18231 W ERWIN ST 91335
Certificate Information: 18231 W ERWIN ST 91335
- Application / Permit
- 19010-20000-00802
- Plan Check / Job No.
- B19VN02988
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 26'-0" X 27'-2" DETACHED 2-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/11/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2019 | JENNIFER LEE |
| Corrections Issued | 3/11/2019 | JENNIFER LEE |
| Quality Review Completed | 3/12/2019 | STEVEN KIM |
| Building Plans Picked Up | 3/12/2019 | APPLICANT |
| Green Plans Picked Up | 3/12/2019 | APPLICANT |
| Plan Check Approved | 3/9/2020 | JENNIFER LEE |
| Issued | 3/11/2020 | LADBS |
| CofO in Progress | 11/9/2021 | SEAN HAUPT |
| Permit Finaled | 11/22/2021 | MICHAEL SMITH |
| CofO Issued | 11/22/2021 | MICHAEL SMITH |
| Permit Finaled | 11/22/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| "T" removal | Cleared | 3/12/2019 | HERMINIGILDO AGUSTIN |
| Tract Map conditions | Cleared | 3/12/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 3/12/2019 | HERMINIGILDO AGUSTIN |
| Address approval | Cleared | 3/13/2019 | ISRAEL TAMIRU |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2019 | ISRAEL TAMIRU |
| Sewer availability | Cleared | 3/21/2019 | ISRAEL TAMIRU |
| Hydrant and Access approval | Cleared | 3/22/2019 | JOHN DALLAS |
| Low Impact Development | Cleared | 4/2/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/2/2019 | ARMEN SARKISIAN |
| Green Code | Cleared | 4/4/2019 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/29/2020 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 5/5/2020 | Corrections Issued | STEVEN BACK |
| Underground Mechanical | 5/5/2020 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 5/7/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2020 | Partial Approval | STEVEN BACK |
| Green Building Rough | 5/21/2020 | Not Ready for Inspection | STEVEN BACK |
| Verify Sprinkler Sign Off | 5/21/2020 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 6/15/2020 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 6/15/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2020 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 6/15/2020 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 6/15/2020 | Approved | STEVEN BACK |
| PLUMBING-Rough | 6/15/2020 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 6/15/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 6/17/2020 | Approved | STEVEN BACK |
| Deputy Wood Construction | 6/17/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2020 | Approved | STEVEN BACK |
| Green Building Rough | 6/17/2020 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 6/22/2020 | Partial Approval | STEVEN BACK |
| Green Building Rough | 6/23/2020 | Approved | STEVEN BACK |
| Insulation | 6/25/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 7/6/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/6/2020 | Approved | STEVEN BACK |
| Shower Pan | 7/6/2020 | Approved | STEVEN BACK |
| Gas Test | 7/23/2020 | Partial Approval | STEVEN BACK |
| Sewer | 7/23/2020 | Corrections Issued | STEVEN BACK |
| Underground Mechanical | 7/23/2020 | Corrections Issued | STEVEN BACK |
| Underground Mechanical | 7/28/2020 | Corrections Issued | STEVEN BACK |
| Sewer | 7/30/2020 | Approved | STEVEN BACK |
| Underground Mechanical | 7/30/2020 | Approved | STEVEN BACK |
| Final | 9/28/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 9/28/2021 | Approved | STEVEN BACK |
| Green Building Final | 9/28/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Not Ready | STEVEN BACK |
| Service/Power Release | 9/28/2021 | Corrections Issued | STEVEN BACK |
| Smoke Detectors | 9/28/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 10/14/2021 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 10/14/2021 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 10/14/2021 | Approved | SEAN HAUPT |
| Smoke Detectors | 10/14/2021 | Approved | SEAN HAUPT |