4818 N SEPULVEDA BLVD 91403

Certificate Information: 4818 N SEPULVEDA BLVD 91403

Application / Permit
19010-20000-00795
Plan Check / Job No.
B19VN02946
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 36 UNIT 4-STORY APT WITH PARKING ON GRADE, with 35% density bonus, & replace 30% auto parking with bicycle parking per Ord182386, with 11% of 36 unit , 4 very low income units; "COMPLY WITH DEPARTMENT ORDER effective date 06/11/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/4/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2019 APPLICANT
Assigned to Plan Check Engineer 3/7/2019 CHON CHIO KUO
Disabled Access Plans Picked Up 3/7/2019 APPLICANT
Green Plans Picked Up 3/7/2019 APPLICANT
Corrections Issued 3/11/2019 CHON CHIO KUO
Quality Review Completed 3/13/2019 STEVEN KIM
Building Plans Picked Up 3/15/2019 APPLICANT
Applicant returned to address corrections 6/20/2019 CHON CHIO KUO
Applicant returned to address corrections 7/30/2019 CHON CHIO KUO
Applicant returned to address corrections 10/22/2019 CHON CHIO KUO
Applicant returned to address corrections 4/13/2020 CHON CHIO KUO
Applicant returned to address corrections 5/5/2020 CHON CHIO KUO
Applicant returned to address corrections 10/26/2020 CHON CHIO KUO
Applicant returned to address corrections 12/7/2020 CHON CHIO KUO
Applicant returned to address corrections 12/21/2021 SEAN SHAHMIRI
Plan Check Approved 3/14/2022 SEAN SHAHMIRI
Plan Check Approved 3/17/2022 RARES BODEA
Issued 4/4/2022 APPLICANT
CofO in Progress 4/24/2024 ROBERT DAVIS
CofO Issued 4/30/2024 RICKEY JACKSON
Permit Finaled 4/30/2024 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 4/25/2019 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 5/14/2019 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 5/22/2019 GEORGE SUCHAND
Trees in Parkway Cleared 5/28/2019 JOHN KIM
Sewer availability Cleared 7/3/2019 ELENA LOPEZ
Low Impact Development Cleared 7/17/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/17/2019 ADRIAN SANCHEZ
Building over 3-story or 36-ft Cleared 7/30/2019 CALOSHA APPROVED
Green Code Cleared 8/20/2019 MICHAEL AYERS
Highway dedication Cleared 1/27/2020 JOHN TRIANTAFYLLOS
Fire Marshall Fire Life Safety Cleared 12/1/2020 WILLIAM JOHNS
Permit Cleared 5/10/2021 GABRIEL ROBLES
DAS Clearance Cleared 6/8/2021 NORLITO MEDRANO
Density Bonus 12.22.A.25 Cleared 6/30/2021 MICHAEL ZIRBES
Frnt yard landscape/Water mgmt Cleared 8/25/2021 PABLO ESTRADA
Opn space landscape/Water mgmt Cleared 8/25/2021 PABLO ESTRADA
Disturb/Remove Protected Trees Cleared 12/9/2021 STEPHEN DUPREY
Density Bonus 12.22.A.25 Cleared 3/10/2022 RICHARD TRUONG

