14523 W RYAN ST 91342
Certificate Information: 14523 W RYAN ST 91342
- Application / Permit
- 19010-20000-01031
- Plan Check / Job No.
- B19VN03879
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 53' 11" X 75' 5" IRR.-SHAPE SINGLE FAMILY DWELLING WITH ATTACHED 22' 11" X 21' ATTACHED 2-CAR GARAGE, 27' X 11' IRR.-SHAPE FRONT PORCH AND 9' 2" 20' 3" REAR PATIO COVER. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 2/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2019 | GURUNATH NESARAJAH |
| Corrections Issued | 4/15/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 4/15/2019 | OMID HEDAYAT |
| Green Plans Picked Up | 4/17/2019 | APPLICANT |
| Building Plans Picked Up | 4/19/2019 | APPLICANT |
| Plan Check Approved | 1/10/2020 | GURUNATH NESARAJAH |
| Issued | 2/20/2020 | LADBS |
| CofO in Progress | 9/23/2022 | ARAM AVEDISIAN |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
| CofO Issued | 10/22/2022 | MICHAEL SMITH |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Permit | Cleared | 5/3/2019 | JOHN LIN |
| ZI | Cleared | 5/3/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 8/13/2019 | MARC WOERSCHING |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2019 | JOSHUA DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2019 | JOSHUA DIAZ |
| Sewer availability | Cleared | 8/27/2019 | APEKSHYA BAJRACHARYA |
| Address approval | Cleared | 12/12/2019 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 12/12/2019 | GEORGE SUCHAND |
| Trees in Parkway | Cleared | 12/28/2019 | JOHN KIM |
| Green Code | Cleared | 1/2/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 1/3/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/9/2020 | MARKOS PEREZ-BRAN |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/22/2020 | Approved | GREGG CUMMINGS |
| Special/Order Compliance | 6/22/2020 | Partial Inspection | PIERRE VEGA |
| PLUMBING-Rough | 9/21/2020 | Partial Approval | MISAEL ESPARZA |
| Sewer | 9/21/2020 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 9/25/2020 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/25/2020 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 10/1/2020 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/15/2020 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/10/2020 | Partial Approval | MISAEL ESPARZA |
| Pre-Inspection | 3/8/2021 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 4/6/2021 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 4/13/2021 | Approved | MISAEL ESPARZA |
| Deputy Wood Construction | 4/13/2021 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/14/2021 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/26/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/26/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/26/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 7/26/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 7/26/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 7/26/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 8/2/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 8/2/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/24/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 8/24/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 8/24/2021 | Approved | MISAEL ESPARZA |
| Service/Power Release | 8/24/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 9/7/2021 | Approved | MISAEL ESPARZA |
| Special/Order Compliance | 9/7/2021 | Partial Inspection | JUSTIN HAWLEY |
| Drywall Nailing | 9/16/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 9/16/2021 | Partial Approval | ADAM ESCOTO |
| PLUMBING-Rough | 11/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 11/19/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/30/2021 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Shower Pan | 11/30/2021 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 12/27/2021 | Approved | JOHN HAYES |
| Sewer | 4/15/2022 | Partial Approval | JOHN HAYES |
| Final | 8/18/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 8/18/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 8/18/2022 | Approved | ARAM AVEDISIAN |
| Final | 9/6/2022 | Partial Inspection | ARAM AVEDISIAN |
| Final | 9/23/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 9/23/2022 | Approved | ARAM AVEDISIAN |