2346 S PELHAM AVE 90064
Certificate Information: 2346 S PELHAM AVE 90064
- Application / Permit
- 19010-20000-01417
- Plan Check / Job No.
- B19VN05452
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 15'-6" X 18'-6" DETACHED OPEN TRELLIS PER ENGINEERING.
- Permit Issued
- Issued on 2/28/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 4/21/2019 | ARTIN ZARUKIAN |
| Quality Review Completed | 4/24/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 4/24/2019 | APPLICANT |
| Applicant returned to address corrections | 9/26/2019 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 12/23/2019 | ARTIN ZARUKIAN |
| Plan Check Approved | 1/9/2020 | ARTIN ZARUKIAN |
| Issued | 2/28/2020 | LADBS |
| CofO in Progress | 2/5/2021 | GERMAN RODRIGUEZ MENDOZA |
| CofO Issued | 6/15/2021 | VINCENT COTTON |
| Permit Finaled | 6/15/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/26/2019 | OSCAR CASTRO |
| Grading Pre-Inspection | Cleared | 9/26/2019 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 9/21/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 9/21/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Barrier | 9/21/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 9/21/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 10/9/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 10/9/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Rough | 10/9/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 10/9/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 11/24/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 1/14/2021 | Partial Approval | MATT KELLERMAN |
| FLOOD-Proofing Certificate | 1/14/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Final | 1/14/2021 | Not Ready for Inspection | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2021 | SGSOV Approved | MATT KELLERMAN |
| Service/Power Release | 1/14/2021 | Not Required | MATT KELLERMAN |
| Smoke Detectors | 1/14/2021 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 2/1/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| FLOOD-Proofing Certificate | 2/1/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 2/1/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 2/4/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |