4710 E KLAMATH PL 90032

Certificate Information: 4710 E KLAMATH PL 90032

Application / Permit
19010-20000-01135
Plan Check / Job No.
B19VN04290
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
29' X 40'-6" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 5/21/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2019 APPLICANT
Assigned to Plan Check Engineer 3/28/2019 SELLA BENYAMIN
Corrections Issued 4/1/2019 SELLA BENYAMIN
Green Plans Picked Up 4/2/2019 APPLICANT
Quality Review Completed 4/3/2019 OMID HEDAYAT
Building Plans Picked Up 4/4/2019 APPLICANT
Plan Check Approved 4/19/2019 SELLA BENYAMIN
Issued 5/21/2019 LADBS
CofO in Progress 10/24/2025 LILIANA PORTILLO
Permit Finaled 10/25/2025 DEROLD HAUFF
CofO Issued 10/25/2025 DEROLD HAUFF
Permit Finaled 10/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/17/2019 GUILLERMO PETRA
Construction near power lines Cleared 4/17/2019 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 4/17/2019 GUILLERMO PETRA
Hold Cleared 4/17/2019 LOURDES RAMIRO
Hydrant and Access approval Cleared 4/17/2019 GEORGE SUCHAND
Low Impact Development Cleared 4/17/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 4/17/2019 GUILLERMO PETRA
Sewer availability Cleared 4/17/2019 GUILLERMO PETRA
Green Code Cleared 4/19/2019 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/22/2019 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 5/22/2019 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/25/2019 Partial Approval ENRIQUE MIRELES
BUILDING-Rough-Frame 7/12/2019 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 7/12/2019 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 7/12/2019 Approved ENRIQUE MIRELES
HVAC-Rough 7/12/2019 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 7/12/2019 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 7/12/2019 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 8/23/2019 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 8/23/2019 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 8/23/2019 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 8/23/2019 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 8/23/2019 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 8/27/2019 Approved ENRIQUE MIRELES
HVAC-Rough 8/27/2019 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/27/2019 Approved ENRIQUE MIRELES
Wood Frame 8/27/2019 Approved ENRIQUE MIRELES
Sewer 9/27/2019 Approved ENRIQUE MIRELES
Insulation 11/18/2019 No Access for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 11/18/2019 No Access for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 12/19/2019 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 12/19/2019 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/19/2019 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/19/2019 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 12/19/2019 Not Ready for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 1/2/2020 No Access for Inspection RUBEN SALAS
Special/Order Compliance 1/2/2020 No Access for Inspection ENRIQUE MIRELES
Special/Order Compliance 1/2/2020 No Access for Inspection RUBEN SALAS
Special/Order Compliance 1/14/2020 Partial Inspection RUBEN SALAS
ELECTRICAL-Rough 2/4/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/4/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 2/4/2020 Approved ENRIQUE MIRELES
Special/Order Compliance 2/4/2020 Partial Inspection RUBEN SALAS
Rough-Elec/Plmb/HVAC 2/26/2020 Corrections Issued RUBEN SALAS
Special/Order Compliance 2/26/2020 Corrections Issued RUBEN SALAS
Footing/Foundation/Slab 3/10/2020 Corrections Issued RUBEN SALAS
PLUMBING-Rough 3/10/2020 Partial Approval RUBEN SALAS
Footing/Foundation/Slab 6/5/2020 Partial Approval RUBEN SALAS
ELECTRICAL-Rough 7/7/2020 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 7/7/2020 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 7/7/2020 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 7/9/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 7/9/2020 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/9/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 7/9/2020 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 7/9/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 7/14/2020 Corrections Issued RUBEN SALAS
Verify Sprinkler Sign Off 7/14/2020 Approved RUBEN SALAS
BUILDING-Rough-Frame 11/5/2020 Approved RUBEN SALAS
Insulation 2/8/2021 Approved RUBEN SALAS
Special/Order Compliance 2/8/2021 Approved RUBEN SALAS
Service/Power Release 2/13/2023 No Access for Inspection RUBEN SALAS
ELECTRICAL-Final 4/13/2023 Partial Inspection RUBEN SALAS
Service/Power Release 4/26/2023 Not Ready for Inspection AMY COLIN
Service/Power Release 5/2/2023 Corrections Issued RUBEN SALAS
Service/Power Release 5/2/2023 Partial Inspection AMY COLIN
Service/Power Release 6/23/2023 Approved AMY COLIN
Final 12/24/2024 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 12/24/2024 Approved LILIANA PORTILLO
Green Building Final 12/24/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/24/2024 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 12/24/2024 Approved LILIANA PORTILLO
Final 7/10/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 7/10/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 7/10/2025 SGSOV Approved LILIANA PORTILLO
ELECTRICAL-Final 8/12/2025 Approved LILIANA PORTILLO
Final 8/12/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 8/12/2025 Approved LILIANA PORTILLO
HVAC-Final 8/12/2025 Approved LILIANA PORTILLO
PLUMBING-Final 8/12/2025 Approved LILIANA PORTILLO
Final 10/23/2025 OK to Issue CofO LILIANA PORTILLO