15902 W ROXFORD ST 91342

Certificate Information: 15902 W ROXFORD ST 91342

Application / Permit
19010-20000-00826
Plan Check / Job No.
B19VN03107
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'-0" x 30'-0" TWO STORY DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED 5'-0" x 10'-0" PORCH.
Permit Issued
Issued on 8/26/2020
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2019 APPLICANT
Assigned to Plan Check Engineer 3/21/2019 SARKIS HARABEDIAN
Corrections Issued 3/27/2019 SARKIS HARABEDIAN
Quality Review Completed 3/28/2019 OMID HEDAYAT
Building Plans Picked Up 4/11/2019 APPLICANT
Green Plans Picked Up 4/11/2019 APPLICANT
Applicant returned to address corrections 6/11/2020 SARKIS HARABEDIAN
Plan Check Approved 8/26/2020 SARKIS HARABEDIAN
Issued 8/26/2020 APPLICANT
CofO in Progress 9/16/2022 ARAM AVEDISIAN
CofO Issued 10/15/2022 MICHAEL SMITH
Permit Finaled 10/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/8/2019 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 5/8/2019 SAFA JAVANMARDI
Hydrant and Access approval Cleared 2/27/2020 GEORGE SUCHAND
Low Impact Development Cleared 2/27/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 2/27/2020 APEKSHYA BAJRACHARYA
Green Code Cleared 4/16/2020 MICHAEL AYERS
GPI Written Notices Cleared 6/12/2020 SARKIS HARABEDIAN
Grading Pre-Inspection Cleared 6/12/2020 SARKIS HARABEDIAN
Private sewage disp. approval Cleared 6/12/2020 DAN RYAN EVANGELISTA

Contact Information

Contractor Owner-Builder       ,
Engineer Stewart,, Carl William; Lic. No.: C86681 8811 GENTLE WIND DR      CORONA, CA 92883

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/16/2020 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 2/10/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 3/1/2021 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 5/11/2021 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 5/11/2021 No Access for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 5/11/2021 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Partial Approval MISAEL ESPARZA
Green Building Rough 5/18/2021 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 5/18/2021 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 5/18/2021 Not Ready for Inspection MISAEL ESPARZA
Pre-Inspection 5/25/2021 Approved MISAEL ESPARZA
Pre-Inspection 5/25/2021 Partial Inspection MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 6/23/2021 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 7/26/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 7/26/2021 Partial Approval MICHEL ABAJAN
HVAC-Rough 8/6/2021 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 8/6/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/7/2021 Partial Approval MISAEL ESPARZA
Green Building Rough 9/7/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/7/2021 Partial Approval MISAEL ESPARZA
MERV13>=Rough 9/7/2021 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 9/7/2021 Approved MISAEL ESPARZA
Insulation 9/15/2021 Approved MICHEL ABAJAN
Drywall Nailing 9/30/2021 Corrections Issued JOHN HAYES
Special/Order Compliance 10/6/2021 Corrections Issued JOHN HAYES
Interior/Exterior Lathing 10/15/2021 Approved JOHN HAYES
Underground Mechanical 10/15/2021 Approved JOHN HAYES
Gas Test 11/24/2021 Approved JESUS RODRIGUEZ
Underground Mechanical 11/24/2021 Approved JESUS RODRIGUEZ
Final 2/2/2022 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 5/25/2022 Not Ready for Inspection JOHN HAYES
Drywall Nailing 5/25/2022 Not Ready for Inspection JOHN HAYES
Final 5/25/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 5/25/2022 Not Ready for Inspection JOHN HAYES
Green Building Final 5/25/2022 Not Ready for Inspection JOHN HAYES
MERV13>=Final 5/25/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/25/2022 SGSOV Not Ready JOHN HAYES
Service/Power Release 5/25/2022 Not Ready for Inspection JOHN HAYES
Smoke Detectors 5/25/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 9/16/2022 Approved ARAM AVEDISIAN
Drywall Nailing 9/16/2022 Approved ARAM AVEDISIAN
Final 9/16/2022 OK to Issue CofO ARAM AVEDISIAN
Footing/Foundation/Slab 9/16/2022 Approved ARAM AVEDISIAN
Green Building Final 9/16/2022 Approved ARAM AVEDISIAN
MERV13>=Final 9/16/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 9/16/2022 Approved ARAM AVEDISIAN
Smoke Detectors 9/16/2022 Approved ARAM AVEDISIAN