10113 N LOUISE AVE 91325
Certificate Information: 10113 N LOUISE AVE 91325
- Application / Permit
- 19010-20000-01360
- Plan Check / Job No.
- B19VN05264
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED DETTACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229.
- Permit Issued
- Issued on 12/19/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2019 | APPLICANT |
| Green Plans Picked Up | 4/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | RODNEY SAMIIAN |
| Corrections Issued | 4/24/2019 | RODNEY SAMIIAN |
| Quality Review Completed | 4/25/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 4/25/2019 | APPLICANT |
| Plan Check Approved | 12/18/2019 | RODNEY SAMIIAN |
| Issued | 12/19/2019 | LADBS |
| CofO in Progress | 9/1/2020 | MARK JOHNSON |
| Permit Finaled | 3/20/2021 | MICHAEL SMITH |
| CofO Issued | 3/20/2021 | MICHAEL SMITH |
| Permit Finaled | 3/20/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2019 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 10/30/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 10/30/2019 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 11/12/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/12/2019 | JOHN LIN |
| Green Code | Cleared | 11/19/2019 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/6/2020 | Approved | MARK JOHNSON |
| Footing/Foundation/Slab | 2/12/2020 | Partial Approval | MARK JOHNSON |
| Wood Frame | 2/25/2020 | Partial Approval | MARK JOHNSON |
| Wood Frame | 3/3/2020 | Corrections Issued | MARK JOHNSON |
| HVAC-Rough | 4/7/2020 | Corrections Issued | MARK JOHNSON |
| Sewer | 4/7/2020 | Corrections Issued | MARK JOHNSON |
| BUILDING-Rough-Frame | 4/17/2020 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 4/17/2020 | Approved | MARK JOHNSON |
| Green Building Rough | 4/17/2020 | Approved | MARK JOHNSON |
| HVAC-Rough | 4/17/2020 | Corrections Issued | MARK JOHNSON |
| PLUMBING-Rough | 4/17/2020 | Corrections Issued | MARK JOHNSON |
| Sewer | 4/17/2020 | Approved | MARK JOHNSON |
| Verify Sprinkler Sign Off | 4/17/2020 | Approved | MARK JOHNSON |
| Wood Frame | 4/17/2020 | Approved | MARK JOHNSON |
| HVAC-Rough | 4/29/2020 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 4/29/2020 | Not Ready for Inspection | MARK JOHNSON |
| Interior/Exterior Lathing | 4/30/2020 | Not Ready for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 5/4/2020 | Approved | MARK JOHNSON |
| Insulation | 5/4/2020 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 5/4/2020 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 5/4/2020 | Approved | MARK JOHNSON |
| Drywall Nailing | 5/12/2020 | Approved | MARK JOHNSON |
| ELECTRICAL-Final | 7/29/2020 | Approved | MARK JOHNSON |
| Final | 7/29/2020 | Corrections Issued | MARK JOHNSON |
| HVAC-Final | 7/29/2020 | Approved | MARK JOHNSON |
| PLUMBING-Final | 7/29/2020 | Approved | MARK JOHNSON |
| Final | 8/13/2020 | Not Ready for Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 8/13/2020 | Approved | MARK JOHNSON |
| Green Building Final | 8/13/2020 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 8/13/2020 | SGSOV Approved | MARK JOHNSON |
| Service/Power Release | 8/13/2020 | Not Required | MARK JOHNSON |
| Smoke Detectors | 8/13/2020 | Approved | MARK JOHNSON |
| Final | 9/1/2020 | OK to Issue CofO | MARK JOHNSON |