENI
Building Plans Picked Up 4/30/2019 APPLICANT
Applicant returned to address corrections 4/7/2020 ALDOUS CHIC
Applicant returned to address corrections 4/8/2020 ALDOUS CHIC
Applicant returned to address corrections 10/5/2020 SELLA BENYAMIN
Applicant returned to address corrections 12/17/2020 SELLA BENYAMIN
Plan Check Approved 4/20/2023 SELLA BENYAMIN
Issued 8/30/2023 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/12/2019 ALDOUS CHIC
GPI Written Notices Cleared 4/26/2019 ALDOUS CHIC
Address approval Cleared 2/26/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 2/26/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 2/26/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 2/26/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/26/2020 ADRIAN CASTRO
Permit Cleared 2/26/2020 ADRIAN CASTRO
Permit Cleared 2/26/2020 ADRIAN CASTRO
Work Adjacent to Public Way Cleared 2/26/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 3/6/2020 GEORGE SUCHAND
Low Impact Development Cleared 3/9/2020 MITESH PATEL
Highway dedication Cleared 3/10/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 3/11/2020 JAMES KHO
Sewer availability Cleared 3/11/2020 JAMES KHO
Green Code Cleared 4/6/2020 DAVID MATSON
Miscellaneous Cleared 6/16/2020 SARAHI ORTEGA
Specific Plan Cleared 6/17/2020 SARAHI ORTEGA
ZI Cleared 6/17/2020 SARAHI ORTEGA
Trees in Parkway Cleared 8/28/2020 STEPHEN DUPREY

Contact Information

Contractor 1st Choice Solar Construction; Lic. No.: 576474-B 333 CITY BLVD WEST STE 1700      ORANGE, CA 92868
Engineer Haro,, Ruben; Lic. No.: C72213 1554 CIPRES CT      CAMARILLO, CA 93010
Engineer Haro,, Ruben; Lic. No.: GE2990 1554 CIPRES CT      CAMARILLO, CA 93010
Engineer Rahman,, Moksudur; Lic. No.: C69263 14616 MCKENDREE AVE      CHINO, CA 91708
Geologist Bovenizer,, Ernest; Lic. No.: EG2515 7622 GODDARD AVENUE      LOS ANGELES, CA 90045

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2024 Corrections Issued OSVALDO PARAMO
Deputy Reinf. Concrete 8/23/2024 Conditional Approval OSVALDO PARAMO
Piling/Pier/Caisson 8/23/2024 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/3/2024 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 10/3/2024 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 10/15/2024 Conditional Approval OSVALDO PARAMO
Piling/Pier/Caisson 10/21/2024 Approved ROY SPAULDING
Deputy Reinf. Concrete 10/22/2024 Conditional Approval OSVALDO PARAMO
Piling/Pier/Caisson 1/31/2025 Partial Approval ALIZAH MAYAGOITIA
Deputy Other (see comments) 2/6/2025 Conditional Approval ALIZAH MAYAGOITIA
Deputy Reinf. Concrete 2/6/2025 Conditional Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 3/17/2025 Not Ready for Inspection NICHOLAS LOPEZ
Footing/Foundation/Slab 3/17/2025 Not Ready for Inspection NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 3/20/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/20/2025 Partial Approval ALIZAH MAYAGOITIA
Piling/Pier/Caisson 3/20/2025 Approved ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 5/23/2025 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/5/2025 Partial Approval ALIZAH MAYAGOITIA
Deputy Reinf. Concrete 6/6/2025 Conditional Approval ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 7/3/2025 Conditional Approval ALIZAH MAYAGOITIA
Piling/Pier/Caisson 7/3/2025 Partial Approval ALIZAH MAYAGOITIA
Deputy Shotcrete 7/9/2025 Approved REGINA MENDEZ
Piling/Pier/Caisson 7/31/2025 Partial Approval ALIZAH MAYAGOITIA
Deputy Shotcrete 8/8/2025 Conditional Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 9/9/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Piling/Pier/Caisson 9/9/2025 Corrections Issued ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 11/6/2025 Conditional Approval ALEX COLIN
Deputy Reinf. Concrete 12/23/2025 Conditional Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 1/9/2026 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 1/9/2026 Partial Approval ALIZAH MAYAGOITIA
Piling/Pier/Caisson 1/9/2026 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 1/15/2026 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 1/15/2026 Partial Approval ALIZAH MAYAGOITIA
Deputy Reinf. Concrete 1/20/2026 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/27/2026 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 2/27/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 2/27/2026 Partial Approval ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 2/27/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/5/2026 Partial Approval ALIZAH MAYAGOITIA
Reinforced Concrete Frame 3/5/2026 Partial Approval ALIZAH MAYAGOITIA
Deputy Steel/Welding 4/17/2026 Conditional Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 5/22/2026 Corrections Issued OSVALDO PARAMO
Structural Steel Frame 5/22/2026 Approved OSVALDO PARAMO
Wood Frame 5/22/2026 Partial Inspection OSVALDO PARAMO
Drywall Nailing 6/1/2026 Partial Approval GEM DE OCAMPO