- Work Description
- NEW 2-STORY 59' X 46' 6" IRREGULAR-SHAPE SINGLE FAMILY DWELLING WITH ATTACHED 22' X 19' 6" 2-CAR GARAGE, 6' 6" X 23' OPEN TRELLIS AND 15' 3" X 14' OPEN TRELLIS. NFPA 13D FIRE SPRINKLERS TO BE PROVIDED. ALL WORK DONE PER STRUCTURAL ENGINEERING
- Permit Issued
- Issued on 7/8/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | GURUNATH NESARAJAH |
| Corrections Issued | 4/23/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 4/24/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 4/25/2019 | APPLICANT |
| Green Plans Picked Up | 5/23/2019 | APPLICANT |
| Plan Check Approved | 6/14/2019 | GURUNATH NESARAJAH |
| Issued | 7/8/2019 | LADBS |
| CofO in Progress | 5/3/2021 | BRIAN SULLIVAN |
| Permit Finaled | 5/7/2021 | DEROLD HAUFF |
| CofO Issued | 5/7/2021 | DEROLD HAUFF |
| Permit Finaled | 5/7/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/3/2019 | SAFA JAVANMARDI |
| BHO/Hillside ordinance | Cleared | 5/3/2019 | SAFA JAVANMARDI |
| BHO/Hillside ordinance | Cleared | 5/3/2019 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2019 | SAFA JAVANMARDI |
| Permit | Cleared | 5/3/2019 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/3/2019 | SAFA JAVANMARDI |
| Trees in Parkway | Cleared | 5/14/2019 | JOHN KIM |
| Hydrant and Access approval | Cleared | 5/16/2019 | GEORGE SUCHAND |
| Distance to fire station | Cleared | 6/3/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 6/3/2019 | MICHAEL AYERS |
| "D" conditions | Cleared | 6/4/2019 | RICHARD REASER |
| ZI | Cleared | 6/4/2019 | RICHARD REASER |
| Low Impact Development | Cleared | 6/11/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/11/2019 | MARKOS PEREZ-BRAN |
| GPI Written Notices | Cleared | 6/13/2019 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alatorre-Y-Barroso,, Alejandro J; Lic. No.: C32761 | 24795 DAPHNE EAST MISSION VIEJO, CA 92691 |
| Engineer | Elia,, Victor Anthony; Lic. No.: C64803 | 40912 CARLENA LN TEMECULA, CA 92591 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
| Landscape Architect | Alaniz,, Arthur Louis; Lic. No.: LA5554 | 26 CLEAR VISTA ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 9/6/2019 | Partial Inspection | ROBERT CORNELL |
| Deputy Shotcrete | 9/24/2019 | Conditional Approval | ROBERT CORNELL |
| Deputy Shotcrete | 9/26/2019 | Conditional Approval | ROBERT CORNELL |
| Footing/Foundation/Slab | 10/16/2019 | Approved | ROBERT CORNELL |
| Excavation/Setback/Form/Re-Bar | 10/28/2019 | Approved | ROBERT CORNELL |
| Deputy Reinf. Concrete | 11/4/2019 | Conditional Approval | ROBERT CORNELL |
| BUILDING-Rough-Frame | 11/27/2019 | Partial Approval | ROBERT CORNELL |
| Wood Frame | 11/27/2019 | Partial Approval | ROBERT CORNELL |
| Wood Frame | 1/3/2020 | Corrections Issued | BRIAN SULLIVAN |
| Wood Frame | 2/24/2020 | Partial Approval | ROBERT CORNELL |
| HVAC-Rough | 3/9/2020 | Corrections Issued | ROBERT CORNELL |
| PLUMBING-Rough | 3/9/2020 | Approved | ROBERT CORNELL |
| BUILDING-Rough-Frame | 3/10/2020 | Partial Approval | ROBERT CORNELL |
| Deputy Wood Construction | 3/10/2020 | Approved | ROBERT CORNELL |
| ELECTRICAL-Rough | 3/10/2020 | Approved | ROBERT CORNELL |
| Green Building Rough | 3/10/2020 | Approved | ROBERT CORNELL |
| Verify Sprinkler Sign Off | 3/10/2020 | Approved | ROBERT CORNELL |
| Shower Pan | 4/1/2020 | Approved | ROBERT CORNELL |
| Special/Order Compliance | 4/1/2020 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/13/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 4/22/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/29/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Insulation | 5/1/2020 | Corrections Issued | BRIAN SULLIVAN |
| Special/Order Compliance | 5/14/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Drywall Nailing | 5/26/2020 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/2/2020 | Corrections Issued | BRAD BESCOS |
| Special/Order Compliance | 6/2/2020 | Corrections Issued | BRIAN SULLIVAN |
| Special/Order Compliance | 8/11/2020 | Corrections Issued | BRIAN SULLIVAN |
| Special/Order Compliance | 8/31/2020 | Partial Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 9/14/2020 | Partial Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2020 | Approved | BRIAN SULLIVAN |
| Pre-Inspection | 11/18/2020 | Approved | BRIAN SULLIVAN |
| Pre-Inspection | 11/23/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Pre-Inspection | 12/1/2020 | Corrections Issued | BRIAN SULLIVAN |
| Pre-Inspection | 12/1/2020 | Partial Inspection | BRAD BESCOS |
| Wood Frame | 1/11/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 1/15/2021 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/20/2021 | Approved | BRIAN SULLIVAN |
| Special/Order Compliance | 2/5/2021 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Final | 4/8/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 4/8/2021 | Corrections Issued | BRIAN SULLIVAN |
| Final | 4/9/2021 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 4/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 4/9/2021 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/9/2021 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 4/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Smoke Detectors | 4/9/2021 | Approved | BRIAN SULLIVAN |
| Final | 5/3/2021 | OK to Issue CofO | BRIAN SULLIVAN |
| Green Building Final | 5/3/2021 | Approved | BRIAN SULLIVAN |
| Service/Power Release | 5/3/2021 | Approved | BRIAN SULLIVAN |