1144 W 49TH ST 90037

Certificate Information: 1144 W 49TH ST 90037

Application / Permit
19010-20000-01222
Plan Check / Job No.
B19VN04680
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 26'-6" X 34'-7" 2-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 W/ ATTACHED 2-CAR GARAGE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/4/2020
Issuing Office
Current Status
CofO Issued on 1/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2019 APPLICANT
Assigned to Plan Check Engineer 4/4/2019 JENNIFER LEE
Green Plans Picked Up 4/5/2019 APPLICANT
Corrections Issued 4/8/2019 JENNIFER LEE
Quality Review Completed 4/9/2019 STEVEN KIM
Plan Check Approved 7/18/2019 JENNIFER LEE
Issued 6/4/2020 APPLICANT
Building Plans Picked Up 7/15/2021 APPLICANT
CofO in Progress 1/19/2022 JOAQUIN GREENOUGH
Permit Finaled 1/22/2022 DEROLD HAUFF
CofO Issued 1/22/2022 DEROLD HAUFF
Permit Finaled 1/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/19/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/19/2019 GUILLERMO PETRA
Permit Cleared 4/19/2019 GUILLERMO PETRA
Sewer availability Cleared 4/19/2019 GUILLERMO PETRA
Green Code Cleared 5/10/2019 PARISA ZAHABI
Low Impact Development Cleared 7/8/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/10/2019 ERIK BEASLEY
Hydrant and Access approval Cleared 7/12/2019 GEORGE SUCHAND
Trees in Parkway Cleared 7/17/2019 STEPHEN DUPREY

Contact Information

Contractor Stream Development Inc; Lic. No.: 1062718-B 669 N 3RD AVENUE      UPLAND, CA 91786
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 6/11/2020 Partial Inspection ROBERT MCDOWELL
Pre-Inspection 6/11/2020 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 6/17/2020 Not Ready for Inspection ROBERT MCDOWELL
Underground Mechanical 6/17/2020 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 6/19/2020 Conditional Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Partial Approval ROBERT MCDOWELL
Deputy Wood Construction 7/8/2020 No Access for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 7/8/2020 Corrections Issued JOSEPH MCGARRY
Deputy Wood Construction 7/9/2020 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 7/10/2020 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 7/14/2020 Approved ROBERT MCDOWELL
Deputy Wood Construction 7/16/2020 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 7/17/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 7/17/2020 Corrections Issued ROBERT MCDOWELL
HVAC-Rough 8/4/2020 Not Ready for Inspection ROBERT MCDOWELL
Shower Pan 8/4/2020 Approved ROBERT MCDOWELL
Green Building Rough 8/7/2020 Approved ROBERT MCDOWELL
HVAC-Rough 8/7/2020 Approved ROBERT MCDOWELL
Insulation 8/12/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 8/12/2020 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 8/18/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 8/21/2020 Conditional Approval SABAS ALONSO
Interior/Exterior Lathing 9/23/2020 Approved ROBERT MCDOWELL
Drywall Nailing 10/1/2020 Approved HORACE FULTZ
Underground Mechanical 3/15/2021 No Access for Inspection ROBERT MCDOWELL
Underground Mechanical 3/22/2021 Not Ready for Inspection ROBERT MCDOWELL
Underground Mechanical 4/7/2021 Approved ROBERT MCDOWELL
Sewer 4/13/2021 Approved FREDDIE RIVERA
ELECTRICAL-Final 4/19/2021 Not Ready for Inspection ROBERT MCDOWELL
HVAC-Final 4/19/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 4/19/2021 Not Ready for Inspection ROBERT MCDOWELL
ELECTRICAL-Final 4/27/2021 Not Ready for Inspection ROBERT MCDOWELL
HVAC-Final 4/27/2021 Not Ready for Inspection ROBERT MCDOWELL
PLUMBING-Final 4/27/2021 Not Ready for Inspection ROBERT MCDOWELL
ELECTRICAL-Final 5/5/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 5/5/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 5/7/2021 Not Ready for Inspection ROBERT MCDOWELL
BUILDING-Rough-Frame 5/18/2021 Approved ROBERT MCDOWELL
Final 5/18/2021 Conditional Approval ROBERT MCDOWELL
Footing/Foundation/Slab 5/18/2021 Approved ROBERT MCDOWELL
Green Building Final 5/18/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 5/18/2021 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 5/18/2021 Approved ROBERT MCDOWELL
Smoke Detectors 5/18/2021 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 5/18/2021 Approved ROBERT MCDOWELL
Final 11/5/2021 Not Ready for Inspection SABAS ALONSO
Final 1/12/2022 OK to Issue CofO JOAQUIN GREENOUGH