8838 N SHOSHONE AVE 91325

Certificate Information: 8838 N SHOSHONE AVE 91325

Application / Permit
19010-20000-01319
Plan Check / Job No.
B19VN05088
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32'-6" X 25'-6" IRREG SHAPED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 5/23/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2019 APPLICANT
Green Plans Picked Up 4/9/2019 APPLICANT
Assigned to Plan Check Engineer 4/18/2019 JEROME MAGAT PALMA
Corrections Issued 4/22/2019 JEROME MAGAT PALMA
Quality Review Completed 4/22/2019 ABDUL CHEGENI
Building Plans Picked Up 4/22/2019 APPLICANT
Applicant returned to address corrections 5/7/2019 JEROME MAGAT PALMA
Plan Check Approved 5/23/2019 JEROME MAGAT PALMA
Issued 5/23/2019 LADBS
CofO in Progress 1/15/2021 MARK JOHNSON
CofO Issued 3/27/2021 MICHAEL SMITH
Permit Finaled 3/27/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/7/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 5/7/2019 JOHN LIN
Green Code Cleared 5/7/2019 JEROME MAGAT PALMA
Sewer availability Cleared 5/7/2019 JOHN LIN
Hydrant and Access approval Cleared 5/20/2019 GEORGE SUCHAND
Low Impact Development Cleared 5/20/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/20/2019 KARAN PATEL

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/18/2019 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 7/23/2019 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 8/13/2019 Approved MARK JOHNSON
ELECTRICAL-Rough 8/21/2019 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 8/21/2019 Approved MARK JOHNSON
PLUMBING-Rough 9/5/2019 Approved MARK JOHNSON
Sewer 9/11/2019 Approved MARK JOHNSON
BUILDING-Rough-Frame 9/13/2019 Partial Inspection MARK JOHNSON
Gas Test 9/13/2019 Approved MARK JOHNSON
Green Building Rough 9/13/2019 Approved MARK JOHNSON
HVAC-Rough 9/13/2019 Approved MARK JOHNSON
Gas Test 9/18/2019 Partial Approval MARK JOHNSON
PLUMBING-Rough 9/18/2019 Partial Approval MARK JOHNSON
Interior/Exterior Lathing 9/27/2019 Approved MARK JOHNSON
Insulation 10/10/2019 Approved MARK JOHNSON
Drywall Nailing 10/17/2019 Approved JEFFREY PARD
ELECTRICAL-Rough 10/31/2019 Partial Approval MARK JOHNSON
ELECTRICAL-Final 11/19/2019 Approved MARK JOHNSON
HVAC-Final 11/19/2019 Approved MARK JOHNSON
PLUMBING-Final 11/19/2019 Approved MARK JOHNSON
Smoke Detectors 11/19/2019 Approved MARK JOHNSON
ELECTRICAL-Final 2/13/2020 Approved MARK JOHNSON
Enclosure/Fence 2/13/2020 Not Ready for Inspection MARK JOHNSON
HVAC-Final 2/13/2020 Approved MARK JOHNSON
PLUMBING-Final 2/13/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 9/14/2020 Approved VINCENT HANLEY
Final 9/14/2020 Corrections Issued VINCENT HANLEY
Green Building Final 9/14/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/14/2020 SGSOV Approved VINCENT HANLEY
Service/Power Release 9/14/2020 Approved VINCENT HANLEY
Final 9/24/2020 Not Ready for Inspection MARK JOHNSON
Final 1/14/2021 OK to Issue CofO MARK JOHNSON