9008 N AQUEDUCT AVE 91343

Certificate Information: 9008 N AQUEDUCT AVE 91343

Application / Permit
19010-20000-01440
Plan Check / Job No.
B19VN05542
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE IRREG. 39'-3"X63'-11" ONE STORY ADU WITH ATTACHED TWO CAR GARAGE _ PER AB 494 AND SB 229
Permit Issued
Issued on 7/11/2019
Issuing Office
Valley
Current Status
Issued on 7/11/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/8/2019 APPLICANT
Assigned to Plan Check Engineer 4/25/2019 DAWN MC NULTY
Corrections Issued 4/29/2019 DAWN MC NULTY
Quality Review Completed 4/30/2019 CHON CHIO KUO
Building Plans Picked Up 5/2/2019 APPLICANT
Green Plans Picked Up 5/2/2019 APPLICANT
Plan Check Approved 7/9/2019 DAWN MC NULTY
Issued 7/11/2019 LADBS

Permit Application Clearance Information

Green Code Cleared 7/1/2019 DAVID MATSON
Address approval Cleared 7/8/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/8/2019 LEE GUILBEAUX
Hydrant and Access approval Cleared 7/8/2019 GILBERT URREA
Low Impact Development Cleared 7/8/2019 ANDRES COVARRUBIAS
Permit Cleared 7/8/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/8/2019 ELENA LOPEZ
Sewer availability Cleared 7/8/2019 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/8/2019 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Husain,, Shahzain; Lic. No.: C62744 1843 MONTGOMERY RD      THOUSAND OAKS, CA 91360

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/6/2019 Not Ready for Inspection JACK KARGODORIAN
Sewer 9/6/2019 Not Ready for Inspection JACK KARGODORIAN
Underground Mechanical 9/6/2019 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 9/11/2019 Approved JACK KARGODORIAN
Underground Mechanical 9/11/2019 Partial Inspection JACK KARGODORIAN
Deputy Reinf. Concrete 9/13/2019 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 11/5/2019 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 11/5/2019 Partial Inspection JACK KARGODORIAN
MERV13>=Rough 11/5/2019 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 11/5/2019 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 12/12/2019 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 12/12/2019 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 12/12/2019 Approved MATTHEW NELSON
HVAC-Rough 12/12/2019 Approved MATTHEW NELSON
MERV13>=Rough 12/12/2019 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 12/12/2019 Not Ready for Inspection MATTHEW NELSON
Deputy Wood Construction 12/13/2019 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 12/19/2019 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 12/19/2019 Not Ready for Inspection JACK KARGODORIAN
MERV13>=Rough 12/19/2019 Approved JACK KARGODORIAN
PLUMBING-Rough 12/19/2019 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 12/19/2019 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/6/2020 Not Ready for Inspection JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 1/6/2020 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/27/2020 Approved JACK KARGODORIAN
PLUMBING-Rough 1/27/2020 Partial Approval JACK KARGODORIAN
Insulation 2/28/2020 No Access for Inspection JACK KARGODORIAN
Masonry Wall/Backfill 2/28/2020 No Access for Inspection JACK KARGODORIAN
Insulation 3/6/2020 Approved JACK KARGODORIAN
Underground Mechanical 3/6/2020 Approved JACK KARGODORIAN
Drywall Nailing 3/16/2020 Approved ROBERT MINASSIANS
Interior/Exterior Lathing 3/25/2020 Approved MICHEL ABAJAN
Shower Pan 3/25/2020 Approved MICHEL ABAJAN
Final 5/1/2020 Corrections Issued DANIEL ORRANTE
Footing/Foundation/Slab 5/1/2020 Approved DANIEL ORRANTE
Green Building Final 5/1/2020 Approved DANIEL ORRANTE
MERV13>=Final 5/1/2020 Approved DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 5/1/2020 SGSOV Approved DANIEL ORRANTE
Service/Power Release 5/1/2020 Not Ready for Inspection DANIEL ORRANTE
Smoke Detectors 5/1/2020 Approved DANIEL ORRANTE
Final 9/14/2020 No Access for Inspection MICHEL ABAJAN
Service/Power Release 9/14/2020 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Final 9/21/2020 Corrections Issued JENNIFER RABUCHIN
Final 9/21/2020 Corrections Issued JENNIFER RABUCHIN
Gas Test 9/21/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Final 9/21/2020 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 9/21/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 9/21/2020 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 9/21/2020 Not Ready for Inspection JENNIFER RABUCHIN
Final 12/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Final 12/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
Service/Power Release 12/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
Final 1/6/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Final 1/6/2021 Approved ARTHUR SARGSYAN
Service/Power Release 1/6/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 2/19/2021 Not Ready for Inspection ARTHUR SARGSYAN
Service/Power Release 2/19/2021 Not Ready for Inspection ARTHUR SARGSYAN
Pre-Inspection 11/4/2025 Corrections Issued RYAN SALAZAR
Final 4/20/2026 Corrections Issued DAVID MATSON
Service/Power Release 4/20/2026 Not Ready for Inspection DAVID MATSON