7718 N AMPERE AVE 91605
Certificate Information: 7718 N AMPERE AVE 91605
- Application / Permit
- 19010-20000-00916
- Plan Check / Job No.
- B19VN03351
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE TWO STORY 25'X25'-6" ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 6/3/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2019 | DAWN MC NULTY |
| Corrections Issued | 4/9/2019 | DAWN MC NULTY |
| Quality Review Completed | 4/9/2019 | STEVEN KIM |
| Green Plans Picked Up | 4/10/2019 | APPLICANT |
| Applicant returned to address corrections | 2/12/2020 | DAWN MC NULTY |
| Plan Check Approved | 2/20/2020 | DAWN MC NULTY |
| Issued | 6/3/2020 | LADBS |
| Building Plans Picked Up | 6/4/2020 | APPLICANT |
| CofO in Progress | 1/11/2022 | GREGG CUMMINGS |
| No Progress | 5/18/2022 | DAVID MATSON |
| CofO in Progress | 5/18/2022 | DAVID MATSON |
| CofO in Progress | 6/8/2022 | DAVID MATSON |
| CofO Issued | 6/8/2022 | MICHAEL SMITH |
| Permit Finaled | 6/8/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/22/2019 | RIDWAN HARDY |
| "T" removal | Cleared | 10/29/2019 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 10/29/2019 | ANDRES COVARRUBIAS |
| Miscellaneous | Cleared | 10/29/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 10/29/2019 | STEVEN WECHSLER |
| Tract Map conditions | Cleared | 10/29/2019 | STEVEN WECHSLER |
| Tract Map conditions | Cleared | 10/29/2019 | STEVEN WECHSLER |
| Address approval | Cleared | 11/15/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2019 | JOHN LIN |
| Permit | Cleared | 11/15/2019 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 11/15/2019 | JOHN LIN |
| Sewer availability | Cleared | 11/15/2019 | JOHN LIN |
| Hydrant and Access approval | Cleared | 11/20/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 11/21/2019 | DAWN MC NULTY |
| Trees in Parkway | Cleared | 2/14/2020 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/19/2020 | Corrections Issued | GREGG CUMMINGS |
| Special/Order Compliance | 8/19/2020 | Approved | PIERRE VEGA |
| Footing/Foundation/Slab | 8/25/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 9/15/2020 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 9/22/2020 | Partial Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 9/22/2020 | Partial Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 9/23/2020 | No Access for Inspection | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2020 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 10/9/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2020 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 11/16/2020 | Approved | GREGG CUMMINGS |
| Wood Frame | 11/17/2020 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 11/23/2020 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 12/4/2020 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 12/4/2020 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/8/2020 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 12/8/2020 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/17/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 12/17/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 12/17/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/28/2020 | Approved | GREGG CUMMINGS |
| Green Building Rough | 12/28/2020 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 12/28/2020 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/5/2021 | Partial Approval | JOHN HAYES |
| Insulation | 1/6/2021 | Approved | GREGG CUMMINGS |
| Shower Pan | 1/14/2021 | Approved | DAVID MATSON |
| Drywall Nailing | 1/20/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 3/30/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 4/16/2021 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/14/2021 | Partial Inspection | GREGG CUMMINGS |
| Final | 12/13/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 12/13/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/13/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 12/13/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 12/13/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 1/7/2022 | Approved | JENNIFER RABUCHIN |
| Final | 1/7/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Final | 1/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/7/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/7/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/7/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 1/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/11/2022 | Conditional Approval | GREGG CUMMINGS |
| HVAC-Final | 1/11/2022 | Approved | GREGG CUMMINGS |
| Service/Power Release | 1/11/2022 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 1/11/2022 | Approved | GREGG CUMMINGS |
| Final | 5/18/2022 | Corrections Issued | DAVID MATSON |