PROPOSE 54'X70'-1" TWO STORY SFD WITH ATTACHED 2 CAR GARAGE AND ATTACHED 8'-2"X"X51' TRELLIS AT REAR_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 12/10/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2019 APPLICANT
Assigned to Plan Check Engineer 4/11/2019 DAWN MC NULTY
Corrections Issued 4/24/2019 DAWN MC NULTY
Quality Review Completed 4/24/2019 CHON CHIO KUO
Building Plans Picked Up 5/1/2019 APPLICANT
Green Plans Picked Up 5/1/2019 APPLICANT
Applicant returned to address corrections 7/23/2019 DAWN MC NULTY
Applicant returned to address corrections 7/24/2019 DAWN MC NULTY
Applicant returned to address corrections 8/2/2019 DAWN MC NULTY
Plan Check Approved 8/8/2019 DAWN MC NULTY
Issued 12/10/2019 LADBS
CofO in Progress 4/20/2021 RICHARD DOCKUS
Permit Finaled 5/28/2021 MICHAEL SMITH
CofO Issued 5/28/2021 MICHAEL SMITH
Permit Finaled 5/28/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/25/2019 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 6/25/2019 GEORGE SUCHAND
Permit Cleared 6/25/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 7/17/2019 ADRIAN SANCHEZ
Low Impact Development Cleared 7/17/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/17/2019 ADRIAN SANCHEZ
Sewer availability Cleared 7/17/2019 ADRIAN SANCHEZ
Frnt yard landscape/Water mgmt Cleared 7/18/2019 HERMINIGILDO AGUSTIN
Green Code Cleared 7/30/2019 MICHAEL AYERS

Contact Information

Contractor Landmark Construction Crew Inc; Lic. No.: 989394-B 12515 SHERMAN WAY STE A      NORTH HOLLYWOOD, CA 91605

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/24/2020 Approved GREG ALLTON
Footing/Foundation/Slab 2/3/2020 Corrections Issued WILLIAM KUEHN
Footing/Foundation/Slab 2/5/2020 Approved BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Partial Approval BRENDAN LOONEY
Deputy Steel/Welding 5/7/2020 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Approved BRENDAN LOONEY
Wood Frame 7/21/2020 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 8/10/2020 Not Ready for Inspection WILLIAM KUEHN
ELECTRICAL-Rough 8/10/2020 Not Ready for Inspection WILLIAM KUEHN
Green Building Rough 8/10/2020 Not Ready for Inspection WILLIAM KUEHN
HVAC-Rough 8/10/2020 Not Ready for Inspection WILLIAM KUEHN
PLUMBING-Rough 8/10/2020 Not Ready for Inspection WILLIAM KUEHN
Verify Sprinkler Sign Off 8/10/2020 Not Ready for Inspection WILLIAM KUEHN
Wood Frame 8/10/2020 Not Ready for Inspection WILLIAM KUEHN
ELECTRICAL-Rough 8/13/2020 Approved BRENDAN LOONEY
HVAC-Rough 8/13/2020 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 8/13/2020 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 8/13/2020 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 8/17/2020 Not Ready for Inspection BRENDAN LOONEY
Grading Pre-Inspection 8/17/2020 Partial Inspection BRENDAN LOONEY
Green Building Rough 8/17/2020 Approved BRENDAN LOONEY
HVAC-Rough 8/17/2020 Approved BRENDAN LOONEY
PLUMBING-Rough 8/17/2020 Approved BRENDAN LOONEY
Verify Sprinkler Sign Off 8/17/2020 Approved BRENDAN LOONEY
Wood Frame 8/17/2020 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 9/1/2020 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 9/22/2020 Conditional Approval BRENDAN LOONEY
Drywall Nailing 9/22/2020 Conditional Approval BRENDAN LOONEY
Interior/Exterior Lathing 10/6/2020 Partial Inspection BRENDAN LOONEY
Interior/Exterior Lathing 10/13/2020 Not Ready for Inspection BRENDAN LOONEY
Shower Pan 10/14/2020 Approved BRENDAN LOONEY
Interior/Exterior Lathing 10/20/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 1/19/2021 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 1/19/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 1/19/2021 Not Ready for Inspection BRENDAN LOONEY
Special/Order Compliance 2/3/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 3/1/2021 Not Ready for Inspection ARAM AVEDISIAN
Drywall Nailing 3/1/2021 Not Ready for Inspection ARAM AVEDISIAN
Final 3/1/2021 Not Ready for Inspection ARAM AVEDISIAN
Green Building Final 3/1/2021 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/1/2021 SGSOV Not Ready ARAM AVEDISIAN
Service/Power Release 3/1/2021 Approved ARAM AVEDISIAN
Smoke Detectors 3/1/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/5/2021 Not Ready for Inspection BRENDAN LOONEY
Drywall Nailing 3/5/2021 Not Ready for Inspection BRENDAN LOONEY
Final 3/5/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Final 3/5/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 3/5/2021 SGSOV Not Ready BRENDAN LOONEY
BUILDING-Rough-Frame 3/10/2021 Not Ready for Inspection BRENDAN LOONEY
Drywall Nailing 3/10/2021 Not Ready for Inspection BRENDAN LOONEY
Final 3/10/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 3/10/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 3/10/2021 SGSOV Not Ready BRENDAN LOONEY
BUILDING-Rough-Frame 4/12/2021 Approved RICHARD DOCKUS
Drywall Nailing 4/12/2021 Approved RICHARD DOCKUS
Final 4/12/2021 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 4/12/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 4/12/2021 SGSOV Approved RICHARD DOCKUS
Final 4/19/2021 OK to Issue CofO RICHARD DOCKUS