6242 N LINDLEY AVE 91316
Certificate Information: 6242 N LINDLEY AVE 91316
- Application / Permit
- 19010-20000-01397
- Plan Check / Job No.
- B19VN05369
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 33' x 58'-8" TWO STORY, SINGLE FAMILY DWELLING WITH NFPA-13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 11/16/2021
- Issuing Office
- Current Status
- CofO Issued on 5/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2019 | RODNEY SAMIIAN |
| Corrections Issued | 5/13/2019 | RODNEY SAMIIAN |
| Quality Review Completed | 5/14/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 7/19/2019 | APPLICANT |
| Green Plans Picked Up | 7/19/2019 | APPLICANT |
| Applicant returned to address corrections | 10/12/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 11/15/2021 | SEAN SHAHMIRI |
| Issued | 11/16/2021 | APPLICANT |
| CofO in Progress | 3/13/2024 | JON MCHUGH |
| CofO in Progress | 5/6/2024 | JOHN JANSON |
| Permit Finaled | 5/7/2024 | JOHN JANSON |
| CofO Issued | 5/7/2024 | JOHN JANSON |
| Permit Finaled | 5/7/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2021 | GUILLERMO PETRA |
| "T" removal | Cleared | 5/3/2021 | DANG NGUYEN |
| ZA Case | Cleared | 5/3/2021 | DANG NGUYEN |
| ZA Case | Cleared | 5/3/2021 | DANG NGUYEN |
| ZA Case | Cleared | 5/3/2021 | DANG NGUYEN |
| ZI | Cleared | 6/24/2021 | DANG NGUYEN |
| Low Impact Development | Cleared | 7/23/2021 | SUNG JOON WON |
| Permit | Cleared | 7/30/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/30/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/31/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/31/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 9/17/2021 | KURT CORRAL |
| Green Code | Cleared | 10/12/2021 | PARISA ZAHABI |
Contact Information
| Contractor | S A B D Investments Inc; Lic. No.: 1029441-B | 445 N FLORENCE STREET BURBANK, CA 91505 |
| Engineer | Casillas,, Rafael Ortega; Lic. No.: C68234 | 1937 S BRADSHAWE AVE MONTEREY PARK, CA 91754 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/9/2021 | No Access for Inspection | SEAN HAUPT |
| Special/Order Compliance | 12/9/2021 | Corrections Issued | SEAN HAUPT |
| Underground Mechanical | 12/20/2021 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 1/21/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Partial Approval | VINCENT HANLEY |
| Deputy Other (see comments) | 5/20/2022 | Partial Approval | SEAN HAUPT |
| Deputy Wood Construction | 5/20/2022 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Approved | SEAN HAUPT |
| Deputy Reinf. Concrete | 8/30/2022 | Conditional Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 8/31/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/9/2022 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 11/9/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Rough | 11/9/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 11/9/2022 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 11/9/2022 | Corrections Issued | SEAN HAUPT |
| Verify Sprinkler Sign Off | 11/9/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 11/15/2022 | Partial Approval | SEAN HAUPT |
| HVAC-Rough | 11/15/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 11/15/2022 | Approved | SEAN HAUPT |
| Insulation | 11/28/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 12/2/2022 | Partial Approval | JON MCHUGH |
| Shower Pan | 12/2/2022 | Not Ready for Inspection | JON MCHUGH |
| Drywall Nailing | 12/7/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 12/7/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| Shower Pan | 12/12/2022 | Not Ready for Inspection | JON MCHUGH |
| Shower Pan | 12/15/2022 | Approved | JON MCHUGH |
| Sewer | 5/30/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 5/30/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 9/15/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 9/15/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 9/15/2023 | Approved | JON MCHUGH |
| Final | 9/15/2023 | Corrections Issued | JON MCHUGH |
| Gas Test | 9/15/2023 | Approved | JON MCHUGH |
| HVAC-Final | 9/15/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 9/15/2023 | Corrections Issued | JON MCHUGH |
| Final | 1/18/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 1/18/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 1/18/2024 | Approved | JON MCHUGH |
| Smoke Detectors | 1/18/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 3/12/2024 | Approved | JON MCHUGH |
| Final | 3/12/2024 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 3/12/2024 | Approved | JON MCHUGH |
| HVAC-Final | 3/12/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 3/12/2024 | Approved | JON MCHUGH |