4710 E KLAMATH PL 90032
Certificate Information: 4710 E KLAMATH PL 90032
- Application / Permit
- 19010-20000-01135
- Plan Check / Job No.
- B19VN04290
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 29' X 40'-6" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 5/21/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2019 | SELLA BENYAMIN |
| Corrections Issued | 4/1/2019 | SELLA BENYAMIN |
| Green Plans Picked Up | 4/2/2019 | APPLICANT |
| Quality Review Completed | 4/3/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 4/4/2019 | APPLICANT |
| Plan Check Approved | 4/19/2019 | SELLA BENYAMIN |
| Issued | 5/21/2019 | LADBS |
| CofO in Progress | 10/24/2025 | LILIANA PORTILLO |
| Permit Finaled | 10/25/2025 | DEROLD HAUFF |
| CofO Issued | 10/25/2025 | DEROLD HAUFF |
| Permit Finaled | 10/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/17/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 4/17/2019 | OSCAR CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2019 | GUILLERMO PETRA |
| Hold | Cleared | 4/17/2019 | LOURDES RAMIRO |
| Hydrant and Access approval | Cleared | 4/17/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 4/17/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 4/17/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/17/2019 | GUILLERMO PETRA |
| Green Code | Cleared | 4/19/2019 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/22/2019 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 5/22/2019 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 6/25/2019 | Partial Approval | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/12/2019 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/12/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 7/12/2019 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 7/12/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/12/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/12/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/23/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/23/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 8/23/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/23/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 8/23/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/27/2019 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 8/27/2019 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/27/2019 | Approved | ENRIQUE MIRELES |
| Wood Frame | 8/27/2019 | Approved | ENRIQUE MIRELES |
| Sewer | 9/27/2019 | Approved | ENRIQUE MIRELES |
| Insulation | 11/18/2019 | No Access for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/18/2019 | No Access for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/19/2019 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/19/2019 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2019 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/19/2019 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 12/19/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 1/2/2020 | No Access for Inspection | RUBEN SALAS |
| Special/Order Compliance | 1/2/2020 | No Access for Inspection | ENRIQUE MIRELES |
| Special/Order Compliance | 1/2/2020 | No Access for Inspection | RUBEN SALAS |
| Special/Order Compliance | 1/14/2020 | Partial Inspection | RUBEN SALAS |
| ELECTRICAL-Rough | 2/4/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/4/2020 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 2/4/2020 | Partial Inspection | RUBEN SALAS |
| Rough-Elec/Plmb/HVAC | 2/26/2020 | Corrections Issued | RUBEN SALAS |
| Special/Order Compliance | 2/26/2020 | Corrections Issued | RUBEN SALAS |
| Footing/Foundation/Slab | 3/10/2020 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Rough | 3/10/2020 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 6/5/2020 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 7/7/2020 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2020 | Partial Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/7/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 7/7/2020 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/9/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/9/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/9/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/9/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/14/2020 | Corrections Issued | RUBEN SALAS |
| Verify Sprinkler Sign Off | 7/14/2020 | Approved | RUBEN SALAS |
| BUILDING-Rough-Frame | 11/5/2020 | Approved | RUBEN SALAS |
| Insulation | 2/8/2021 | Approved | RUBEN SALAS |
| Special/Order Compliance | 2/8/2021 | Approved | RUBEN SALAS |
| Service/Power Release | 2/13/2023 | No Access for Inspection | RUBEN SALAS |
| ELECTRICAL-Final | 4/13/2023 | Partial Inspection | RUBEN SALAS |
| Service/Power Release | 4/26/2023 | Not Ready for Inspection | AMY COLIN |
| Service/Power Release | 5/2/2023 | Corrections Issued | RUBEN SALAS |
| Service/Power Release | 5/2/2023 | Partial Inspection | AMY COLIN |
| Service/Power Release | 6/23/2023 | Approved | AMY COLIN |
| Final | 12/24/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 12/24/2024 | Approved | LILIANA PORTILLO |
| Green Building Final | 12/24/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 12/24/2024 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 12/24/2024 | Approved | LILIANA PORTILLO |
| Final | 7/10/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 7/10/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 7/10/2025 | SGSOV Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/12/2025 | Approved | LILIANA PORTILLO |
| Final | 8/12/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 8/12/2025 | Approved | LILIANA PORTILLO |
| HVAC-Final | 8/12/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 8/12/2025 | Approved | LILIANA PORTILLO |
| Final | 10/23/2025 | OK to Issue CofO | LILIANA PORTILLO |