Contact Information

Contractor M L N Builders Inc; Lic. No.: 1054900-B 7234 BELLAIRE AVE      NORTH HOLLYWOOD, CA 91605
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Jitechian,, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/6/2022 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/15/2022 Partial Approval JEFFREY DURAN
Deputy Shotcrete 4/20/2022 Approved JOHN KITCKO
Deputy Shotcrete 4/21/2022 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 4/21/2022 Partial Approval JOHN KITCKO
Deputy Shotcrete 4/22/2022 Approved JOHN KITCKO
Deputy Shotcrete 4/25/2022 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/26/2022 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/27/2022 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/28/2022 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/28/2022 Partial Approval JEFFREY DURAN
Deputy Shotcrete 4/29/2022 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 5/23/2022 Corrections Issued JOHN KITCKO
Deputy Reinf. Concrete 5/24/2022 Conditional Approval JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 5/24/2022 SGSOV Approved JOHN KITCKO
Footing/Foundation/Slab 7/5/2022 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 7/7/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/11/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 7/11/2022 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 7/25/2022 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 7/27/2022 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 7/28/2022 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Partial Approval CAMERON CHABAN
Deputy Wood Construction 8/1/2022 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 8/15/2022 Approved JOHN KITCKO
Green Building Rough 8/15/2022 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 8/15/2022 Not Ready for Inspection JOHN KITCKO
Wood Frame 8/15/2022 Partial Approval JOHN KITCKO
Deputy Wood Construction 8/25/2022 Conditional Approval JEFFREY DURAN
Insulation 9/7/2022 Partial Approval DANIEL VARNUM
Deputy Wood Construction 9/19/2022 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/22/2022 Conditional Approval CAMERON CHABAN
Green Building Rough 9/22/2022 Partial Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 9/22/2022 Partial Inspection CAMERON CHABAN
Deputy Wood Construction 9/23/2022 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Partial Approval CAMERON CHABAN
Insulation 12/6/2022 Partial Approval KENNETH ROBERTS
Insulation 12/9/2022 Partial Inspection DEANDRE HOFFMAN
Insulation 12/12/2022 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 12/13/2022 Conditional Approval DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 12/16/2022 Partial Approval DANIEL VARNUM
Green Building Rough 12/16/2022 Not Ready for Inspection DANIEL VARNUM
Insulation 12/16/2022 Partial Approval DANIEL VARNUM
Deputy Wood Construction 1/12/2023 Conditional Approval CAMERON CHABAN
Drywall Nailing 1/12/2023 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Partial Inspection CAMERON CHABAN
Green Building Rough 1/12/2023 Partial Inspection CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Partial Inspection JEFFREY FULTON
Insulation 1/27/2023 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Partial Inspection CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Conditional Approval CAMERON CHABAN
Green Building Rough 2/24/2023 Approved CAMERON CHABAN
Wood Frame 2/24/2023 Partial Approval CAMERON CHABAN
Insulation 3/3/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/7/2023 Partial Approval CAMERON CHABAN
Insulation 3/8/2023 Partial Approval CAMERON CHABAN
Wood Frame 3/15/2023 Conditional Approval CAMERON CHABAN
Drywall Nailing 3/16/2023 Partial Approval CAMERON CHABAN
Insulation 3/16/2023 Conditional Approval CAMERON CHABAN
Verify Sprinkler Sign Off 3/16/2023 Approved CAMERON CHABAN
Insulation 3/20/2023 Partial Inspection JEFFREY FULTON
Wood Frame 3/20/2023 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 3/23/2023 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 3/29/2023 Partial Approval ROBERT DAVIS
Special/Order Compliance 3/29/2023 No Access for Inspection STEVEN LEVITT
Interior/Exterior Lathing 3/31/2023 Conditional Approval CAMERON CHABAN
Special/Order Compliance 3/31/2023 Approved STEVEN LEVITT
Interior/Exterior Lathing 4/5/2023 Partial Approval CAMERON CHABAN
Drywall Nailing 4/7/2023 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 4/7/2023 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 4/18/2023 Partial Approval CAMERON CHABAN
Interior/Exterior Lathing 5/9/2023 Partial Approval CAMERON CHABAN
Drywall Nailing 5/10/2023 Partial Inspection ANDREW DORSO
Special/Order Compliance 6/1/2023 Conditional Approval STEVEN LEVITT
Special/Order Compliance 6/1/2023 Partial Inspection CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 7/27/2023 Partial Approval CAMERON CHABAN
Footing/Foundation/Slab 7/27/2023 Partial Inspection CAMERON CHABAN
Masonry Wall/Backfill 8/2/2023 Not Ready for Inspection CAMERON CHABAN
Reinforced Masonry Frame 8/2/2023 Not Ready for Inspection CAMERON CHABAN
Masonry Wall/Backfill 8/4/2023 Conditional Approval CAMERON CHABAN
Reinforced Masonry Frame 8/4/2023 Partial Inspection CAMERON CHABAN
Drywall Nailing 9/11/2023 Partial Approval STEVEN LEVITT
Light Gage Steel Frame 12/5/2023 Approved CAMERON CHABAN
Drywall Nailing 12/6/2023 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 1/17/2024 Partial Approval STEVEN LEVITT
Drywall Nailing 4/12/2024 Approved ROBERT DAVIS
Final 4/12/2024 Corrections Issued ROBERT DAVIS
Footing/Foundation/Slab 4/12/2024 Approved ROBERT DAVIS
Green Building Final 4/12/2024 Approved ROBERT DAVIS
Reinforced Concrete Frame 4/12/2024 Approved ROBERT DAVIS
Smoke Detectors 4/12/2024 Approved ROBERT DAVIS
Wood Frame 4/12/2024 Approved ROBERT DAVIS
Final 4/17/2024 OK to Issue CofO ROBERT DAVIS
Final 4/19/2024 Partial Inspection GREGORY POMISH