14525 W RYAN ST 91342
Certificate Information: 14525 W RYAN ST 91342
- Application / Permit
- 19010-20000-01032
- Plan Check / Job No.
- B19VN03879
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 22' 1" X 54' 1" 1-STORY ACCESSORY DWELLING UNIT WITH ATTACHED 4' 5" X 9' PER AB 494 & SB 229. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 2/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2019 | GURUNATH NESARAJAH |
| Corrections Issued | 4/15/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 4/15/2019 | OMID HEDAYAT |
| Green Plans Picked Up | 4/17/2019 | APPLICANT |
| Building Plans Picked Up | 4/19/2019 | APPLICANT |
| Plan Check Approved | 1/10/2020 | GURUNATH NESARAJAH |
| Issued | 2/20/2020 | LADBS |
| CofO in Progress | 3/10/2023 | ARAM AVEDISIAN |
| CofO Issued | 3/28/2023 | MICHAEL SMITH |
| Permit Finaled | 3/28/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| ZI | Cleared | 5/3/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 8/13/2019 | MARC WOERSCHING |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2019 | JOSHUA DIAZ |
| Sewer availability | Cleared | 8/27/2019 | APEKSHYA BAJRACHARYA |
| Address approval | Cleared | 9/25/2019 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 12/12/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 1/2/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 1/3/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/9/2020 | APEKSHYA BAJRACHARYA |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/24/2020 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/24/2020 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 9/24/2020 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/15/2020 | Partial Approval | MISAEL ESPARZA |
| Pre-Inspection | 3/8/2021 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 4/6/2021 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 4/13/2021 | Approved | MISAEL ESPARZA |
| Deputy Wood Construction | 4/13/2021 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/15/2021 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/26/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/26/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 7/26/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 7/26/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 7/26/2021 | Partial Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 7/26/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 8/2/2021 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 8/2/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 8/2/2021 | Partial Approval | MISAEL ESPARZA |
| Gas Test | 8/27/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/17/2021 | No Access for Inspection | JOHN HAYES |
| Green Building Rough | 9/17/2021 | No Access for Inspection | JOHN HAYES |
| PLUMBING-Rough | 9/17/2021 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/21/2021 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 9/21/2021 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 9/21/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/14/2021 | Approved | JOHN HAYES |
| Green Building Rough | 10/14/2021 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 10/14/2021 | Approved | JOHN HAYES |
| Insulation | 10/25/2021 | Approved | JOHN HAYES |
| Drywall Nailing | 11/15/2021 | Approved | JOHN HAYES |
| Shower Pan | 5/23/2022 | Approved | JOHN HAYES |
| Final | 11/3/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 11/3/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 11/3/2022 | Approved | ARAM AVEDISIAN |
| Final | 11/18/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 11/18/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 3/10/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 3/10/2023 | Approved | ARAM AVEDISIAN |