Excavation/Setback/Form/Re-Bar
|
4/6/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
4/15/2022
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
4/20/2022
|
Approved
|
JOHN KITCKO
|
|
Deputy Shotcrete
|
4/21/2022
|
Approved
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
4/21/2022
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Shotcrete
|
4/22/2022
|
Approved
|
JOHN KITCKO
|
|
Deputy Shotcrete
|
4/25/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
4/26/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
4/27/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
4/28/2022
|
Approved
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
4/28/2022
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
4/29/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Footing/Foundation/Slab
|
5/23/2022
|
Corrections Issued
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
5/24/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
SGSOV-Seismic Gas S/O Valve
|
5/24/2022
|
SGSOV Approved
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
7/5/2022
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
7/7/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
7/11/2022
|
Approved
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
7/11/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
7/25/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
7/27/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
7/28/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/28/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Deputy Wood Construction
|
8/1/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
8/15/2022
|
Approved
|
JOHN KITCKO
|
|
Green Building Rough
|
8/15/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
8/15/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
8/15/2022
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Wood Construction
|
8/25/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Insulation
|
9/7/2022
|
Partial Approval
|
DANIEL VARNUM
|
|
Deputy Wood Construction
|
9/19/2022
|
Conditional Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/22/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Green Building Rough
|
9/22/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Verify Sprinkler Sign Off
|
9/22/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Deputy Wood Construction
|
9/23/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/16/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/17/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Insulation
|
12/6/2022
|
Partial Approval
|
KENNETH ROBERTS
|
|
Insulation
|
12/9/2022
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Insulation
|
12/12/2022
|
Partial Inspection
|
JEFFREY FULTON
|
|
Deputy Wood Construction
|
12/13/2022
|
Conditional Approval
|
DEANDRE HOFFMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/13/2022
|
Partial Approval
|
DEANDRE HOFFMAN
|
|
Drywall Nailing
|
12/16/2022
|
Partial Approval
|
DANIEL VARNUM
|
|
Green Building Rough
|
12/16/2022
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Insulation
|
12/16/2022
|
Partial Approval
|
DANIEL VARNUM
|
|
Deputy Wood Construction
|
1/12/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Drywall Nailing
|
1/12/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/12/2023
|
Partial Inspection
|
CAMERON CHABAN
|
|
Green Building Rough
|
1/12/2023
|
Partial Inspection
|
CAMERON CHABAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/24/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
1/27/2023
|
Partial Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/3/2023
|
Partial Inspection
|
CAMERON CHABAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/6/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Green Building Rough
|
2/24/2023
|
Approved
|
CAMERON CHABAN
|
|
Wood Frame
|
2/24/2023
|
Partial Approval
|
CAMERON CHABAN
|
|
Insulation
|
3/3/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
3/7/2023
|
Partial Approval
|
CAMERON CHABAN
|
|
Insulation
|
3/8/2023
|
Partial Approval
|
CAMERON CHABAN
|
|
Wood Frame
|
3/15/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Drywall Nailing
|
3/16/2023
|
Partial Approval
|
CAMERON CHABAN
|
|
Insulation
|
3/16/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Verify Sprinkler Sign Off
|
3/16/2023
|
Approved
|
CAMERON CHABAN
|
|
Insulation
|
3/20/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
3/20/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
3/23/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
3/29/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Special/Order Compliance
|
3/29/2023
|
No Access for Inspection
|
STEVEN LEVITT
|
|
Interior/Exterior Lathing
|
3/31/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Special/Order Compliance
|
3/31/2023
|
Approved
|
STEVEN LEVITT
|
|
Interior/Exterior Lathing
|
4/5/2023
|
Partial Approval
|
CAMERON CHABAN
|
|
Drywall Nailing
|
4/7/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
4/7/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
4/18/2023
|
Partial Approval
|
CAMERON CHABAN
|
|
Interior/Exterior Lathing
|
5/9/2023
|
Partial Approval
|
CAMERON CHABAN
|
|
Drywall Nailing
|
5/10/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Special/Order Compliance
|
6/1/2023
|
Conditional Approval
|
STEVEN LEVITT
|
|
Special/Order Compliance
|
6/1/2023
|
Partial Inspection
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
7/27/2023
|
Partial Approval
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
7/27/2023
|
Partial Inspection
|
CAMERON CHABAN
|
|
Masonry Wall/Backfill
|
8/2/2023
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Reinforced Masonry Frame
|
8/2/2023
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Masonry Wall/Backfill
|
8/4/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Reinforced Masonry Frame
|
8/4/2023
|
Partial Inspection
|
CAMERON CHABAN
|
|
Drywall Nailing
|
9/11/2023
|
Partial Approval
|
STEVEN LEVITT
|
|
Light Gage Steel Frame
|
12/5/2023
|
Approved
|
CAMERON CHABAN
|
|
Drywall Nailing
|
12/6/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
1/17/2024
|
Partial Approval
|
STEVEN LEVITT
|
|
Drywall Nailing
|
4/12/2024
|
Approved
|
ROBERT DAVIS
|
|
Final
|
4/12/2024
|
Corrections Issued
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
4/12/2024
|
Approved
|
ROBERT DAVIS
|
|
Green Building Final
|
4/12/2024
|
Approved
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
4/12/2024
|
Approved
|
ROBERT DAVIS
|
|
Smoke Detectors
|
4/12/2024
|
Approved
|
ROBERT DAVIS
|
|
Wood Frame
|
4/12/2024
|
Approved
|
ROBERT DAVIS
|
|
Final
|
4/17/2024
|
OK to Issue CofO
|
ROBERT DAVIS
|
|
Final
|
4/19/2024
|
Partial Inspection
|
GREGORY POMISH
|