1144 W 49TH ST 90037
Certificate Information: 1144 W 49TH ST 90037
- Application / Permit
- 19010-20000-01222
- Plan Check / Job No.
- B19VN04680
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 26'-6" X 34'-7" 2-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 W/ ATTACHED 2-CAR GARAGE. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/4/2020
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2019 | JENNIFER LEE |
| Green Plans Picked Up | 4/5/2019 | APPLICANT |
| Corrections Issued | 4/8/2019 | JENNIFER LEE |
| Quality Review Completed | 4/9/2019 | STEVEN KIM |
| Plan Check Approved | 7/18/2019 | JENNIFER LEE |
| Issued | 6/4/2020 | APPLICANT |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| CofO in Progress | 1/19/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
| CofO Issued | 1/22/2022 | DEROLD HAUFF |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2019 | GUILLERMO PETRA |
| Permit | Cleared | 4/19/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/19/2019 | GUILLERMO PETRA |
| Green Code | Cleared | 5/10/2019 | PARISA ZAHABI |
| Low Impact Development | Cleared | 7/8/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/10/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 7/12/2019 | GEORGE SUCHAND |
| Trees in Parkway | Cleared | 7/17/2019 | STEPHEN DUPREY |
Contact Information
| Contractor | Stream Development Inc; Lic. No.: 1062718-B | 669 N 3RD AVENUE UPLAND, CA 91786 |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 6/11/2020 | Partial Inspection | ROBERT MCDOWELL |
| Pre-Inspection | 6/11/2020 | Approved | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 6/17/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Underground Mechanical | 6/17/2020 | Approved | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 6/19/2020 | Conditional Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2020 | Partial Approval | ROBERT MCDOWELL |
| Deputy Wood Construction | 7/8/2020 | No Access for Inspection | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2020 | Corrections Issued | JOSEPH MCGARRY |
| Deputy Wood Construction | 7/9/2020 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2020 | Approved | ROBERT MCDOWELL |
| Deputy Wood Construction | 7/16/2020 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 7/17/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 7/17/2020 | Corrections Issued | ROBERT MCDOWELL |
| HVAC-Rough | 8/4/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Shower Pan | 8/4/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 8/7/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 8/7/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 8/12/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 8/12/2020 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 8/18/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 8/21/2020 | Conditional Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 9/23/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 10/1/2020 | Approved | HORACE FULTZ |
| Underground Mechanical | 3/15/2021 | No Access for Inspection | ROBERT MCDOWELL |
| Underground Mechanical | 3/22/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Underground Mechanical | 4/7/2021 | Approved | ROBERT MCDOWELL |
| Sewer | 4/13/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/19/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Final | 4/19/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 4/19/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| ELECTRICAL-Final | 4/27/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Final | 4/27/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| PLUMBING-Final | 4/27/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| ELECTRICAL-Final | 5/5/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 5/5/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 5/7/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/18/2021 | Approved | ROBERT MCDOWELL |
| Final | 5/18/2021 | Conditional Approval | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 5/18/2021 | Approved | ROBERT MCDOWELL |
| Green Building Final | 5/18/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 5/18/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 5/18/2021 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 5/18/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 5/18/2021 | Approved | ROBERT MCDOWELL |
| Final | 11/5/2021 | Not Ready for Inspection | SABAS ALONSO |
| Final | 1/12/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |