4821 E FARQUHAR ST 90032
Certificate Information: 4821 E FARQUHAR ST 90032
- Application / Permit
- 19010-20000-01204
- Plan Check / Job No.
- B19VN04572
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (35'-0" x 35'-0") IRREGULAR SHAPED TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO-CAR GARAGE. " NFPA 13-D FIRE SPRINKLERS THRU-OUT "(SEE COMMENTS)
- Permit Issued
- Issued on 12/12/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | SARKIS HARABEDIAN |
| Corrections Issued | 5/14/2019 | SARKIS HARABEDIAN |
| Quality Review Completed | 5/15/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 5/22/2019 | APPLICANT |
| Green Plans Picked Up | 5/22/2019 | APPLICANT |
| Applicant returned to address corrections | 7/8/2019 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 7/15/2019 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 8/22/2019 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 10/4/2019 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 10/29/2019 | SARKIS HARABEDIAN |
| Plan Check Approved | 12/4/2019 | SARKIS HARABEDIAN |
| Plan Check Approved | 12/10/2019 | SARKIS HARABEDIAN |
| Issued | 12/12/2019 | LADBS |
| CofO in Progress | 12/13/2021 | COREY HUPP |
| Permit Finaled | 12/18/2021 | DEROLD HAUFF |
| CofO Issued | 12/18/2021 | DEROLD HAUFF |
| Permit Finaled | 12/18/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2019 | ELENA LOPEZ |
| BHO/Hillside ordinance | Cleared | 6/24/2019 | ELENA LOPEZ |
| BHO/Hillside ordinance | Cleared | 6/24/2019 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2019 | ELENA LOPEZ |
| Low Impact Development | Cleared | 6/24/2019 | MITESH PATEL |
| Permit | Cleared | 6/24/2019 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 6/24/2019 | ELENA LOPEZ |
| Sewer availability | Cleared | 6/25/2019 | MICHAEL CASTILLO |
| Trees in Parkway | Cleared | 7/1/2019 | JOHN KIM |
| "D" conditions | Cleared | 10/31/2019 | NICOLE SANCHEZ |
| "Q" conditions | Cleared | 10/31/2019 | NICOLE SANCHEZ |
| CPC | Cleared | 10/31/2019 | NICOLE SANCHEZ |
| Green Code | Cleared | 11/27/2019 | MICHAEL AYERS |
| BHO/Hillside ordinance | Cleared | 12/2/2019 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 12/3/2019 | JOHN CONNEALLY |
| GPI Written Notices | Cleared | 12/4/2019 | SARKIS HARABEDIAN |
| Grading Pre-Inspection | Cleared | 12/4/2019 | SARKIS HARABEDIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Jitechian,, Ara; Lic. No.: C54893 | 9433 VIA PATRICIA BURBANK, CA 91504 |
| Engineer | Wang,, Guan; Lic. No.: C79702 | 135 N SAN GABRIEL BLVD SAN GABRIEL, CA 91775 |
| Geologist | Miller,, Steven Burl; Lic. No.: EG1303 | 23890 COPPERHILL DRIVE #111 VALENCIA, CA 91354 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/20/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/31/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/30/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/8/2020 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/20/2020 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 8/19/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 9/10/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/14/2020 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 1/19/2021 | Corrections Issued | COREY HUPP |
| ELECTRICAL-Rough | 1/19/2021 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 2/22/2021 | Corrections Issued | COREY HUPP |
| ELECTRICAL-Rough | 2/22/2021 | Approved | COREY HUPP |
| HVAC-Rough | 2/22/2021 | Approved | COREY HUPP |
| PLUMBING-Rough | 2/22/2021 | Approved | COREY HUPP |
| Verify Sprinkler Sign Off | 2/22/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 3/1/2021 | Approved | COREY HUPP |
| Green Building Rough | 3/1/2021 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 3/5/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 3/16/2021 | Not Ready for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 3/16/2021 | Partial Approval | COREY HUPP |
| Drywall Nailing | 3/24/2021 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 4/1/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/6/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/15/2021 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 6/7/2021 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 6/24/2021 | Approved | OSVALDO PARAMO |
| Final | 8/31/2021 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/31/2021 | Conditional Approval | SCOTT FINNILA |
| Green Building Final | 8/31/2021 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/31/2021 | SGSOV Approved | SCOTT FINNILA |
| Service/Power Release | 8/31/2021 | Corrections Issued | SCOTT FINNILA |
| Smoke Detectors | 8/31/2021 | Approved | SCOTT FINNILA |
| Final | 9/8/2021 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/8/2021 | Approved | OSVALDO PARAMO |
| Service/Power Release | 9/8/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 9/14/2021 | Corrections Issued | COREY HUPP |
| Final | 12/8/2021 | Corrections Issued | COREY HUPP |
| Service/Power Release | 12/8/2021 | Approved | COREY HUPP |
| Final | 12/13/2021 | OK to Issue CofO | COREY HUPP |