3406 S INGLEWOOD BLVD 90066

Certificate Information: 3406 S INGLEWOOD BLVD 90066

Application / Permit
19010-20000-01225
Plan Check / Job No.
B19VN04698
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
NEW 11'-0" X 20'-11" DETACHED STORAGE ROOM WITH ROOF DECK ABOVE
Permit Issued
Issued on 2/21/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2019 APPLICANT
Assigned to Plan Check Engineer 4/4/2019 JEROME MAGAT PALMA
Corrections Issued 4/8/2019 JEROME MAGAT PALMA
Quality Review Completed 4/8/2019 ABDUL CHEGENI
Building Plans Picked Up 4/11/2019 APPLICANT
Green Plans Picked Up 4/11/2019 APPLICANT
Plan Check Approved 2/20/2020 JEROME MAGAT PALMA
Issued 2/21/2020 LADBS
CofO in Progress 10/26/2021 KENNETH NAGLE
Permit Finaled 10/26/2021 KENNETH NAGLE
CofO Issued 10/26/2021 KENNETH NAGLE
Permit Finaled 10/26/2021 KENNETH NAGLE

Permit Application Clearance Information

Green Code Cleared 9/18/2019 JEROME MAGAT PALMA
Green Code Cleared 9/18/2019 PARISA ZAHABI
Low Impact Development Cleared 10/11/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 10/11/2019 JEANETTE VONG
Construction near power lines Cleared 11/14/2019 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/13/2020 CARL MILLS
Grading Pre-Inspection Cleared 2/20/2020 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/9/2020 Approved KEVIN BEAULIEU
Piling/Pier/Caisson 5/21/2020 Approved KENNETH NAGLE
Deputy Reinf. Concrete 5/26/2020 No Access for Inspection KENNETH NAGLE
Deputy Reinf. Concrete 6/4/2020 Conditional Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 6/5/2020 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 6/8/2020 Conditional Approval KENNETH NAGLE
Footing/Foundation/Slab 6/8/2020 Partial Approval KENNETH NAGLE
Deputy Reinf. Concrete 6/9/2020 No Access for Inspection KENNETH NAGLE
Deputy Reinf. Concrete 6/17/2020 Conditional Approval KEVIN SARGSYAN
Masonry Wall/Backfill 6/17/2020 Conditional Approval JUSTIN CURTIS
Deputy Reinf. Concrete 6/18/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/3/2020 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/10/2020 Partial Approval EVAN COOPER
Green Building Rough 8/10/2020 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 8/10/2020 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 10/2/2020 Not Ready for Inspection ANTHONY MCDOWALL
ELECTRICAL-Rough 10/2/2020 Approved ANTHONY MCDOWALL
Green Building Rough 10/2/2020 Not Ready for Inspection ANTHONY MCDOWALL
Interior/Exterior Lathing 10/2/2020 Partial Approval ANTHONY MCDOWALL
Verify Sprinkler Sign Off 10/2/2020 Not Ready for Inspection ANTHONY MCDOWALL
BUILDING-Rough-Frame 1/7/2021 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Final 1/7/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 1/7/2021 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 1/7/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/8/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/22/2021 Approved OGANES TARAKHCHYAN
Final 7/22/2021 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/22/2021 Approved OGANES TARAKHCHYAN
Green Building Final 7/22/2021 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/22/2021 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 7/22/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Smoke Detectors 7/22/2021 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 7/22/2021 Approved OGANES TARAKHCHYAN
Final 8/16/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Service/Power Release 8/16/2021 Approved OGANES TARAKHCHYAN
Final 8/25/2021 Partial Approval OGANES TARAKHCHYAN